Q

Inputs to plan risk management process?

A
PMP
Project charter
Stakeholder register
OPA
EEF
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

4 ways to deal with risks?

A

Avoid
Mitigate
Transfer
Accept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Tools of plan risk management process?

A

Expert judgement
Analytical tool
Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Outputs of plan risk management process?

A

Risk management plan

- risk breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Processes of risk management

A
  1. Plan risk management
  2. Identify risk - gather team create list using RBS
  3. Perform qualitative risk analysis - assign prob & impact on each risk
  4. Perform quantitative risk analysis - assign $ value to prob & impact
  5. Plan risk response - decide whether to avoid, mitigate, transfer or accept