Contract Administration - Coopers Science Labs Flashcards

1
Q

Why did you advise use of traditional, single stage tender?

A
  • Client required full design prepared before works were tendered and required a lump sum cost for the works to ensure cost certainty against projected budget
  • Works relatively simple in nature and didn’t require contractor input for buildability
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How did you receive the tenders?

A
  • Advised that tenders be submitted over e-signature
  • This ensured all tenders submitted privately and to the deadline stated
  • Ensured all tenders were opened in the presence of a chartered surveyor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did you analyse the tenders?

A
  • Received all tenders
  • Checked for arithmetical errors, obvious errors in programme dates and lead-in periods
  • Checked for any obvious errors in pricing compared between contractors
  • Clarified any mistakes / errors and then wrote a tender report
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What did the tender report include?

A
  • List of tenders received
  • Initial cost of the tenders
  • Any qualifications / clarifications identified
  • Post-tender adjustments
  • Revised tender sums
  • Comparison of tenders
  • Recommendation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What timeframe did you judge the materials order to be “in good time”?

A
  • Pre-start meeting was 4 weeks before the commencement of the works to allow the contractor to mobilise
  • Within this period, I expected the contractor to place the orders
  • Order was not placed until 3 weeks into the contract (7 weeks from selection of colours)
  • Late delivery had detrimental affect on installation of:
    o Sinks and taps
    o Gas taps and pipework installation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The works were at a school (so no loss of rent) – what were liquidated damages calculated on?

A
  • Additional fees above what was agreed within the fee proposal
  • I based this on my time for travel, inspection and reporting to the client and calculated on this basis
  • £600.00 was set within the preliminaries and agreed with the school
  • All contractors tendered on this basis so were aware of this figure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why did you assess the client was due LDs?

A
  • Contractor caused delay that affected the critical path
  • Contractor did not mitigate the delay quickly enough
  • Works were not completed on time
  • Contractor did not submit a formal extension of time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the critical path?

A
  • Completion of tasks in an order whereby not completing a particular item will result in later items being unable to start
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How did the worktop delivery affect the critical path?

A
  • Affected the second fix of the mechanical installation
  • All sinks, taps, gas pipework was to be installed following
  • Classroom unusable due to this
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why did you issue a certificate of non-completion?

A
  • Contractor responsible for the delay
  • Works were not completed by the completion date
  • Safeguarded the client so that they were entitled to claim LDs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What certificate did you issue for liquidated damages?

A
  • A pay less notice – the LDs amount was deducted from the contractor’s penultimate payment application
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What did you issue following completion of the works

A
  • Practical completion certification was issued once I was satisfied that the works were completed free of patent defects
  • All relevant certification was issued within O&M manual
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What certification did you require?

A
  • Gas safe installation certificate
  • Fire-stopping detailing to all service penetrations
  • NICEIC live electrical installation certification
  • Data sheets / information on type of flooring, LED lighting, furniture, decorations
  • Building control approval certificate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly