Cost Flashcards

0
Q

What is EAC estimate at completion?

A

How much will the new project cost? What is the new cost baseline?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

EAC formula?

A
  1. Assumes performance will be at original BAC budgeted rate

EAC = AC + BAC - EV

  1. Assumes performance up to this point in the project will continue following CPI

EAC = BAC / CPI

  1. Accepts negative cost performance up to this point but insist project hit a firm completion date

EAC = AC + (BAC - EV)/(CPI x SPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is ETC estimate to complete?

A

How much money is needed to complete the remaining work?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is SPI?

A

How well is project using time?

EV/PV

>1 = ahead of sched
<1 = behind sched
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is CPI?

A

EV/AC

>1 = under budget
<1 = over budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly