Lecture 5: Construction Management Flashcards

1
Q

Means by which a person or persons can
let someone else do something for
them. These agreements are similar to contracts.Consists of a principal being represented by an agent in business dealings with a third party.

A

Agency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A ________ is an agent of the
Owner.
The ____ is hired and paid by the Owner to represent the latter in matters of contract
administration.

A

Construction manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Projects exceeding budget (Cost overruns)
  2. Projects consistently fell behind schedule (Delays)
  3. Construction quality was not as expected
  4. Design efforts fell short of expectations
  5. Owners had limited participation
  6. Contracting flexibility was minimal
  7. Contract disputes were common and costly
  8. Fair value was not being produced
A

The need for a construction manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

This term was introduced to remind A/E’s that satisfying the Owner’s needs
in a practical and economic way is the Owner’s main priority. The balance between form, function, and
budget has to be reached.

A

Designability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Late involvement of the contractor in the project does not allow for the Contactor’s input to be incorporated in design at its earlier phases.
  2. This term was introduced in response to the repeated observation that some designs can not be economically or safely built.
  3. It describes the level of cost-related features designed in the project.
  4. It requires a sound knowledge of construction methods, tools and techniques
A

Constructability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Should be performed while design is

being developed to maximize its benefit and avoid major design changes or late and costly construction changes.

A

Constructability review

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Is the term used for the economic
optimization of the contracting aspects of a
project.
It references contract structures, contract
documents, and general and special contract conditions.
May also be referred to as contract administration or contract management.

A

Contractability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. A contracting approach involving a “Construction
    Manager” as an owner’s agent.
  2. The Construction Manager (CM) may be involved as early
    as the planning phase or as late as the Procurement phase
    or anywhere in between.
A

Construction

Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Responsible for coordination, supervision, evaluation, overseeing the tests performed by the GC, reviewing and authorizing the interim and final payment requisitions submitted by the GC.
  2. Does not have labor, material, or equipment involved in construction (other than management team)
  3. Has no contracted responsibilities to the owner as an independent contractor or as the A/E.
  4. Has a service contract with the owner.
A

Agency Construction Manager (ACM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. When the bidding process results in costs within the budget.
  2. When owner occupancy (Project completion) occurs on schedule.
  3. When specified quality is met.
  4. When no claims are brought against the owner by contractors.
A

Measuring ACM Performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Has the same main duties as the ACM, with the addition of guaranteeing a schedule (Completion date) and a budget (Completion cost).
  2. Is liable to the owner in case of deviation from the set goals.
  3. Rate of compensation much higher than ACM (To offset the risks involved)
  4. Is somewhere between an ACM and aGC
A

Construction Manager at risk (CM at Risk)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Five basic schedules

A
  1. Program schedule
  2. Detailed construction schedule
  3. Milestone schedule
  4. Short-term contractors activity plan (CAP)
  5. Completion schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Drives the project from start to finish

A

Program Schedule:

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

(a.k.a. Master Schedule):
Determines the time needed for construction (Prepared by
Contractor)

A

Detailed Construction Schedule:

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Drives the project during construction

providing the start and finish dates of major milestones

A

Milestone Schedule:

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Plans contractor’s activities to meet milestones. Usually 6 to 8
weeks period.

A

Short Term Contractor’s Activity Plan (CAP):

17
Q

Coordinates construction completion and occupancy.

A

Completion Schedule:

18
Q

CM keeps the positive

attributes of GC

A
  1. Firm commitment to cost, time, and quality
  2. Competitive bidding of prescribed scope of work.
  3. Accommodation of Fast Track
  4. Construction expertise available during design
  5. Continuity between design and construction
  6. Uses existing industry participants
  7. Contractors can act as CM
  8. A/E’s can act as CM
19
Q
  1. Insufficient construction expertise available during design
  2. Insufficient contracting expertise available to the Owner
  3. Lack of Owner decision making involvement during
    construction
  4. No measure of bidders’ management ability prior to
    contract award
  5. Limits on Owner’s involvement in the selection of trade
    contractors
  6. Insufficient continuity between design and construction
  7. Adversarial relationship between Owner and Contractor
  8. Post bid shopping
  9. Inequitable risk allocation
A

CM eliminates GC system

Negatives

20
Q

CM eliminates negatives of Design-build

A
  1. Design quality directly affects contractor’s profit
  2. Owner must have high level construction
    expertise otherwise hires bridging consultant
  3. No decision-making checks and balances
  4. Cannot be used in public sector without
    modification
21
Q
1. Professional party 
assisting in preparation of 
schedule and budget.
2. Complements A/E’s 
effort and offers a new 
eye for VE and 
Constructability 
issues.
3. Can consolidate the risks 
for construction and 
supervision (CM at risk)
A

Advantages of having a CM.

22
Q
Disadvantages:
1. Extra cost to the owner
2. Unclear lines of 
responsibility/coordination 
problems with A/E.
A

Disadvantages of a CM.

23
Q
  1. Method usually used for the purchase of
    material/equipment.
  2. Does not cover labor for installation.
  3. Becomes a valid contract only upon signing by both parties (Vendor and buyer).
  4. May use boiler plates or tailor-made forms
  5. May have flow-down language from original contract.
  6. May include cash discounts for immediate or short –term payment, as well as for large
    quantities.
A

Purchase Orders

24
Q

What information should purchase orders contain?

A
1. Construction project for which the prime construction contract 
is held by the buyer
2. Owner for that project
3. Architect/engineer
4. Contractor/ buyer
5. Seller/supplier
6. Complete description of material ordered
7. Price to be paid (Sales tax, customs, delivery charges, etc.)
8. Delivery conditions (Schedules, On-
site, FOB, etc.)
9. Inspection provisions
10. Signatures
25
Q
  1. One of the contractual remedies for delays
  2. Sometimes the damages suffered due to delays in
    project completion are very hard, or impossible, to
    determine at the time the contract was signed.
A

Liquidated damages

26
Q

The owner will try to evaluate, in anticipation, the value
of such losses and determine an equitable
compensation for the resulting damages.
The ____ usually has no input into the
determination of the value of the liquidated damages.

A

contractor

27
Q

_________ are not a penalty. Current judicial attitude toward liquidated damages is to enforce such provisions in the event of unexcused late completion by the contractor.

A

Liquidated damages

28
Q

Defenses against Liquidated damages:

A
  1. Proving the project is substantially complete
  2. Excusable or compensable delays
  3. Concurrent delays
29
Q

What does Amount of damages mean when talking about liquidated damages?

A

Actual damages not punitive damages

30
Q

Substantiating documents when dealing with liquidated damages are?

A
  1. Schedule
  2. Weather reports
  3. Change and variation ordersEtc.
  4. Milestones