Cost Flashcards
0
Q
What is EAC estimate at completion?
A
How much will the new project cost? What is the new cost baseline?
1
Q
EAC formula?
A
- Assumes performance will be at original BAC budgeted rate
EAC = AC + BAC - EV
- Assumes performance up to this point in the project will continue following CPI
EAC = BAC / CPI
- Accepts negative cost performance up to this point but insist project hit a firm completion date
EAC = AC + (BAC - EV)/(CPI x SPI)
2
Q
What is ETC estimate to complete?
A
How much money is needed to complete the remaining work?
3
Q
What is SPI?
A
How well is project using time?
EV/PV
>1 = ahead of sched <1 = behind sched
4
Q
What is CPI?
A
EV/AC
>1 = under budget <1 = over budget