Lecture 3: types of contracts Flashcards
study
The classification of contract types is based on what?
method of payment, presence of competition, parties to the contract, and delivery method.
methods of payment
Lump sum, Unit Price, Cost +
presence of competition:
Competitively bid, Negotiated
Parties to the contract:
- General Contractor (Prime or GC) and subs
- Construction management agency
- Construction management at risk
- Force account
Types of delivery methods
Design-bid-buildDesign-buildFast trackDBOT, DBOOT, BOT, Turnkey
Contractor has the greatest risk.
Firm lump sum
Contractor’s risk is 5/6.
fixed lump sum with escalation formula.
Contractors risk is 3/4.
fixed lump sum.
The risk between the owner and contractor is 50/50.
Unit price
Owner’s risk is 3/4.
Cost plus sliding fee (GMP)
Owners risk is 5/6.
Cost plus fixed fee
Owners risk is 100%
Cost plus %.
- Contractor agrees to perform the contract work for a determined sum of money
- Could be firm (no change whatsoever) or subject to modification
- Requires a well defined scope of work
- Requires enough time for the bidders to evaluate and price their bids
- Offers minimum risk for the owner and maximum risk for the contractor
- The _____ figure should cover for all project costs (Labor, material, equipment, overheads, profit, etc.)
Lump sum
- Payments are made on the basis of a pre-submitted schedule of payments (Including interim or progress payments and final payment)
- Adding an escalation clause is a good practice3. Most contractual disputes result from this type
- Contractor should include a margin for contingencies to cater for unexpected events
Lump sum payment
- Contractor is required to calculate quantities from contract documents (Drawings., Specs., etc.).2. Contractor should price one unit of each contract item.
- Total price is calculated by multiplying the number of measured units x unit cost.
- Allows for changes within pre-set limits.
- Total sum of the contract also called equivalent lump sum.
Unit price
- Payment requisitions submitted regularly based on actual performance.
- Payment requisitions should follow a schedule of activities and payments.3. Used when the scope of the project is fairly clear, however, some changes might occur.
- Beware of +/-%, especially in case of unbalancing.
- Risk is almost equally distributed between Owner and Contractor.
Unit price contracts payment
- Mostly a negotiated contract
- Mainly used in cases of:Emergency, Unclear scope, Severe time constraints, and Specialized projects where the contractor is involved in design
Cost plus contracts
The contractor is reimbursed for all the incurred costs +
- A percentage of the cost 2. A fixed fee
- A sliding fee
Cost plus contract payment
Reimbursable costs include:Labor costs (Payroll + taxes + benefits)Equipment costs (Ownership + Operation + transportation + setup)Material Costs (including sales tax + storage+ transportation+ inspection + testing) but excludes work redone due to poor workmanship
“Cost” Component
Also includes:
- SubcontractsBonds and insuranceConsumables (Small tools, etc)
- Overheads (Other than included in “Plus”)
- Losses due to unexpected risks (Other than contractor’s fault)
“Cost” component
1. Worst solution for the owner
- The larger the cost, the larger the dollar amount of the percentage
- Cost control totally shifted to the owner
- No incentive for the contractor to reduce costs
“Plus Component” percentage
- Agreed upon during contract negotiations
- No incentive for the contractor to control costBetter than “+ %”
- Owner still has to perform cost controlDr. Ihab M. H. Saad 2016
Plus component fixed fee
- Starts with a fixed fee for a target contract costCan follow one of two settings:
- Fee increases with increased scope and therefore cost (No contractor incentive to reduce costs)
- Fee increases with decreased cost, and decreases with increased cost till it reaches a ceiling, thus becoming closer to a GMP (Contractor shares in cost control)
“Plus” Component Sliding Fee:
- Also known as “target” or “ceiling”Main cost + “Plus” = Fixed amount “Target”
- If cost increases, “Plus” decreases until it vanishes, or even becomes a negative value if total cost exceeds target
- Offers incentive for contractor to control costs
Guaranteed Maximum Price (GMP)
- Best arrangement for both owner and contractor under such type of contract
- Offers common goal of reducing price and controlling costs
- Savings shared between parties according to a pre-set percentage
Fixed fee with upset price and profit sharing: