Conflict Avoidance, Management and Dispute Resolution Procedures Flashcards
1
Q
What are the forms of dispute resolution available under the JCT suite of contracts?
A
- Negotiation - problem solving by the parties themselves.
- Mediation/Concilliation - 3rd party intervention but no binding decision imposed.
- 3rd Party Adjudication. Right to this created by the Construction Act 1996. Quick decision given within 28 days. Binding unless subsequently overturned by arbitration/litigation.
- Arbitration. If contract allows. More formal form of dispute resolution. 3rd Party Arbitrator can order facts/details of costs. Decision binding.
- Litigation/Court procedings. Expensive.
2
Q
What is Independent Expert Determination?
A
- Private process involving an independent technical expert.
- Makes binding decision on technical matters.
- No recourse and decision is final.
- Similar to arbitration but the independent expert does not need to refer back to the parties before making a decision - makes process quicker.
3
Q
Define ADR
A
All methods of dispute resolution taking place outside of the courts.
4
Q
List for me some ADR procedures
A
- Arbitration
- Independent Determination
- Mediation
- Early neutral evaluaion
- Adjudication
- Dispute Resolution Boards
5
Q
What is a Dispute Resolution Board?
A
- 1-3 people appointed at start of large construction project. Each party choose one board member and then the 2 choose a third.
- They consider project issues and recomend resolution of disputes.
- Non-binding.
6
Q
What is Adjudication?
A
Right to this created by the Construction Act 1996. Quick decision given within 28 days. Binding unless subsequently overturned by arbitration/litigation.
7
Q
What is Arbitration?
A
- Both sides to a dispute agree to let a 3rd party (the arbitrator) decide.
- Arbitrator may be a lawyer.
- Make decision according to law.
- Decision is binding and can be enforced through courts.
8
Q
How can conflict in construction be avoided?
A
- Good management - proactive, planned, early raising of issues.
- Clear contract docs - no ambiguities
- Partnering and alliancing - cooperation and team-working - NEC suite of contracts.
- Good project management
- Good client management
- Good contractor management
- Good payment practice
- Record keeping
- Regular reporting
9
Q
What is risk management?
A
- An example would be the use of a risk register.
- Each risk quntified in terms of probablility and potential impact.
- Each risk given a mitigation strategy and a person/party responsible for it.