Contract Administration - Coopers Science Labs Flashcards
1
Q
Why did you advise use of traditional, single stage tender?
A
- Client required full design prepared before works were tendered and required a lump sum cost for the works to ensure cost certainty against projected budget
- Works relatively simple in nature and didn’t require contractor input for buildability
2
Q
How did you receive the tenders?
A
- Advised that tenders be submitted over e-signature
- This ensured all tenders submitted privately and to the deadline stated
- Ensured all tenders were opened in the presence of a chartered surveyor
3
Q
How did you analyse the tenders?
A
- Received all tenders
- Checked for arithmetical errors, obvious errors in programme dates and lead-in periods
- Checked for any obvious errors in pricing compared between contractors
- Clarified any mistakes / errors and then wrote a tender report
4
Q
What did the tender report include?
A
- List of tenders received
- Initial cost of the tenders
- Any qualifications / clarifications identified
- Post-tender adjustments
- Revised tender sums
- Comparison of tenders
- Recommendation
5
Q
What timeframe did you judge the materials order to be “in good time”?
A
- Pre-start meeting was 4 weeks before the commencement of the works to allow the contractor to mobilise
- Within this period, I expected the contractor to place the orders
- Order was not placed until 3 weeks into the contract (7 weeks from selection of colours)
- Late delivery had detrimental affect on installation of:
o Sinks and taps
o Gas taps and pipework installation
6
Q
The works were at a school (so no loss of rent) – what were liquidated damages calculated on?
A
- Additional fees above what was agreed within the fee proposal
- I based this on my time for travel, inspection and reporting to the client and calculated on this basis
- £600.00 was set within the preliminaries and agreed with the school
- All contractors tendered on this basis so were aware of this figure
7
Q
Why did you assess the client was due LDs?
A
- Contractor caused delay that affected the critical path
- Contractor did not mitigate the delay quickly enough
- Works were not completed on time
- Contractor did not submit a formal extension of time
8
Q
What is the critical path?
A
- Completion of tasks in an order whereby not completing a particular item will result in later items being unable to start
9
Q
How did the worktop delivery affect the critical path?
A
- Affected the second fix of the mechanical installation
- All sinks, taps, gas pipework was to be installed following
- Classroom unusable due to this
10
Q
Why did you issue a certificate of non-completion?
A
- Contractor responsible for the delay
- Works were not completed by the completion date
- Safeguarded the client so that they were entitled to claim LDs
11
Q
What certificate did you issue for liquidated damages?
A
- A pay less notice – the LDs amount was deducted from the contractor’s penultimate payment application
12
Q
What did you issue following completion of the works
A
- Practical completion certification was issued once I was satisfied that the works were completed free of patent defects
- All relevant certification was issued within O&M manual
13
Q
What certification did you require?
A
- Gas safe installation certificate
- Fire-stopping detailing to all service penetrations
- NICEIC live electrical installation certification
- Data sheets / information on type of flooring, LED lighting, furniture, decorations
- Building control approval certificate