Contract Practice Flashcards

1
Q
  • What is the difference between reasonable v best endeavors in contract terms?
A

Best endeavors is the most stringent method.
Reasonable endeavors in least onerous obligation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  • What is a collateral warranty? when would it be used? Who do they apply to? What are the disadvantages of a CW?
A

To bridge the contractual gap between parties who don’t have direct contractual relationship
Can apply to subcontractors and designers
Disadvantages could be the complexity and cost of preparing and negotiating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  • What would you expect to see in a Letter of Intent?
A

Identification of parties, project description
Scope of works, pricing and timelines. Key deliverable.

Date- signature – termination conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • What are the implications for the client for using an NEC contract?
A

NEC promotes collaborative working
Encourages early warnings notices,
Client to be responsive and proactive
Project Management focused
Simple and clear language
Dispute res
Payment mechanisms ie – Stage payment and certification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • What is the definition Partial Possession? What implications does it have under the JCT contract?
A

This means the client request possession from the contractor and the contractor can agree to this or not

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  • What current challenges is Covid and/or Brexit bringing to Contract Practice?
A

Supply chain disruption, H*S provisions,
Regulatory issues, currency fluctuations,
Data protection. Staffing provisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  • When might the NEC suite of contracts be used
A

Engineering contract
Public sector works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  • What is a performance bond?
A

It is a financial guarantee provided by the contract to the client. It offers financial protection – contractors have ability to win bigger projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  • When might a performance bond be used?
A

For large projects - Government contracts/ high value projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  • Typically, what insurance options are available under the JCT suite of contracts?
A

5.4 Joint Names – 5.5 Employer covers the works on a joint Names.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  • What are the typical elements of a project that need to be considered when selecting a form of contract?
A

Complexity, scope of project, H*S, design liability and timeline, Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  • What elements of a project might be relevant when considering which building contract would be most appropriate?
A

Contractors design? time line and client obligations, Nominated contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  • If a lump sum contract is one type, what other types of building contract are there?
A

Target Cost Contract, Cost plus, Remeasurement contract, Management contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  • Does a contract need to be in writing?
A

OFFER, ACEPTANCE, CONSIDERATION, INTENTION TO CREATE CONTRACT, CAPACITY OF PARTIES TO CONTRACT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Unit 15 Warnford * Explain the content of the contract documentation.

A

Drawings, SOW, Priced Tender, Tender Return,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Unit 15 Warnford * What were the liquidated damages and how were they calculated?

A

Client chose this as their rent

17
Q

Unit 15 Warnford * Why was a minor works contract used

A

Simple in Nature.
No Sectional Completion
No nominated SC

18
Q

Unit 15 Warnford* Was it necessary to consider a collateral warranty for anything?

A

No

19
Q

Unit 15 Warnford* How were the valuation dates set in the contract?

A

Fortnightly.

20
Q

Manor Joinery* Why as an intermediate contract used for this project?

A

The works were quite complex and the contract sum was above 500k – contractor also designed the works and client wanted sectional completion.

21
Q

Manor Joinery* What was included in the employer’s schedule of amendments?

A

Contract amendments were- retention release should not be released to half on PC until all H&S/o&Ms are received.
Insurance option B is used for new builds rather then Option A.

22
Q

Manor Joinery* What was the contractor’s design portion for?

A

Design of the CCTV and mechanical works.