Contract Practice Flashcards
What key contract rules came from the Housing Grants Construction and Regeneration Act 1996?
- Gives a right to adjudication
- Gives a right to stage/periodic/milestone payments for projects >45 days
- A payment notice MUST be issued 5 days after the due date
- Right to suspend work for non payment
- Removes pay when paid provisions
- Created the scheme for construction contracts to cover the above if they are not specified within the contract
What is the valuation procedure under a standard JCT
- Valuation date (fixed under the contract as a set date every month. But it must be a working day)
- 7 days (excl BH) later is the due date
- 5 days later is the payment certificate
- 14 days after the due date is the final date for payment
- 5 days before the final date for payment is the final date for a pay less
- Valuations must be done regardless of if the contractor submits their valuation or not
What is the valuation procedure under a JCT D&B
- Valuation date (fixed under the contract as a set date every month. But it must be a working day). If the contractor submits their valuation late, the following are pushed back by the same number of days
- 7 days (excl BH) later is the due date
- 5 days later is the payment certificate
- 14 days after the due date is the final date for payment
- 5 days before the final date for payment is the final date for a pay less
What is the timeline for adjudication
- Either party raises a notice of adjudication
- Within 7 days of the notice, an adjudicator is chosen (either already named in the contract or an adjudicating body) and the referring party must issue the adjudicator with a referral notice
- The adjudicator must make a decision within 28 days after the referral notice, or 42 days if the referring party consents, or longer if both parties consent
What powers does an adjudicator have?
- Ask for any documents/statements reasonably required
- Question any party to the contract or their representatives
- Visit sites and undertake tests
- Give directions as to the conduct of the adjudication
What must a notice of adjudication contain?
- The nature of the dispute and involved parties
- Details of where and when the dispute arose
- The nature of the redress which is sought
- The names and addresses of the parties of the contract
What is the effect of an adjudicator’s decision?
It is binding on all parties unless legal redress is sought
What is the effect of an arbitrator’s decision?
It is legally binding on all parties
What are the JCT contract sections?
- Recitals
- Articles
- Particulars
- Attestation
- Conditions
What are the contract recitals?
Factual explanations for the basis of the contract e.g. cost, where the drawings are, sections etc
What are the contract articles?
Sets out what is agreed
What are the contract particulars?
Aspects of the contract that are specific to the project
What is contract attestation?
- Confirming the agreement is genuine
- Under hand or deed
What are the principles of contract law?
- Offer
- Acceptance (might be by action, rather than a signature)
- Consideration
- Intention to create legal relations
- Capacity
- Legality (lawful purpose for the contract)
What are some contract documents?
- The contract
- Schedule of amendments
- Preliminaries
- Contract Sum Analysis or BoQ
- Section Sums (if applicable)
- Information release schedule
- Drawings
- Specifications
- Employer’s requirements
- List of named/nominated sub contractors
- Client policies (net zero, H&S etc)
- Pre-Construction Information pack
What is included in a Pre-Construction Information Pack?
Information about:
- The project
- Planning and management
- H&S hazards and how they are to be addressed
- Any existing H&S file
- ER’s and Contractor’s proposals
What are the types of contract?
JCT
- SBC
- MW
- IC
- D&B
NEC
FIDIC
What are the NEC Payment Options?
A - Priced contract with activity schedule
B - Priced contract with BoQ
C - Target contract with activity schedule
D - target contract with BoQ
E - Cost reimbursable
F - Management