Construction Tech - All Saints Flashcards

1
Q

Give an overview of the works specification

A
  • Strip out of existing WC – including all M&E, cubicles, flooring, shelving, sinks, sanitaryware, windows ceiling covering
  • Installation of new sanitaryware including 1no. new WC, new drainage, cubicles, M&E, sinks, hand dryers, windows, decorations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How did the specify the strip out?

A
  • Strip out existing fixtures & fittings (e.g. shelving, cubicles, doors, flooring, ceiling, etc.)
  • Strip out M&E – lighting, hand dryers, ventilation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did you specify the installation of new WCs?

A
  • Sanitaryware to be connected to fresh and foul water supplies
  • Contour 21 back to wall rimless standard height WC pan
  • Conceala 2 cistern 4.5/3 litre dual flush valve side supply
  • Contour 21 seat no cover, top fixing hinges and retaining buffers
  • Contemporary flush plate dual flush
  • All fixed into existing waste pipework – new waste pipework as described before
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How were the cubicles fixed?

A
  1. Mark out centre lines of each partition, ensuring all verticals are plumb
  2. Attach D brackets to wall using screws and wall plugs, space evenly
  3. Position leg 100-150mm from front of partition, drill through and secure with T nuts
    a. Place partition between the brackets 100mm above floor level
    b. Drill through the partition and secure with T-nuts
  4. Attach 3 brackets to middle pilaster
  5. Drill through partition and secure pilaster with T-nuts through D brackets
    a. Secure leg to floor with a screw
  6. Attach 3 D brackets to opposite wall using screws and wall plugs
  7. Position end pilaster 100mm above floor and drill through, secure with T nuts through D brackets
  8. Position header rail and drill through pilasters
  9. Attach bottom part of hinge plate via pre-drilled holes on pilaster
  10. Attach other part of hinge to door with T nuts via pre-drilled holes
  11. Hang door by slotting hinge parts together making sure screw is then fitted, add 2 rubber buffers to where door meets other pilaster
  12. Ensemble latch in pre-drilled holes
  13. Test door / lock to ensure installation is correct
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How was the flooring laid?

A
  • Remove all fixtures / fittings – all sanitaryware
  • Measure dimensions of the room
  • Mark out all locations / measurements of the fixtures, fittings and sanitaryware
  • Concrete underlay – due to breaking out of tiles floor slightly uneven so concrete was screeded
  • Lay out vinyl as flat as possible, press into angle between floor / wall with bolster chisel to make a sharp crease
  • When whole vinyl sheet is laid, lift edges and stick to sub-floor with adhesive – polyurethane based products
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What flooring did you specify?

A
  • Polyflor Verona – safety flooring
  • Came with warranty that stipulated non-slip throughout its lifetime
  • RRL Pendulum test value = >36
    o Anything over 35 is classed as non-slip safety floor
    R Rating of R12 (suitable for public lavatories)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is the slip resistance of a floor calculated?

A
  • Using a pendulum test – anything above 36 is classed as a safety / non-slip floor
  • Verona PUR PolySafe flooring
  • RRL Pendulum Test - >40 (wet test – 4S, Rubber/Slider 96) classification P3
    R Rating - R12
  • Wet slip resistance is sustainable throughout the guaranteed life of the product in adherence with HSE guidelines
  • Pendulum arm swings slider over test sample in wet and dry conditions
  • Readings taken referred to as British Pendulum Number (BPN)
  • Higher the number, the better the slip resistance value (SRV)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What items did you specify for a moist environment?

A
  • Safety flooring
  • Whiterock cladding for all walls
  • Good quality ironmongery
  • Extract fan
  • Moisture resistant paint
  • Moisture resistant plasterboard
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How did you advise that the ventilation was inadequate?

A
  • The existing ventilation consisted of an air brick with external grille
  • No mechanical ventilation was present
  • I knew this did not comply with Approved Document F: Ventilation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What ventilation did you install? What are the requirements?

A
  • 2no. Vent-axia axial inline extractor fan with timer 240v
  • Mounted in ceiling void
  • Aluminium insulated flexible ducting – insulation required so that air temp maintained and vapour does not condense in duct
  • Requirements – 15 litres per second per shower / bath, 6 litres per second per WC pan or urinal
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How did you specify the installation of drainage?

