Chapter 4 Time Management Flashcards
Input to plan schedule management process?
OPA
eEF
PMP
Project Charter
Processes of time management?
- Plan schedule management
- Define activities: activities list
- Sequence activities: id & document in project schedule network diagram relationship among activities
- Estimate activity resources
- Estimate activity duration
- Develop schedule
- Control schedule
Tools of plan schedule management?
Analytical techniques
Expert judgement
Meetings
Output of plan schedule management process?
Schedule management plan:
-How to management plan
-Define criteria and process to develop, monitor & control e.g:
Level of accuracy
Performance measurement rules. EV, spi, sv
Reporting formats
Inputs to define activities process?
Schedule management plan
Scope baseline: project scope statement, wbs & wbs dictionary
OPA
EEF
Tools of define activities process?
Expert judgement
Rolling wave planning - iterative planning based on progressive elaboration / plan as you go
Outputs of define activities process?
- Activities list - lower lvl than wbs
- Activities attributes - description, relationship between activities and resourcing required
- Milestone list - important checkpoints of the project
Inputs to sequence activities process?
Activity list Activity attributes Milestone list Schedule management plan OPA EEF
Tools of sequence activities process?
- Precedence diagramming method (PDM) or network diagram
- Dependency determination
- Leads and lags
Outputs of sequence activities process?
Project schedule network diagram
Project document updates
Dependency determination - four major dependencies?
- Mandatory - often legally required.
- Discretionary - preferred logic.
- External - beyond the team’s control.
- Internal - within the team’s control.
Lead and lags?
Lead = start an activity before it’s predecessor is finished
E.g.
FS-5 days
Lags = delay before successor can start
E.g.
FS+3 days
Inputs to estimate activity resources process?
- Schedule management plan
- Activity list
- Activity attributes
- Resource calendars
- Risk register
- Activity cost estimate
- EEF
- OPA
Tools of estimate activity resources process?
- Expert judgement
- Alternatives analysis
- Bottom up estimating
- Published estimating data
- PM software
Outputs of estimate activity resources process?
- Activity resource requirements
- Resource breakdown structure - hierarchical structure of resources, organised by resource category and resource type
- Project document updates