lecture 18 Flashcards
- Typically given in calendar days (including holidays and weekends), unless otherwise clearly stated.
- Work Day
- Not universally defined (8 hours? One shift? 2 shifts? 24 hours?).
- Any day except Saturdays, Sundays, and holidays.
- Most appropriate when the site conditions are subject to delays caused by weather, differing site conditions, etc.
- Typically extend ____________
for severe weather delays
Construction duration
- is defined in the contract as the day the contractor
receives the notice to proceed(NTP), the day of having acquired the site free from any encumbrances, or any other agreed upon date stated in the contract. - The time counter starts to count the project duration from the start
date.
Start Date
- is the start date + the project duration as stated in
the contract. - Can be a Fixed completion day in case of calendar days, or when
owner needs completed project by a specific date, or a floating date if project duration is given in workdays. - There is risk involved in the project execution, especially if the contractor fails to meet the milestones and the completion date.
Completion Date
- in this case means something
less than absolute or final, but almost final. - Different from the actual construction completion date stated in the contract.
- Project can be occupied and used by the owner with minor items to be corrected.
- Same as practical completion.
- Last periodic payment is made to the contractor except retainage which is released after punch list items are corrected.
- Usually, liquidated damages are not assessed beyond _______, unless otherwise stated.
Substantial completion
- Also known as snag list.
- Document containing remaining work items to address after substantial completion, or defective items to be completed before project handover.
- Retainage is usually released after correction of _____ items.
- Once the items on the _____ have been completed, the project can be handed over, and reaches Final Completion.
Punch List
Expediting the work progress, usually to recover from a
delay.
Acceleration
Consists of a direct order by owner to
hire additional workers, work overtime,
or work extra shifts on the project. Can convert an excusable delay into a compensable delay.
Owner initiated or Actual acceleration
Does not result from direct order. Initiated by the contractor to avoid paying liquidated damages after Owner’s refusal to permit or grant time extensions for a delay.
Contractor initiated or Construction acceleration
- Provide compensation to the owner
for financial and other losses resulting from delayed completion beyond the contractual completion date. - Avoids lawsuits since the concept and amount are agreed upon at contract signing.
- Predetermined cost per day of late completion
is used in lieu of actual damages. In extreme cases, may be assessed on minutes of delay rather than days. - Not constituting penalty. Penalty provisions generally are not enforceable unless a bonus clause also exists.
- Must be reasonable anticipated costs of late completion reflecting the actual damages the owner suffered, not punitive damages.
Liquidated Damages
- Contractor or Contractor’s agent
- Owner’s or Owner’s agent
- Forced majeure or acts of God.
- Unforeseen events or conditions
Sources of delays
- May result in extreme cases in contract termination.
2. Owner will claim damages against contractor.
Contractor or contractor’s agent delay
- Extension of contract time.
- Contract amount can be changed.
- Contractor can claim damages against owner
Owner or owner’s agent delay
Events or actions beyond the control of any of the contract parties
Force majeure or acts of God delay
- Excusable delays
- Compensable delays
- Non-Excusable/Non-Compensable delays
- Concurrent delays
four types of delays
- These are usually delays resulting from 3rd party or
“Force Majeure” reasons. - Since it is not the fault of any of the 2 main
contract parties (Owner or Contractor), the
owner can only excuse the contractor from any
damages resulting from the delay, and grant the
contractor an extension of time equal to the
delayed amount and any additional impact
delays.
Excusable delays