IBC Chapter 1 Flashcards

1
Q
  1. The ______shall keep a detailed record of alterations made under an annual permit.

A. Municipal clerk
B. Person to whom the permit is issued
C. Building official
D. Fire marshal

A
  1. B 105.1.2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. According to the IBC, in the flood hazard areas the elevation certification shall be submitted to the building official .

A. Upon placement of the lowest floor, including the basement, and prior to the further vertical construction.
B. Before the Certificate of Occupancy
C. Upon placement of the foundation walls
D. Upon completion of the framing inspection

A
  1. A 110.3.3
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. The Building Official may issue a permit for a temporary structure for________days.

A. 30
B. 60
C. 180
D. 90

A
  1. C 108.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. A permit is not required for repairs involving the .

A. Connections of approved portable electrical equipment to approved receptacles
B. Cutting away of any wall or partition
C. Replacement of waste line, vent or similar piping
D. Removal or change of any required means of egress element

A
  1. A 105.2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Unless state or local law mandates a different time period, at least one set of approved construction documents shall be retained by the building official for at least .

A. 180 days after issuance of the certificate of occupancy
B. 30 days after initial inspection
C. 180 after completion of the permitted work
D. 90 days after issuance of the certificate of occupancy

A
  1. C 107.5
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. The _______is authorized to establish a refund policy.
    A. Building official
    B. Permit desk
    C. Building inspector
    D. All of the above
A
  1. A 109.6
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. The has the authority to authorize disconnection of the utility service to a building in case of an emergency.
    A. building official
    B. mayor
    C. fire chief
    D. utility company
A
  1. A 112.3
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. Which of the following types of work does not require a building permit?

A. driveway located 4 feet above grade
B. 3-foot-high retaining wall supporting a surcharge
C. 7-foot-high solid masonry fence
D. 180-square-foot one story detached accessory building

A
  1. C 105.2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. The solid vertical black line located next to code in a International Building Code sections means:

A. The code section has a change in it
B. The code section is important
C. Part of the code was deleted
D. The code section is in the process of being changed

A
  1. A Preface – Marginal Markings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Making sure work remains accessible and exposed for inspection purposes shall be the responsibility of the .

A. Permit holder
B. Design professional in responsible charge
C. Person requesting the inspection
D. Contractor

A
  1. A 110.5
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. The building official shall retain inspection reports .

A. Until the certificate of occupancy is issued
B. For 5 years
C. For 7 years
D. For the period required for the retention of public records

A
  1. D 104.7
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Where conflicts occur between provisions of IBC and the referenced codes and standards
    .

A. The provisions of the IBC shall apply
B. The building Official shall decide which shall apply
C. The provisions of the most strenuous shall apply
D. The provisions for the referenced standard shall apply

A
  1. A 102.4.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. Provisions of the appendix do not apply unless .

A. Specified in the code
B. Applicable to unique conditions
C. Specifically adopted
D. Relevant to fire or life safety

A
  1. C 101.2.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. The Building Official has the authority to the provisions of the code.

A. ignore
B. waive
C. violate
D. interpret

A
  1. D 104.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. Used materials may be utilized under which of the following conditions?

A. They meet the requirements for new materials
B. They are limited to 10 percent of the total materials
C. Used materials may never be used in new construction
D. A representative sampling is tested for compliance

A
  1. A 104.9.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. The Building Official has the authority to grant modifications to the code .

A. for only those issues not affecting life safety or fire safety
B. for individual cases where the strict letter of the code is impractical
C. where intent and purpose of the code cannot be met
D. related only to administrative functions

A
  1. B 104.10
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  1. In order for an alternative material, design or method of construction to be considered acceptable, it must be equivalent to the code based on all but which of the following criteria?

A. durability
B. economics
C. strength
D. fire resistance

A
  1. B 104.11
18
Q
  1. Tests performed by ________may be required by the Building Official where there is insufficient evidence of code compliance.

A. the owner
B. the contractor
C. an approved agency
D. a design professional

A
  1. C 104.11.2
19
Q
  1. A permit is not required for the construction of a one-story detached accessory structure when it has a maximum floor area of square feet.

A. 100
B. 120
C. 150
D. 200

A
  1. B 105.2, #B1
20
Q
  1. Movable fixtures, cases, counters and partitions are exempt from a building permit where they have a maximum height of .

A. 5 feet, 0 inches
B. 5 feet, 6 inches
C. 5 feet, 9 inches
D. 6 feet, 0 inches

A
  1. C 105.2 #B13
21
Q
  1. Where a building is constructed in a floor hazard area, documentation of the lowest floor elevation shall be submitted to the Building Official prior to .

