Design & Specification Flashcards

1
Q

What is the RIBA plan of work?

A
  • First developed in 1963
  • The definitive UK model for the design and construction process.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the RIBA stages?

A
  • 0: Strategic Definition
  • 1: Preparation and Brief
  • 2: Concept Design
  • 3: Developed Design
  • 4: Technical Design
  • 5: Construction
  • 6: Handover and Close out
  • 7: In Use
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

At what RIBA stage would you tender works?

A
  • RIBA Stage 4
  • Depends on procurement route
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

At what RIBA stage would you sign the contract?

A
  • Traditional, RIBA Stage 4
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 0 – Strategic Definition?

A
  • Stage outcome: The best means of achieving the client requirements are confirmed.
  • Core tasks:
    o + Prepare client requirements.
    o + Develop business case for feasible options including review of project risks and budget.
    o + Undertake site appraisals.
  • Core statutory processes:
    o + Strategic appraisal of planning considerations.
  • Information Exchanges:
    o + Client requirements.
    o + Business case.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 1 – Preparation & Briefing?

A
  • Stage outcomes: Project brief approved by the client and confirmed that it can be accommodated on the site.
  • Core tasks:
    o + Prepare client brief - including project outcomes, sustainability outcomes, quality aspirations and spatial requirements.
    o + Undertake feasibility studies.
    o + Agree project budget.
    o + Source site information - surveys.
    o + Prepare project programme.
  • Core statutory processes:
    o + Source pre-application planning advise.
    o + Initiate collation of health and safety Pre-Construction Information.
  • Information Exchanges:
    o + Project brief.
    o + Site information.
    o + Procurement Strategy.
    o + Responsibility Matrix.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 3 - Spatial Coordination

A

Stage outcomes: Architectural and engineering information spatially coordinated.

Core tasks:
+ Undertake design studies, engineering analysis and cost exercises to test architectural concept resulting in spatially coordinated design aligned to updated cost plan, project strategies and outline specification.
+ Initiate change control procedures (process for making any requested changes to the project to make sure they are not made unnecessarily and don’t impact negatively on project programme and cost).
+ Prepare stage design programme.

Core statutory processes:
+ Review design against building regulations.
+ Prepare and submit planning application.

Information exchanges:
+ Signed off stage report.
+ Project strategies.
+ Updated outline specification.
+ Updated cost plan.
+ planning application.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 4 - Technical Design

A

Stage outcomes: All design information required to manufacture and construct the project completed.

Core Tasks:
+ Develop architectural and engineering technical design.
+ Prepare and coordinate design team building system information.
+ Prepare and integrate specialist subcontractor building systems information.
+ Prepare stage design programme.

Core Statutory Processes:
+ Submit Building Regulations Application.
+ Discharge pre-commencement planning conditions.
+ Prepare Construction Phase Plan.
+ Submit F10 form to HSE if applicable.

Information exchange:
+ Manufacturing information.
+ Construction information.
+ Final specifications.
+ Building Regulations Application.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 5 - Manufacturing and Construction?

A

Stage outcomes: Manufacturing, construction and commissioning completed.

Core tasks:
+ Finalise site logistics.
+ Manufacture building systems and construct building.
+ Monitor progress against construction programme.
+ Inspect construction quality.
+ Resolve site queries as required.
+ Undertake commissioning of building.
+ Prepare building manual.

Core statutory processes:
+ Carry out Construction Phase Plan.
+ Comply with planning conditions relating to construction.

Information exchange:
+ Building manual (O&M manual) including Health and Safety File and Fire Safety Information.
+ Practical completion certificate including defects list.
+ Asset information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 6 - Handover

A

Stage outcomes: Building handed over, aftercare initiated and building contract concluded.

Core tasks:
+ Hand over building in line with Plan for Use Strategy.
+ Undertake review of project performance.
+ Undertake seasonal commissioning.
+ Rectify defects.
+ Complete initial aftercare tasks.

Core statutory processes:
+ Comply with planning conditions as required.

Information exchange:
+ Feedback on project performance.
+ Final certificate (AI).
+ Feedback from light touch post occupancy evaluation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 7 - Use

A

Stage outcomes: Building used, operated and maintained efficiently.

Core tasks:
+ Implement facilities management and asset management.
+ Undertake post occupancy evaluation of building performance in use.
+ verify project outcomes including sustainability outcomes.

Core statutory processes:
+ Comply with planning conditions as required.

Information exchange:
+ Feedback from post occupancy evaluation.
+ Updated building manual including health and safety file and fire safety information as necessary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are preliminaries?

A

They provide the description of the project to allow cost assessment and specify general conditions and requirements for execution. For example: project description, site access and parking etc.

From the preliminaries a contractor can price for cost significant items that they need to carry out the works such as site welfare and provision of temporary services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are preambles?

A

A preamble is an explanation of a document, commonly found in contracts, specifications and bills of quantities. It helps with the interpretation of a document.

A preamble may include:

Description of parties to the contract.

A description of the competence of parties to a contract - this will include a set of general standards for the quality of goods or services required.

Tendering procedures.

Objectives of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the difference between preliminaries and preambles?

A

Preambles are the explanation of the works that don’t form part of the costings, preliminaries are used to describe the project and allow costing of items that are required to complete the works, for example temporary access and welfare.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is NBS?

A

The National Building Specification is a UK based company that provides specification platforms used by construction professionals to produce high quality and standardised specifications for construction projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why would you use NBS?

A

Allows collaboration - others can be invited to edit the document.

Ensures consistent standard and format for all projects.

All statutory standards are kept up to date, such as British Standards.

It is the standard specification platform used in the UK so contractors are used to working with this form of specification.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is NBS Chorus?

A

A cloud based collaborative specification platform that is used internationally. It allows construction professionals to produce high quality specifications efficiently.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is a schedule of works?

A

A description of the work in list format often used on smaller projects or those involving alteration works prepared by designers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What supporting documentation could you include within a specification the contractor(s)?

A

Specialist surveys such as structural engineers reports, drainage surveys, asbestos register etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What does the pre-construction information contain?

A

The information that is in the client’s possession or which is reasonably obtained relevant to the works and is of appropriate detail proportionate to the task.
Includes:

  1. Project description.
  2. Client’s considerations and management requirements (hoarding, welfare, traffic restrictions).
  3. Environmental restrictions and existing on site risks (ground conditions, buried services, asbestos surveys, local infrastructure - adjacent railways etc).
  4. Significant design and construction hazards (design risk assessments, suggested method statements).
    Health and Safety file requirements.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the different types of specification?

A

Prescriptive.
Performance.
Descriptive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Name and explain the different types of specification.

A

Prescriptive specifications: Provide detailed descriptions of specific materials to use and how they should be installed.

Performance specifications: Addresses the operational requirements of a installation. The focus is on the project outcome, indicating how it must function, it is up to the contractor how they achieve this.

Descriptive specifications: Designer controls design intent and defines the performance criteria. Specialist contractor uses skills and expertise to complete the design whilst maintaining the design intent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What types of specification would you use for different procurement routes?

A

Prescriptive specification: Traditional

Performance specification: Design and Build

Descriptive specification: construction management & management contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are the building regulations?

A

Statutory instruments that set our the minimum performance standards for the design and construction of buildings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are the approved documents?

A

They provide general guidance on performance and materials expected in order to comply with the functional requirements of the building regulations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Who ensures that the building regulations are complied with?

A

Building control services:
1.Local Authority.

2.Approved Inspector.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is the procedure for obtaining building regulations approval?

A

Dependent on the nature and the scale of the works.

Full plan application: Plans and construction details need to be reviewed prior to starting on site. There may be conditions attached to the approval. Lasts 3 years from notice of approval.

Building notice: Allows work to commence upon giving notice. No need to wait for prior approval before commencing the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What happens is a project contravenes the building regulations?

A

Magistrates Court can penalise the offending party up to £5,000. They can then issue a fine of £50 per day for every day that the works continue to contravene the building regulations.

Local authority can issue an enforcement notice which requires for the works to be made compliant or the local authority can undertake the works themselves then recover the associated costs if the building owner does not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Who is responsible for ensuring compliance with the building regulations?

A

The person who carries out the works. So if the owner does themselves they do but if employing a contractor it is the contractor’s responsibility.

Should bear in mind that ultimately the building owner will be served an enforcement notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Why did you choose an Approved Inspector?

A

Generally more responsive and open to giving advise.
Often present lower costs compared to building control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What documents will building control provide?