A
  • Dig trench to appropriate depth (circa 900mm) and width (410mm – 110mm pipe, 300mm wider than pipe itself)
  • Ensure 1:80 gradient – 25mm height fall per metre
  • PVC 110mm pipework to BS EN 1566-1
  • Lay pipework as follows:
    o Lubricate connector and pipe
    o Push connector onto pipe
    o Lubricate receiving connector and open end of pipe
    o Push next length of pipe into connector
  • Surround new drainage with 110mm pea shingle, backfill with selected as dug material, compacted in layer not exceeding 300mm
  • Internally: 110m pea shingle, around pipe compacted in layer not exceeding 150mm, up to 215mm below finished floor level
  • Covered over with new tarmacadam
  • New pipework directly connected into existing foul water system
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How did the contractor dig out the playground?

A
  • Used a jackhammer to break out the existing concrete / hard wear surface, to expose shingle, made up ground beneath
  • Spades used to move material into buckets and set aside
  • Contractor ensured exclusion zone and chapter 8 fencing around perimeter
  • Wore appropriate PPE:
    o Gloves
    o Safety goggles
    o Ear defenders
    o Safety shoes
    o Long sleeved work trousers & jacket with hi vis
    o Head protection
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How did the contractor de-risk the project?

A
  • PPE & risk assessments
  • Working with competent persons
  • Ensured all designs approved before proceeding
  • Allowed for enough time within programme of works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What building regulations refer to drainage?

A
  • Approved Document H – drainage & waste disposal
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What approvals are required?

A
  • Building control approval – approve laying of pipework and assessing of trench size, gradient before backfilling
  • Approved inspector issued completion cert once all installation complied with regulations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What approvals are required?

A
  • Building control approval – approve laying of pipework and assessing of trench size, gradient before backfilling
  • Approved inspector issued completion cert once all installation complied with regulations
17
Q

Did you opt for Approved Inspector or Building Control approval? Why?

A
  • Approved inspector
  • Generally more responsive / advisory than building control
  • Provided a cheaper quotation
18
Q

Was there a requirement for accessible WCs?

A
  • No – the school had accessible WCs elsewhere within the building
  • Accessible WC was not possible due to the size of the WC area refurbished
19
Q

What certification did the contractor submit?

A
  • All live electrical installation – NICEIC certification
  • Building control certification
  • Guarantee for the non-slip flooring
20
Q

What are the maximum fittings consumption for WCs, basin taps, sink taps?

A
  • WCs – 6/4 litres dual flush or 4.5 litres single flush
  • Basin taps – 6 l/m
  • Sink taps – 8 l/m
21
Q

What wash hand basin & taps did you specify?

A
  • 1200mm solid surface wash trough with 12mm grade laminated access panels and fascia to suit
  • 3no. tap holes at 400mm centres – no further than 250mm from each end panel
  • 3no. non concussive mixer taps, with a timer of 10 seconds
  • Ensure tap temperature suitable for child use – 32 degrees maximum
  • Ariston under sink water heater – 2kW 15ltr, allowing for new copper pipework and expansion vessels
    o To BS EN 60335-2-35 BEAB approved, installation to BS EN 806-4
22
Q

What designs did you advise for infant school children?

A
  • Correct height WC pans
    o 300-305mm for 3-6 years
    o 355mm for up to 11 years
  • Correct height sinks
    o Early years – 500mm
    o KS1 – 700mm
    o KS2 / primary – 750mm
    o Secondary / adult – 750-850mm
  • Correct height cubicles
    o Early years – 1200mm
    o KS 1 – 1350mm
    o KS2 – 1500mm
    o KS4 / adult – 2000mm
  • Temperature of taps – 32 degrees to avoid scalding children
  • No exposed pipework – keep within vanity units / boxing
23
Q

What IP ratings did you specify?

A
  • IP = Ingress Protection
  • Classifies degree of protection provided by an enclosure for electrical equipment with a rated voltage of no more than 72.5kV
  • Defined by British Standard BS EN 60529:1992
  • IP65 – first digit indicates level of protection against ingress of solid objects, second digit is protection against liquids