A. any framing work above the lowest level
B. approval of the framing inspection
C. the final inspection
D. issuance of the certification of occupancy

A
  1. C 110.3.11.1
22
Q
  1. The building permit, or a copy of the permit, shall be kept until completion the project.

A. at the jobsite
B. by the permit applicant
C. by the contractor
D. by the design professional in responsible charge

A
  1. A 105.7
23
Q
  1. When a building permit is issued, the construction documents shall be approved as .

A. “Approved for Construction”
B. “Conditional Approval”
C. “Accepted as Reviewed”
D. “Reviewed for Code Compliance”

A
  1. D 107.3.1
24
Q
  1. Unless otherwise mandated by state or local laws, the approved construction documents shall be retained by the Building Official for a minimum of from the date of completion of the permitted work.

A. 90 days
B. 180 days
C. 1 year
D. 2 years

A
  1. B 107.5
25
Q
  1. Which of the following inspections is not specifically identified by the International Building Code as required inspection?

A. footing inspection
B. frame inspection
C. soil classification
D. energy efficiency inspection

A
  1. C 110.3
26
Q
  1. Whose duty is it to notify the building official that the work is ready for inspection?

A. the permit holder
B. the owner
C. the contractor
D. the architect

A
  1. A 110.5
27
Q
  1. The certificate of occupancy shall contain all of the following information except:

A. the name of the building owner
B. the name of the Building Official
C. the building’s type of construction
D. the building’s maximum height and area

A
  1. D 111.2
28
Q
  1. A temporary certificate of occupancy is valid for what period of time?

A. 30 days
B. 60 days
C. 180 days
D. A period set by the Building Official

A
  1. D 111.3
28
Q
  1. The board of appeals is not authorized to rule on an appeal based on a claim that .

A. the provisions of the code do not fully apply
B. a code requirement should be waived
C. the rules have been incorrectly interpreted
D. a better form of construction is provided

A
  1. B 113.2
28
Q
  1. If there is a conflict in the code between a general requirement and a specific requirement, the
    requirement shall apply.

A. general
B. specific
C. least restrictive
D. most restrictive

A
  1. B 102.1
29
Q
  1. A permit is not required for the construction of a fence where the fence is a maximum of feet in height.

A. 5
B. 6
C. 7
D. 8

A
  1. C 105.2, #B2
29
Q
  1. A permit is required for a prefabricated above-ground swimming pool, accessory to Group R-3 occupancy, that is a minimum of in depth or a has a capacity of more than .

A. 18 inches; 4,000 gallons
B. 24 inches; 5,000 gallons
C. 30 inches; 5,000 gallons
D. 36 inches; 6,000 gallons

A
  1. B 105.2, #B9
30
Q
  1. In Group R-3 and U occupancies, the installation of window awnings is exempt from a permit, provided the awnings each project a maximum of inches from the exterior wall and do not require additional support.

A. 30
B. 36
C. 48
D. 54

A
  1. D 105.2, #B12
30
Q
  1. A permit may be suspended or revoked for all of the following reasons, except .

A. Where it is issued in error
B. On the basis of incomplete information
C. Where issued in violation of a jurisdictional ordinance
D. Where other permits by the contractor have been voided

A
  1. D 105.6
31
Q
  1. The inspection of gypsum board installation is required where gypsum board is part of .

A. a shear assembly only
B. a fire-resistance-rated assembly only
C. either a fire- or smoke-resistant assembly
D. either a shear or fire-resistance-rated assembly

A
  1. D 110.3.5, Exc.
31
Q
  1. A permit is not required for the installation of a self-contained refrigeration system, provided it contains a maximum of pounds of refrigerant and is actuated by a maximum -horsepower motor.

A. 5, 1
B. 10, 1
C. 5, 1 ½
D. 10, 1 ½

A
  1. B 105.2, #M7
32
Q
  1. The means of egress layout required as a part of the construction documents for which of the following occupancies must include the number of occupants to be accommodated?

A. F-1
B. I-1
C. R-2
D. R-3

A
  1. A 107.2.3
32
Q
  1. The final permit valuation shall be determined by the .

A. owner
B. building official
C. design professional
D. general contractor

A
  1. B 109.3
33
Q
  1. Who is responsible for assuring that the work is visible and able to be accessed for inspection purposes?

A. Owner or owner’s authorized agent
B. contractor
C. permit applicant or their authorized agent
D. design professional

A
  1. A 110.1
33
Q
  1. A stop work order shall be in writing and given to any of the following individuals except the
    .

A. owner of the property involved
B owner’s agent
C. permit holder
D. person doing the work

A
  1. C 115.2