A

Plan Certificate: AI / LA review plans and proposed works to confirm whether the works will comply to the building regulations in principal.

Final Certificate: AI / LA issue following inspection of the completed works to certify that they are compliant with the building regulations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What would your duties as a designer under the Construction (Design and Management) Regulations 2015?

A

Ensure the client is aware of their client duties under the regulations prior to undertaking any design work.

Take into account any pre-construction information provided by the client / PD.

Eliminate foreseeable health and safety risks to anyone affected by the project (as practically possible).

Take steps to reduce and control residual risks.

Provide design information to the PD to include in the pre-construction information and health and safety file.

Provide design information to the principal contractor (or contractor on single contractor projects) to help them comply with their duties e.g ensuring Construction Phase Plan is prepared.

Communicate, cooperate and coordinate with:
1. any other designers to ensure all designs are compatible and ensure H&S.
2. all contractors to utilise their experience of building design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What is a budget cost plan?

A

Breakdown of the works required for a project and their anticipated costs.

Document is prepared to indicate the budget needed for a project.

Allows client to present the budget to the board to apply for funding and to determine whether the project is financially feasible.

Would form part of feasibility studies during stage 1 of RIBA.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What is the Regulatory Reform (Fire Safety) Order 2005 for ensure fire safety of a building?

A

Covers England and Wales.

Places responsibility for anyone who has some sense of control in a premises to take reasonable steps to reduce the risk of fire and make sure people can escape safely if there is one. The order applies to all premises whether they are permanent of temporary.

The fire safety act 2021 has now amended the act which means any premises with two or more domestic dwellings must undertake a Fire Risk Assessment which takes into account the structure and external walls (from outer cladding to internal plasterboard), attachments to the external walls (balconies and green walls etc), doors and windows within external walls, doors between domestic premises and common parts (flat entrance doors) and any common parts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Under the Regulatory Reform (Fire Safety) Order 2005 who is responsible for the fire safety in business or non-domestic premises?

A

The responsible person – any person who has a sense of control over a premises, this can include:

Employers
Owner.
Landlords.
Occupier.
Anyone else with control of the premises e.g facilities manager, managing agent etc.

If there is more than one responsible person, these individuals are expected to work together to meet their responsibilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

How do you consider sustainability in your design?

A
  • When am I required to provide increased thermal performance?
  • Thermal elements subject to renovation should be improved to achieve improved u value requirements provided the area is greater than 50% of the surface of the individual element or 25% of the total building envelope
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What is a threshold value?

A
  • Where an element falls below the threshold value, it should be upgraded to achieve an improved value.

Upgrading thermal elements – U-values W/m2K:
- Wall cavity insulation – threshold 0.70 improved 0.55
- Wall external / internal insulation – threshold 0.70 improved 0.30
- Floors – threshold 0.70 improved 0.25
- Pitched roof insulation ceiling level – threshold 0.35 improved 0.16
- Pitched roof insulation rafter level – threshold 0.35 improved 0.16
- Flat roof with integral insulation – threshold 0.35 improved 0.16

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What is consequential improvement?

A
  • Applies to existing building with total useful floor area over 1000m2, where the works consists of or includes; an extension, the initial provision of any fixed building services, an increase to the installed capacity of any fixed building services.
  • Where the works fall into the above, additional works should be undertaken to ensure the building complies with part L, providing a payback of 15 years can be achieved.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

TG - How did you specify the strip out?

A
  • Removal of all fixtures and fittings, including cubicles, soap dispensers, WC pans, basins, waste pipework and dead legs, existing doors, flooring, etc.
  • Hand dryers are on hire so advised to set aside re installation
  • Cap all pipework and take all cabling back to supply
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

TG - How did you specify the sanitaryware installation?

A
  • Sanitaryware to be connected to fresh and foul water supplied to effectively supply and discharge as necessary
  • Waste pipework to MUPVC to BS 5255 or PVC-C to BS EN 1566-1
  • 2no. standard WC pans with 4.5litre dual flush valve
  • 2no. urinals waterless in vitreous china w/ concealed cistern
  • 1200mm solid surface wash trough with 12mm compact grade laminated access panels
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

TG - How did you specify the installation of cubicles?

