Lecture 3: types of contracts Flashcards

study

1
Q

The classification of contract types is based on what?

A

method of payment, presence of competition, parties to the contract, and delivery method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

methods of payment

A

Lump sum, Unit Price, Cost +

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

presence of competition:

A

Competitively bid, Negotiated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Parties to the contract:

A
  1. General Contractor (Prime or GC) and subs
  2. Construction management agency
  3. Construction management at risk
  4. Force account
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Types of delivery methods

A

Design-bid-buildDesign-buildFast trackDBOT, DBOOT, BOT, Turnkey

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contractor has the greatest risk.

A

Firm lump sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contractor’s risk is 5/6.

A

fixed lump sum with escalation formula.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contractors risk is 3/4.

A

fixed lump sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The risk between the owner and contractor is 50/50.

A

Unit price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Owner’s risk is 3/4.

A

Cost plus sliding fee (GMP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Owners risk is 5/6.

A

Cost plus fixed fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Owners risk is 100%

A

Cost plus %.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. Contractor agrees to perform the contract work for a determined sum of money
  2. Could be firm (no change whatsoever) or subject to modification
  3. Requires a well defined scope of work
  4. Requires enough time for the bidders to evaluate and price their bids
  5. Offers minimum risk for the owner and maximum risk for the contractor
  6. The _____ figure should cover for all project costs (Labor, material, equipment, overheads, profit, etc.)
A

Lump sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. Payments are made on the basis of a pre-submitted schedule of payments (Including interim or progress payments and final payment)
  2. Adding an escalation clause is a good practice3. Most contractual disputes result from this type 
  3. Contractor should include a margin for contingencies to cater for unexpected events
A

Lump sum payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. Contractor is required to calculate quantities from contract documents (Drawings., Specs., etc.).2. Contractor should price one unit of each contract item.
  2. Total price is calculated by multiplying the number of measured units x unit cost.
  3. Allows for changes within pre-set limits.
  4. Total sum of the contract also called equivalent lump sum.
A

Unit price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. Payment requisitions submitted regularly based on actual performance.
  2. Payment requisitions should follow a schedule of activities and payments.3. Used when the scope of the project is fairly clear, however, some changes might occur.
  3. Beware of +/-%, especially in case of unbalancing.
  4. Risk is almost equally distributed between Owner and Contractor.
A

Unit price contracts payment

17
Q
  1. Mostly a negotiated contract
  2. Mainly used in cases of:Emergency, Unclear scope, Severe time constraints, and Specialized projects where the contractor is involved in design
A

Cost plus contracts

18
Q

The contractor is reimbursed for all the incurred costs +

  1. A percentage of the cost 2. A fixed fee
  2. A sliding fee
A

Cost plus contract payment

19
Q

Reimbursable costs include:Labor costs (Payroll + taxes + benefits)Equipment costs (Ownership + Operation + transportation + setup)Material Costs (including sales tax + storage+ transportation+ inspection + testing) but excludes work redone due to poor workmanship

A

“Cost” Component

20
Q

Also includes:

  1. SubcontractsBonds and insuranceConsumables (Small tools, etc)
  2. Overheads (Other than included in “Plus”)
  3. Losses due to unexpected risks (Other than contractor’s fault)
A

“Cost” component

21
Q

1. Worst solution for the owner

  1. The larger the cost, the larger the dollar amount of the percentage
  2. Cost control totally shifted to the owner
  3. No incentive for the contractor to reduce costs
A

“Plus Component” percentage

22
Q
  1. Agreed upon during contract negotiations
  2. No incentive for the contractor to control costBetter than “+ %”
  3. Owner still has to perform cost controlDr. Ihab M. H. Saad 2016
A

Plus component fixed fee

23
Q
  1. Starts with a fixed fee for a target contract costCan follow one of two settings:
  2. Fee increases with increased scope and therefore cost (No contractor incentive to reduce costs)
  3. Fee increases with decreased cost, and decreases with increased cost till it reaches a ceiling, thus becoming closer to a GMP (Contractor shares in cost control)
A

“Plus” Component Sliding Fee:

24
Q
  1. Also known as “target” or “ceiling”Main cost + “Plus” = Fixed amount “Target”
  2. If cost increases, “Plus” decreases until it vanishes, or even becomes a negative value if total cost exceeds target
  3. Offers incentive for contractor to control costs
A

Guaranteed Maximum Price (GMP)

25
Q
  1. Best arrangement for both owner and contractor under such type of contract
  2. Offers common goal of reducing price and controlling costs
  3. Savings shared between parties according to a pre-set percentage
A

Fixed fee with upset price and profit sharing: