Lecture 10. Cost Estimating II Flashcards

1
Q

What are the types of construction estimates?

A
  • Degree of project definition.
  • End usage of estimate
  • Estimate generating methodology
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the conceptual estimate?

A

Average cost per standard unit. (# of beds in hotel, cars in car park, students in uni) (i dont get it?)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are examples of cost indices?

A
  • General building (commercial buildings, offices, stores etc)
  • Manufacturing (assembly, electronic assembly etc)
  • Power (thermal and hydroelectric power plants, waste-to-energy plants etc)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Steps for producing as estimate?

A

1) Identification work gc and subs
2) Study specs gc, read specs subs
3) Affect general conditions on project
4) visit site with pm
5) Team meeting, discuss quantities take-off and pricing
6) RFT subs
7) Think jobsite and general overheads and margins.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the errors during detail estimating process?

A
  • Do not cover up/attempt to recover the missing cost with fake change orders.
    (trying to recover estimating mistakes could lead to costly project disputes/loss of rep/loss of clients.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens at 30 to 40% of the finished design?

A
  • Project team reviews the design. (critical designs would have been made)
  • Foundation for producing the first engineering estimate based on drawings.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens at 60% finished design?

A
  • Foundation for second engineering estimate.
  • Verify proposed system/subsystems meet project needs.
  • Compare original proposed budget with more precise quantities and quality requirements.
  • ID unresolved problems that will influence final building cost
  • Review drawings and specifications. (especially in DB contract)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What happens at 90% finished design?

A
  • Complete set of bid docos
  • Last chance review
  • Set of docos sent to the permitting authorities for review
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does price include?

A
  • Permanent and temporary materials to be procured.
  • Labour required for installing
  • Equipment required for moving and installing
  • Other consumables such as fuel and tools.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How much of constructing is labour?

A

30 to 50 percent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the total cost of labour?

A

Sum of total work hours x wage rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the total work hours?

A

Sum of quantity of work / productivity rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is one of the most inaccurate aspect of estimating?

A

Productivity rate as it varies day to day, project to project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the factor of productivity rate?

A
  • External factors (market/environment conditions)

- Internal factors (work/management conditions)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a contingency?

A

Amount of money added to an estimate to cover unforseen needs of the project, construction difficulties or estimating accuracy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What increases contingency?

A
  • Duration greater than 12 months
  • Complexity of project.
  • Incomplete parts of project
  • Unforeseen safety and enviro requirements
17
Q

Why is contingency good?

A
  • Provide a form of insurance that the contractor will stay within bid price.