A
  • 12.5mm compact grade laminate with black core and radiused edges and anti-trap hinges
  • 18mm melamine faced chipboard, satin anodised aluminium fittings
  • Colours to be chosen by the school
  • Cubicles to be plugged and screwed into the concrete flooring
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

TG - How did you specify the flooring installation? Why?

A
  • Break out existing floor tiles, back to floor slab (concrete)
  • Prepare existing floor screed and apply 3mm latex finish
  • Install 2.0mm PUR floor covering, bonded to screeded floor using approved adhesive and laid in accordance with manufacturer’s instructions
    o Provide guarantee of 10 years defective materials
  • Why – long-lasting, waterproof, and non-slip materials for wet room such as WC and comes with guarantee
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

TG - How did you specify the wall cladding?

A
  • Strip existing walls of all paint
  • Supply and install 12.5mm insulated dry lining plasterboard throughout all walls
  • Add skim coat onto plasterboard for smooth finish
  • Installation of white rock panel from floor to ceiling
    o Ensure for 2-3mm gap between each panel and abutments – ceiling windows, etc.
    o Use Altrofix W139 for all welded installations
    o Apply adhesive to back of panel 25-30mm from edge and check it is level
44
Q

TG - How did you specify to install the plasterboard?

A
  • Align thermal liner squarely on wall, allow 15mm expansion joint at top and bottom
  • Trowel continuous ribbon of adhesive around wall edges, openings and services penetrations
  • Place thermal liner into position and tap into position using straight edge
  • Vertical dabs at 300mm cs 25mm from edge, dabs 50-75mm wide and 25mm deep to allow for temping – total contact 20% of wall
  • Ensure 50mm continuous ribbons at top and bottom and around openings
  • When adhesive is dry, fix 2 mechanical fixings through the centre of the board
45
Q

TG - What was the contractor’s design portion?

A
  • Included within the specification a section for each detailing what is required
  • Specified requirements for sanitaryware:
    o 2no. WCs, 2no. urinals (boys) 4no. WCs (girls) wash troughs for each
    o Water heater – to be installed beneath sink in vanity unit
  • Specified requirements for lighting / electrics:
    o Thorlux lighting in each room – lux level 100 – IP rating IP24
    o Hand dryer
    o Small power and fused spurs – in locations away from each of pupils
46
Q

TG - What data sheets did you include

A
  • Flooring – Polyflor verona
  • Lighting – Thorlux down lighting
  • Decorations – dulux trade/ white rock
  • Cubicles
47
Q

TG - What British Standards did you reference?

A
  • Fresh and foul water pipework – BS 5255 or BS EN 1566-1
  • Vinyl flooring installation – BS 8203:2001
  • Electrical installation – lighting installations – BS 7671
  • Electrical installation – test switches – BS 5266
  • Plasterboard installation – openings and service penetrations – BS 8121: 1986 & BS 800: Part 8: 1994
48
Q

TG - What did you include in the tender package?

A
  • Project preliminaries and summary
  • Materials and workmanship (preambles)
  • Schedule of works
  • Appendices:
    o Drawings
    o Asbestos survey
    o Finishes schedule
    o Data sheets
    o Pre-construction information
49
Q

What is a finishes schedule?

A
  • Form of product specification outlining materials desired – e.g. flooring, wall and ceiling materials, doors, colours for decorations, specified lighting
50
Q

When do you appoint a specialist sub-consultant?

A
  • When works out of my area of expertise – e.g. M&E or recommending structural works
51
Q

What is the gap required between WC and cubicle door?

A
  • 450mm minimum
52
Q

TG - How is the slip resistance of a floor calculated?

A
  • Using a pendulum test – anything above 36 is classed as a safety / non-slip floor
  • Verona PUR PolySafe flooring
  • RRL Pendulum Test - >36 (wet test – 4S, Rubber/Slider 96) classification P3
  • Wet slip resistance is sustainable throughout the guaranteed life of the product in adherence with HSE guidelines
  • Pendulum arm swings slider over test sample in wet and dry conditions
  • Readings taken referred to as British Pendulum Number (BPN)
  • Higher the number, the better the slip resistance value (SRV)

Pendulum mean BPN:
- >55 – P5
- 45-54 – P4
- 35-44 – P3
- 25-34 – P2
- 12-24 – P1
- <12 – P0

53
Q

What were the extract requirements?

