means quantifying the amount of work eligible for payment.
Measurement
is the disbursement of money proportionate to that
quantity of work.
Payment
Under some contracts, ________ may involve only identifying the attainment of specified milestones for which predetermined amounts of payment are to be paid.
measurement
Under other contracts, particularly ________,
measurement means verifying the quantities of work submitted for payment based on unit prices.
unit price contracts
Most projects involve ______ and ___________.
significant costs
extended construction periods
The contractor depends on cash flowing through the contractor’s operation to minimize the need to _________.
borrow funds
Progress payments are standard, and the _____ promise to make payment is a primary obligation under the construction contract.
owner’s
Estimates of progress and the amounts paid are valuable indicators other people can use to determine whether their _______ in the project are being met.
interests
The _________ was the solution for the owner in order not to pay more than once for the
same work and protect himself/herself from Mechanic’s lien.
payment bond
States that the subcontractor will receive payment when the contractor receives payment from the owner.
“pay when paid”
Most contracts require that a schedule of values be submitted to the ________ for approval prior to the first application for payment.
architect/engineer (A/E)
It is not uncommon
for the contractor to be required to submit an _________________________________ as
a prerequisite for payment.
updated construction progress schedule, test reports, material certifications, and other accompanying information
On more complex projects, schedules may be both ________, which would allow its use with the application for payment.
manpower and cost loaded
The contractor may also be required to submit a list of __________________ for review by the owner’s lender.
proposed or pending change orders and change order requests
_____ and other standard contract documents refer to progress payments.
AIA
The period between progress payments is usually stated in the _________.
general conditions
__________ is the most common payment interval.
The calendar month
are appropriate for most projects, including those of long duration and high cost, where the rate of progress will vary from month to month.
Monthly progress payments
may be appropriate for small projects performed by small contractors or large fast-track projects where large amounts of money are expended over brief periods on a regular basis.
.
Twice-monthly or even weekly progress payments
are predetermined partial
amounts of the total contract sum tied to the attainment of identifiable
milestones.
Provisional payments
may be percentages of the total quantities in the project, or they may be certain portions of the entire project that have been assigned a predetermined value.
Milestones
are a form of progress payment, but are distinguished from periodic progress payments by being independent of a time interval.
Provisional payments