Lecture 12. Risk Management Flashcards

1
Q

What is risk?

A

Combination of the chance of an event happening and the outcome should such event occur.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is greatest uncertainty?

A

Start of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Through what duration should risk management be taken out during a project?

A

Throughout.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When will risk management have most effect?

A

At the start of a project. (early on)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the most important time to apply risk management?

A

at the ‘project sanction’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The steps for managing risks?

A

Identification
Analysis
Response

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the steps of analysing risks?

A

Evaluation of individual risks, evaluation of risks all together.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What must be determined for individual risks?

A
  • Chance of occurrence

- Effect of occurrence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Process to deal with overall project risks?

A
  • PERT (old technique)
  • MonteCarlo Simulation (new tech)
  • Experience
  • (4 x most likely + optimistic + pessimistic)/6
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How does the practical method work?

A

Making a decision on how to act and taking some action.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Process from risk management?

A
Typical responses
Investigate further
Avoid (change design, construction method)
Share
Insure (CAR)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Method for risk management?

A
  1. id
  2. access the vulnerability of critical assets to specific threats
  3. determine the risk (likelihood, consequences etc)
  4. was to reduce risk
  5. prioritise risk reduction measures based on strategy.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who will assess the risk?

A

Project manager with input from project team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is high probability of occurrence?

A

Greater than 70%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is medium probability of occurrence?

A

Between 30 and 70%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is low probability of occurrence?

A

Below 30%

17
Q

What happens to risks that fall within the red or yellow zone?

A

Response planning, risk migration and/or risk contingency plan.

18
Q

What happens to each risk in terms of quantitative analysis?

A

Their effect eliminated and a numerical rating applied to each risk then documented in the risk management plan.

19
Q

Risk migration?

A

??