A
  • Approved Document F (Ventilation)
  • 25l/s per WC / urinal – minimum intermittent extract rate
54
Q

TG - What designs do you have to consider for a primary school?

A
  • Correct height WC pans
    o 300-305mm for 3-6 years
    o 355mm for up to 11 years
  • Correct height sinks
    o Early years – 500mm
    o KS1 – 700mm
    o KS2 / primary – 750mm
    o Secondary / adult – 750-850mm
  • Correct height cubicles
    o Early years – 1200mm
    o KS 1 – 1350mm
    o KS2 – 1500mm
    o KS4 / adult – 2000mm
  • Temperature of taps – 32 degrees to avoid scalding children
  • No exposed pipework – keep within vanity units / boxing
55
Q

TG - What items did you specify for a moist environment?

A
  • Safety flooring
  • Whiterock cladding for all walls
  • Good quality ironmongery
  • Extract fan
  • Moisture resistant paint
  • Moisture resistant plasterboard
56
Q

Alma- What areas did you look at in respect of fire compartmentation?

A
  • Quality of doors throughout circulation areas and classrooms
  • Identifying presence of fire-stopping to services
  • Looking into roof voids to look at compartmentation between classrooms
57
Q

Alma - What did you observe?

A
  • Gaps, missing self-closers, damaged smoke seals to doors
  • Corridors – open vents between classroom walls and circulation areas
  • Lack of fire-stopping to services
  • Incorrect signage to non-fire rated doors
  • Lack of separation between classrooms in roof voids
58
Q

What are the minimum requirements for a fire rated door?

A
  1. Check for fire rated labels – e.g. BMTrada or FIRAS certified
  2. Check for signage – e.g. fire door keep shut
  3. Door levers & furniture – operatives smoothly and returns to position
  4. Lock and hatches – latch should hold door firmly in place without rattling
  5. Intumescent fire and smoke seals – swell up and expand in a fire to stop smoke / toxic gases
  6. Hinges – 3 hinges each with 4no. screws should be in place
  7. Gaps – an even gap around the door and frame should not exceed 3mm
  8. Mechanical door closer – should be fitted securely, free from damage, no leaking oil
  9. Electro-mechanical hold open devises – should be linked to fire alarm system and traced
59
Q

Alma- Why did you specify JCT MW with Contractor’s Design?

A
  • To enable a specialist sub-contractor to design the fire upgrades to satisfy BS 8214: 2016
  • To ensure specialists were in place to certify all new upgrades
  • To provide documentation at the conclusion of works to enable the school to have accurate records for future reference
60
Q

What does a fire door need to have?

A
  • Should be appropriately fire rated and the associated frame should have the same fire rating!
  • Should open in the direction of escape if more than 60 people are anticipated to be using the escape route.
  • Intumescent strip and cold smoke seal fitted to the tops and side of the door leaf or the frame itself.
  • Door closer.
  • 3 sets of fire rated hinges to each door.
  • Vision panels formed of fire rated glass (if the fire doors on escape routes divides corridors or the door is hung to swing both ways)
  • Gap between door and frame should be 2-4mm.
  • Fire door signs should be fitted to both sides of the door.
  • Fire door retainer (dorgard) can be installed to legally hold open the fire door - the system holds the door open but will automatically release in response to the sound of a fire alarm.
61
Q

Alma- What fire compartmentation did you specify?

A
  • FD30 fire rated doors to each classroom
  • FD60 fire rated doors to double doorsets in circulation areas
  • Filling each open vent with FD30 fire rated plasterboard (pink plasterboard)
  • 1 layer of fire-rated 12.5mm pink plasterboard, 1 layer 18mm ply, fire-rated insulation infil in cavity with stud partitions, 18mm ply, 12.5mm pink plasterboard
62
Q

Alma- What did you specify for the fire-stopping of services?

