Case Study Flashcards
What does the red tick mean on the Slide for Key Issue 1?
It means that although lacking a formal tender process, Option 1 still achieved a degree of certainty for the client through:
* Measured rates
* A trusted and known contractor
* Benchmarking against industry-recognised rates e.g. BCIS, SPONS
You mention cracks in the masonry due to saturation. What else could have caused these, and how did you discount other possibilities?
- Defect mechanism = Ground movement e.g subsidence, settlement, heave. Why Discounted? - walls were plumb, cracking was the same size at both ends.
- Defect mechanism = Expansion or contraction of brickwork due to changes in temperature. Why discounted? - Not discounted completely. Clay brickwork so likely to have expanded in early stages, possibly leading to cracks. Could be contributing factor.
- Defect mechanism = Structural effects e.g. failure of lintels or openings being made. Why discounted? Not discounted. Certainly a contributary factor. Openings could have added to strain and loadings contributing to ‘creep’ in the masonry over time.
If you had pursued Option 1, how would you have worked out abortive costs?
- Pro-rata the contractor’s prelims
- Assess how Prelim costs spread across contract duration
- Look at upfront costs for scaffold hire, materials etc.
- Request expenditure evidence e.g. invoices, supplier notes.
- Works costs on a % basis
If you had pursued Option 2, what would be the implications of having 2 contractors on site under different contracts, in terms of the CDM Regulations?
- CDM Regs are clear that there should be only one Principal Contractor.
- Only time it can be considered are if there are 2 projects on site at same time and they are run independently of each other, and where one Principal Contractor can’t be in overall control.
For Option 3, who decided on the measured rates? How were they established? How did you check costs?
- I proposed measured rates in requesting costs for the additional work.
- Used where any uncertainty existed to the extent e.g. brickwork repairs. Render reinstatement.
- e.g. 0.25 m2 brickwork
What did you need to consider in re-rendering the walls in terms of compliance with Part-L of the Building REgulations?
- If more than 50% of the surface area of an individual thermal element is being renovated, then the whole of that element should be improved to the standard set (external walls are 0.30 Watts per metre square Kelvin)
- In this case, we had an approved inspector on board, who agreed that less than 50% of the wall was being renovated, and in any case the wall was not cost-effective to insulate due to detailing.
- Or, if the works constitute a ‘Major Renovation’ where more than 25% of the surface area of building envelope is being renovated, improvement is required.
- This didnt apply in this instance.
How did you quantify Prov Sums in the Schedule of Works?
These were based on a budget estimate of the likely works involved. Where possible, they were based on a known rate and scaled to the likely quantity required.
What detailing did you identify to the roof/wall-plate junction to achieve adequate thermal qualities?
Ask Mat?
How did you ensure design quality with the negotiated works?
- There was a detailed specification agreed with the contractor prior to pricing.
- Specification was written with reference to British Standards e.g. for render repairs, and Building Regs Part A for structural repairs to roof.
What is the contractual status of progress meeting minutes?
- Not a contractual document.
- Do give prima fascia evidence of progress if they are dated, signed and filed correctly.
- Same applied to Site Notes.
How did you go about formalising the additional time spent on the structural works? Was there an EOT granted? How was this agreed and formalised?
- An instruction was issued for the additional structural works. This was based on a detailed specification for the additional works to provide clarity over what was being priced.
- The contractor provided written confirmation that a delay had occured caused by a ‘relevant event’ i.e. the variation.
- This was accepted and the completion date was adjusted.
- The length of the extension was not immediately decided, as the contractor had to find lead times etc from appropriate sub-contractors.
- The variation also constituted a ‘relevant-matter’ and entitled the contractor to claim loss and expense.
What are Relevant Matters in JCT Contracts?
- A Relevant Matter is something caused by the client that affects the progress of the works.
- Relevant Matters entitle the contractor to claim loss and/or expense.
- A Relevant Matter need not always result in a delay to the Completion Date, so may not always entitle the contractor to an Extension of Time.
What are some examples of Relevant Matters?
- Failure to give a contractor access to site
- Delay in providing instructions
- Discrepancies in the contract docs
- Failure to supply goods or services
- Instructions relating to variations or expenditure of provisional sums
What is a Relevant Event?
- Events that cause a delay to the Completion date, either caused by the Client or by a neutral party. They entitle the contractor to claim an Extension of Time.
- A Relevant Event does not necessarily entitle the contractor to claim loss and expense.
What is the difference between defined and undefined provisional sums?
- Defined = Contractor will have deemed to have made allowance for these in their programme, pricing and planning prelims.
- Undefined = Contractor will not have deemed to have made an allowance for the above.