APC DELEVER PACK Flashcards
Question pack
Can you explain how single-stage and two-stage tendering are different?
Two stage tenders generally take longer.
Single tender- all documents are issued at one and contractor submit a bid.
Two stage – takes longer where the contractors submit initial proposals, the client then shortlists the contractors.
Typically used on larger projects.
- What tendering guidelines are you aware of?
Tendering strategies – 1st edition 2014
- What legislation is relevant to dilapidations?
Dilapidations Protocol
Dilapidations England and Wals
Landlord and Tenant ac 1927 - Section 18
- What legislation is relevant to asbestos?
Control of Asbestos Regulations 2012
Riddor
Hazerdous waste regulations 2005
Enviromental protection act
HASAWA
CDM 2015
What is the HSE notice period for notification
14days
- Why do we have sustainability legislation?
Social, Economical and environmental reasons
- What sustainable assessment methods are you aware of?
BREAM- assesses new construction, refurbishment and in-use buildings.
- What are the types of asbestos licenses x 3
Licensed works Notifiable
Non-Licensed Notifiable
Non licensed Non-Notifiable
- Name the 3 asbestos colors/types
Chrysotile- White – Cement boards , roofing, ceilings and floors.
Amosite – Brown – brittle fibers, cement sheets, pipe insulation
Crocidolite – Blue – most dangerous- Spray Coating
- What was the construction of the warehouse?
Steel portal frame with low level brickwork.
- What information did you include in the tenders?
PCI – Designer risk register, Pre lims, M&W, Sow, Tender compilation page, FoT, Appendices.
- How long was the tender period?
3 weeks – extended to 5.
- How were the contractors selected for the tender list?
All previously used by JLL, I carried out a DUNN and Brad credit check on them all.
- Explain what the content of your tender report was.
Intro, outline of procurement, contractors used etc, Tender Analysis, clarifications.
cost comparison, Particulars, Recommendations and project costs
- How did you identify all the relevant stakeholders on the project?
Identify project scope, create a stake holder map, priorities.
- How were you able to understand the influence of each stakeholder and prioritise each?
H&S first,CDM - Risk register and PCI, instructed M&W to prepare design, I designed what I needed to.
- Explain how the triple skin composite roof structure was fixed to the structure.
Mechanical fasteners.
- Why was the JCT MW contract used with contractors design?
The project was simple in nature. No need for CoW, Nominated sub contractor or Sectional completion.
- What was the contractors design portion?
The M&E design and Solar PV.
- Why could this not have been designed during the design phase?
This was due to the client not accepting the option, and then a new asset manager joining
- Were the CDM Regulations applicable to this project?
Yes