A
  • Rockwool Firepro HS firestop compound
    o Unsupported spans up to 1800mm
    o High load bearing capacity
    o Multiple or single service penetrations
    o Formed into blocks
    o Setting time between 30 and 90 minutes
  • Installation: trowel stiff mix into opening to correct depth, using non-combustible shuttering material to support the mix until it sets for larger holes
    o Pre-cast into blocks
    o Fit closure device / material fitted to each services before installation (e.g. pipe collars)
  • Rockwool firepro pipe collars CE
    o High performance intumescent
    o Up to EI240 fire resistance
    o Suit plastic pipes ranging from 32mm to 160mm
  • Installation:
    o Solid block, masonry walls – need min thickness of 100mm
    o Ensure firestop compound is used around the penetration
    o Lock the pipe collar around the pipe by closing the fixing strap, push collar flush to surface of the wall
    o Fasten with fire rated fixings - 3no 80mm steel pigtail screws
  • Rockwool firepro high expansion intumescent sealant
    o Sealing combustible pipe and metal pipes with combustible insulation
    o Compatible with cPVC pipes
  • Installation:
    o Prepare joint by cleaning surface, gun firmly into the joint to give good solid fill to required depth
63
Q

Alma- What certification did you specify for each fire rated element?

A
  • FIRAS certification or equal and approved
  • BMTRADA for the fire-stopping to services, each of which were labelled with:
    o Reference number to trace information
    o Installer operative details
    o Product details and brand (Rockwool)
    o Date of installation
    o Fire rating – 60 minutes
    o Type of fire stopping – e.g. to penetrations
64
Q

Alma- How do you achieve fire compartmentation?

A
  • Fire resisting construction cavity barriers, with fire stopping as necessary
  • Installation of
  • Approved Document B defines as cavity as “any concealed space”, cavity barriers should be provided in the following situations:
    o To divide cavities at junctions and cavity closures
    o Close the edges of cavities at junctions and cavity closures
    o To protected escape routes
    o To cavities affecting alternative escape routes
  • Fire doors with frame and furniture, must meet requirement of BS 476-22 or BS EN 1634-1
  • Extending each partition into the roof space to ensure compartmentation of each classroom
65
Q

What are the requirements of approved document B for fire doors?

A
  • Approved Document B2 – Buildings Other than Dwelling Houses
  • In a common parts, forming part of a protected stairway the doors must be FD30S
  • In compartment walls separating buildings must be a minimum of FD60
66
Q

What widths are the doors required to be?

A
  • Basis provided in approved document M2 (access and use of buildings other than dwellings)
  • 750mm for existing buildings, 775mm at right angles to access routes at least 1200mm wide.
  • BS9999 provides a more fire engineered calculation, based on the use, risk categories and occupancy characteristics.
67
Q

Can you specify FD20 Doors?

A
  • Mentioned in approved document B, however in 2017 the BWF (British Woodworking Federation) recommended that FD20 standard no longer be recognised.
68
Q

What are the changes to approved document B?

A
  • Combustible cladding/materials banned on new high rise homes over 18m tall
  • Testing and classification of composite fire door sets – 28th August 2018
69
Q

How does this relate to fire doors?

A
  • On the 31st July 2018 the department of Housing, communities and local government wrote to building control bodies alerting them to the need to check the performance of fire resisting door sets.
70
Q

What were the recommendations of the Hackitt Report?

A
  • A new regulatory framework for multi-occupancy higher-risk residential buildings that are more than 10 stores in height
  • A joint competency authority, comprising building regs, Fire and Rescue and HSE to oversee safety risks in these buildings
  • New dutyholder roles aligned with the CDM regulations
71
Q

What is BS 8214?

A
  • Code of Practice for timber based fire door assemblies
72
Q

What is BS 476?

A
  • BS 476: Part 22
  • Fire tests on building materials and structures
73
Q

What other fire safety guidance did you refer to?

A
  • Building bulletin 100: Design of Fire Safety in Schools
  • Required FD30S for enclosing a protected stairway
  • FD60S in walls separating buildings
74
Q

What is the typical thickness of a fire door?

A

44mm

75
Q

Alma - What was the specification of the glazing within the fire doors?

A
  • Within a critical area as defined in approved document K
  • Falling into a zone 1500mm from the floor within a door, 300m horizontally from the edge of the door
  • 800mm from the floor surface in all other areas
  • Fire rated glass must be used within fire doors
76
Q

What are the types of glazing?

A
  • Toughened
  • Annealed
  • Laminated
  • Heat strengthened
77
Q

How are fire doors tested?

A
  • Tested under BS476 part 22
  • Certificate provided – FIRAS, BMTrada or equivalent
78
Q

Alma - What was the ironmongery specification?

A
  • BS1935 – Building Hardware – Single Axis Hinges
  • BS EN 1154 – Building Hardware – Controlled door Closing Devices
  • BS1155 – Electrically Powered Hold Open Devices
79
Q

How did you know the door sets were compliant?

A
  • FIRAS Certification for the installers
  • BWF Certifire certification
80
Q

Alma - What information was presented on the test certificates?

A
  • Door type, location, size, fire rating, date of installation
81
Q

What labels would be fitted to the door?

A
  • BWF CERTIFIRE tickers, states the fire door rating.
82
Q

What is a nominal fire door?

A
  • A door set that is not certified, but in the opinion of an assessor would hold back the fire for a specified period of time.
83
Q

How did you ensure that the contractors fitting the doors were competent?

A
  • FIRAS Installer Certification Scheme
84
Q

What standards did you review?

A
  • ASDMA (Architectural and Specialist Door Manufacturers Association) – Guidance on installation.
  • BB100 – Design for fire safety in schools
  • Approved Document B, Volume 2 – Buildings other than dwelling houses
  • BS9999: 2017 – Fire Safety in design
  • BS EN 1935 – Single Axis Hinges
  • BS EN 1154 – Door Closers
  • BS8214: 2016 – Timber based fire door assemblies
85
Q

What features would you expect to find on a fire door?

A
  • Intumescent strips
  • Self-closers
  • Hold open devices
  • Fire rated door glazing
  • Push plates, kick plates, d-handles
  • Stickers/markings on the top edge noting the fire resistance, certification and manufacturers information.
86
Q

What is the minimum gap around fire doors?

A
  • BS9999 – where fire doors with smoke control strips the gap should be less than 3mm in height.
87
Q

What are cold smoke seals?

A
  • Placed between the door and frame on all sides, used to prevent smoke passing through the gaps
88
Q

What are intumescent strips?

A
  • Intumescent strips are chemically designed to expand when exposed to heat, used to seal the gap around the frame.
89
Q

What are the British Standards for pitched roof works?

A
  • BS 5534: 2014 – Slating and tiling for pitched roofs and vertical cladding
  • BS 5250: 2011 – Code of practice for condensation control in buildings
90
Q

What was the 2018 update to BS 5534?

A
  • Ensure underlays are installed with a maximum drape of 15mm
  • Avoidance of underlay exposure for more than a few days during installation
  • Checking of underlay zonal classification label
  • Standard states this may not be suitable for roofs on historically or architecturally important building.
91
Q

OFS - What did you specify for pitched roof renewal?

A
  • Marley vapour permeable membrane with BS 5534 25x38 treated battens
  • Acme clay classic plain tiles – hung on 2no. nail fixings (aluminium 38mm – do not rust)
  • Double course to eaves and ridges
  • Tile & half’s to alternate courses at abutments and verges
  • Marley 10mm eave vent system to eaves
  • Marley dry vented ridge system with segmental ride
  • Code 4 lead soakers, code 5 cover flashing to abutments
  • Code 5 lead flashings to chimneys and back gutter
92
Q

Why was this considered over refurbishment/localised tile repairs?

A
  • Pitched coverings were approx. 25% patch replaced – safe assumption that the system is failing and roof tiles need to be replaced in their entirety
  • Health and safety incident whereby a roof tile slipped into the courtyard – assessment made of condition of existing battens / tiles
93
Q

What were the existing roof coverings?

A

were the existing roof coverings?
- Tile coverings
- Cold deck construction

94
Q

What type of pitched roof was it?

A
  • Mansard & pitched – 1898 Victorian building
95
Q

What was the pitch, what head lap did you specify?

A
  • High pitch with 65mm head lap
96
Q

Did this incorporate additional insulation?

A
  • Yes – incorporated insulation at loft level (not rafter) to achieve 0.16 U-value due to consequential improvement
  • Insulation – Knauf loft roll 44 270mm insulation
97
Q

What are the types of roofing underlay?

A
  • Breathable & non-breathable
98
Q

What is the difference between a breathable and non-breathable underlay, and when would these be used?

A
  • Non-breathable are non-permeable (e.g. bituminous or polypropylene)
    o Most cost effective and functional
    o Low level (eaves) and high level (ridge) ventilation systems
    o Locations where roofs require counter-battens to ventilate the batten void
  • Breathable (low resistance) – lightweight, durable, easy to install
    o Vapour permeable – used as roof ventilation but must be used with high-level ventilation according to BS & NHBC
    o Vapour and air permeable
99
Q

What are the British Standards for roofing underlay?

A
  • BS 5534
    o Ensure underlays are installed to max 15mm drape – prevents transfer of wind loads (ballooning) roof covering
    o Avoid leaving underlays exposed – over exposure to UV light or freeze/thaw could lead to degradation of underlays – underlays should not be exposed for more than a few days
  • BS 5250
    o In case of LR vapour-permeable underlays, designers must ensure manufacturer’s stated water vapour resistance values are suitable for application
    o These underlays should comply with BS EN 13859-1
100
Q

OFS - Was any statutory permissions required?

A
  • Building Control
  • Planning permission – was enquired, and a meeting with planning officer was arranged – was advised spec was in line with regulations so no planning permission required
  • Windows – self certification
100
Q

What was the cause of the parapet wall cracking?

A
  • Rainwater goods original – not wide enough to accommodate more rain
  • Caused breakdown of asphalt roof coverings & walls – water ingress internally
  • Corroded steel filler joists which expanded their volume and pushed brickwork outwards
  • Significant cracking
101
Q

Describe the specification for the parapet wall rebuilding

A
  • Remove soldier course across all elevations down to creasing tiles, keep intact bricks for reinstallation – any defective bricks replaced with matching
  • Remove creasing tiles and mortar and dispose
  • Take down brick courses to 2no. courses beneath cracking
  • Rebuild brickwork using NHL 3.5 mortar, with the same or matching bricks
    o Provisional rate allowed for, for each parapet wall section
  • Install new creasing tiles & soldier course with NHL 5 mortar
102
Q

How did you specify the overlaying of the flat roof coverings?

A
  • Ensure building remains watertight at all times – areas of the roof remained in a single day must be done so ensuring the provision of night joints
  • Heat up lumps, rolls, blisters, cracks, etc. in asphalt and iron out to provide a smooth surface
  • New 3-layer waterproof system to be installed with insulation
  • New system incorporating new internal gutter channels using lead chutes linking to existing cast iron rainwater goods
  • In accordance with the manufacturer’s specification
103
Q

How did you specify the replacement of the flat roof covering?

A
  • Ensure provision of night joints
  • Top hat scaffold required
  • Strip asphalt from roof, including to upstands and main roof field down to concrete deck
  • Break out clinker concrete slab & safely remove filler joists
  • Install new timber joists (75mm x 220mm) at 600mm centres, ensure for hard packing e.g. slates or tile to bed into mortar in brickwork
  • Joists placed on fixed wall plate bedded into mortar on top of the inner skin and strapped using galvanised holding-down straps
  • Install roof deck of exterior grade 18mm plywood, embedding into brickwork
  • 3-layer waterproof system with 130mm insulation to achieve 0.16W/m2K U-value
104
Q

How did you specify repairs to cracking?

A
  • Installation of helical bars – threaded bars embedded into mortar joints
  • Rake out or cut slots into horizontal mortar beds minimum 500mm either side of crack
  • Clean slots and thorough soak substrate within the slot
  • Inject a bead of resin along back of the slot
  • Push helical bar into grout to obtain good coverage
  • Use further bead of resin over exposed bar, finishing 12mm from face
  • Repoint mortar bed and make good vertical crack
105
Q

What does NHL mortar number show?

A
  • Mean compressive strength after 28 days
106
Q

How did you specify the render replacement?

A
  • Contractor to undertake tap test with CA in attendance to assess bonding of existing – remove all loose render
  • Hack off blown sections, cut back to brickwork, form square undercut edges
  • Rake out brickwork joints to provide a key
  • Apply 12mm scratch coat of lime mortar to smooth contours of the wall, leave to dry 5-7 days – NHL 3.5 x 2 coats
  • Apply levelling coat not exceeding 12mm, scrape back with straight edge to level surface, leave to dry NHL 3.5 x 2 coats
  • 5-7mm finishing coat, progressively thinner / weaker lightly rubbed to achieve smooth finish – NHL 3.5 x 1 coat
  • Requested provisional sqm quantities from the contractor