Design economics Flashcards

1
Q

What information is typically required for an OCE?

A
  • Site information (Location, restrictions, use)
  • Building information (Use, size, spec)
  • Enabling works/decanting
  • Programme
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the methods of producing an OCE?

A
  • Floor area method
  • Functional unit method
  • Elemental method
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the elemental method of producing an OCE?

A

Using rates and quantities from other similar projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What components make up an OCE?

A
  • Measured works
  • Prelims
  • OH&P
  • Fees
  • Risks
  • Inflation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you calculate Tender Inflation?

A

Inflation from the base date of your estimate to the date of tender receipt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do you calculate Construction Inflation?

A

Inflation from the date of tender return to the midpoint of construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why is construction inflation taken to the programme midpoint?

A

This should account for inflation on materials procured throughout the programme, but may need to be amended if large items such as plant are procured towards the very start/end of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the types of cost plan?

A
  • Stage 0: Rough OCE
  • Stage 1: OCE
  • Stage 2: Formal Cost Plan 1
  • Stage 3: Formal Cost Plan 2
  • Stage 4: Formal Cost Plan 3/Pre-Tender Estimate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Whats the difference between Whole Life Costing and Life Cycle Costing?

A
  • LCC is cradle to grave
  • WLC is LCC and other non-construction cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What ratios can affect construction cost and why?

A
  • Wall to floor (inefficient floor area using an expensive facade)
  • NIA to GIA (wasted sellable space)
  • Ceiling Height (Could be a waste of resources for no additional sellable space)
  • Building height (the point at which deeper foundations are needed can make the build inefficient)
  • Shape regularity (linked to wall to floor)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What sources of cost data are there?

A
  • Benchmarking
  • BCIS
  • SPONS
  • Market testing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are pros and cons of Benchmarking?

A

Pros
- Can be used for specific rates
- Provides a wide variety to give an average
Cons
- Need to take into account inflation and location factors
- Need to understand nuances to see if the data is applicable to your project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a fair net to gross?

A

70-80%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Whats a good wall to floor ratio?

A

0.4-0.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What’s the difference between cost and price?

A
  • Cost is Labour, Plant, and Materials
  • Price is what the Client pays, and it includes the Cost and OH&P
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you proceed if your cost plan exceeds the budget?

A
  • Check your assumptions to see how well they align with the designers’ intentions
  • Look at the reason for the overspend i.e. if the budget was based on another project, what makes this project different?
  • Look at potential value engineering solutions
17
Q

What is buildability?

A

A review during the design stage of how the components and will be manufactured and put together. Typically, this can be improved through early contractor involvement

18
Q

What is shell and core?

A

The main structure, basic services, and external shell of a building. It might also include fitting out common areas like a reception, with services leading to but stopping at tenant thresholds. Life safety equipment will typically be installed throughout however

19
Q

What is Cat A?

A

This is a fit out of basic finished such as ceiling tiles, Raised Access Flooring, carpets, and basic lighting and power

20
Q

What is Cat B?

A

This is full fit out with bespoke elements, internal walls, upgraded finishes, services feeding into floor boxes

21
Q

What is BWIC?

A

Builders Work in Connection. This is typically to take into account works such as drilling, fixing, cutting etc when they’re installing the services

22
Q

What are preliminaries?

A

Costs for items that are necessary for the Contractor to complete the works, but are not the works themselves

23
Q

What is typically excluded from a cost estimate?

A
  • VAT
  • Fees
  • Site acquisition
  • Section 106/CIL
  • Asbestos removal
  • Loose FF&E (Desks etc.)
24
Q

What is RIBA Stage 0?

A

Strategic Definition

25
What is RIBA Stage 1?
Preparation and Brief
26
What is RIBA Stage 2?
Concept Design
27
What is RIBA Stage 3?
Spatial Coordination
28
What is RIBA Stage 4?
Technical Design
29
What is RIBA Stage 5?
Manufacturing and Construction
30
What is RIBA Stage 6?
Handover
31
What is RIBA Stage 7?
Use
32
What is a base date of a cost estimate?
It is the date from which rates are based on
33
What does BCIS stand for?
Building Cost Information Service
34
What is Value Management?
An overall process of looking at what value mean to the client, and putting processes in place to try and ensure value is maximised in the first instance.
35
What is Value Engineering?
The process of maintaining form and function at a reduced price, or increasing form and function at the same price