lecture 13 Flashcards
- is a demand or assertion by one of the parties seeking, as a matter of right, payment of money or other relief with respect to the terms of the contract. (AIA A201)
- It is a demand or assertion by owner or contractor seeking an adjustment of contract price or contract times, or both, or other relief with respect to the terms of the contract.(EJCDC C700)
- It is a request for compensation for dealing with a situation that differs materially from what was anticipated by the parties at the time of entering into the contract.
- It is an entitlement for a change observed in the contract administration process
- It can be a claim for restitution, which includes financial compensation or reimbursement
- It can be a claim for extension of time
- It can be a claim for acceleration
Claims
If not resolved amicably, a claim can become a _____.
dispute
Generally, ____________ usually result in claims.
Contract document modifications
Three sources of claims may occur on a project.
- They include claims by the contractor (often on behalf of their subcontractors and suppliers) against the owner,
- and claims by the owner against the contractor or the A/E.
- The third source is a claim initiated by someone other than a party to the construction contract.
A contractor prepares pricing based on the _________ and other factors that are reasonably foreseeable at the time.
procurement documents
If, during the course of the project, the contractor encounters conditions contrary to those stipulated or inferred in the contract documents, a ____ may be initiated.
claim
Change conditions include:
- Active interference by the owner or A/E
- Conditions beyond the control of either the contractor or the owner
- Unknown or concealed conditions that affect the extent of the work
- Modifications made to the contract documents 5. Errors and omissions in the contract documents
The contractor is required to provide clear documentation that a changed condition actually was not ________ at the time of pricing and resulted in demonstrable damages.
not foresseable
Claims resulting from changed conditions may also be submitted by the _______ on behalf of the contractor’s subcontractors and suppliers.
contractor
In claims involving breach of contract, the contractor must __________________ by the other party.
document nonperformance
Two types of claims relating to breach of contract are .
- claims for untimely payment or nonpayment and
2. claims for improper or ineffective construction contract administration
Why would the Owner make a Claim?
- Correction of nonconforming or defective work
- Repair of damages to existing property
- Liquidated or compensatory damages for late performance
- Ineffective management and/or control of the work by the contractor resulting in added costs.
Ineffective management and/or control of the work by the contractor resulting in added costs for:
- Inordinate re-reviews of shop drawings
- Reviews of substitution requests
- Interferences with the owner’s operations
- Additional site visits, inspections, and related administrative time
- These types of claims are also grounds for withholding payment. It is important that the owner understand that the general conditions require the party initiating the claim to provide documentation establishing the claim.
- Therefore, the owner should carefully document such claims, attempt to settle the claim, and unilaterally withhold payment only as a last resort to satisfying the claim.
Owner’s claims
An example could be the excessive settlement or cracking of an existing building foundation where an adjacent excavation caused unstable soil conditions to occur.
third party claim
Under the provisions of ________, the contractor agrees to indemnify the owner and A/E against all thirdparty claims resulting from the contractor’s performance of work on the project.
AIA Document A201 and EJCDC C-700
Third party claims may not require a privity of contracts, and are therefore often filed as ___.
torts