Chapter 3 Scope Management Flashcards
Name two outputs of plan scope management process?
Scope management plan
Requirements management plan
Six processes of scope management?
Plan scope management Collect requirements Define scope Create wbs Control scope Validate scopep
Input to plan scope management?
Project charter
PMP
OPA
EEF
Tools of plan scope management?
Meetings
Expert judgement
Name output of plan scope management process?
Scope management plan: define process to document scope, process to create wbs control and validate scope.
Requirements management plan: define process to prioritize requirements, collect requirements and creating requirement traceability matrix.
Input to collect requirements process?
Stakeholder management plan Stakeholder register Project charter Scope management plan Requirements management plan
Tools of collect requirements process?
Interviews Focus group Facilitated workshops Delphi technique Mind maps Brainstorming Questionnaire
Examples of group decision making technique?
Unanimity
Majority
Plurality
Dictatorship
Outputs of collect requirements?
Requirement documents
Requirement traceability matrix
Inputs to define scope process?
Scope management plan
Requirements document
Project charter
OPA
Tools of define scope process?
Facilitated workshop
Expert judgement
Product analysis - analysing work needed to be done to achieve the deliverable
Alternative generation
Outputs of define scope process?
Project scope statement
Project document update
Inputs to create wbs process?
Scope management plan
OPA
Collect requirements outputs
I.e. Requirement document & requirement traceability matrix.
Define scope outputs
I.e. Project scope statement
Outputs of create wbs process?
WBS
WBS dictionary
Scope baseline
Inputs to control scope process?
PMP
Work performance data
Requirements document
Requirements traceability matrix