Chapter 9 Flashcards
Cost estimates
The process of forecasting/estimating the time and cost of completing project deliverables
- the task of balancing the expectations of stakeholders and the need for control while the project is implemented
types of estimates
- top-down (macro) estimates:
- analogy
- group consensus
- mathematical relationships - bottom-up (micro) estimates:
- estimates of elements of the work breakdown structure
method for cost estimation
duration = (a + 4m + b)/6
a: optimistic
m: most likely
b: pessimistic
Cost escalation
The amount by which the actual costs grow to exceed the initial estimates
the ratio that costs are more than the estimate
“normal” to occur on projects = +- 20%
Sources of Cost Escalation and Overruns
- Uncertainty and Lack of Accurate Information
- Changes in Requirements or Design
- Economic and social factors
- inefficiency, Poor Communication, and Poor Lack of Control
- ego Involvement of the Estimator
- project contract
- bias and ambition
Uncertainty and Lack of Accurate Information
- information needed for cost estimation not available when estimations are make
- only available when designs finalised and work activities are well defined
Changes in Requirements or Design
- when discretionary, nonessential changes get made to the system requirements
- provisions made for changes in contract
- managed with change control and configuration management
Economic and social factors
- costs can escalate, independent of the quality of planning (due to forces beyond project control: strikes, material shortage etc)
- inflation should be taken into consideration –> causes cash flow difficulties
Inefficiency, Poor Communication, and Poor Lack of Control
- Especially in bigger projects with lots of team members
- management has a substantial influence on this
Ego Involvement of the Estimator
- Overly optimistic = underestimate the time and cost
- lack of experience
- important for all workers to give input into cost estimates
project contract
- fixed price
- forces contractors to control costs - cost plus
- has not obligation to control costs
accuracy vs precision
Accuracy: the closeness of the estimated value to the actual value
Precision: the number of decimal places in the estimate
–> accuracy is more important than precision
System Life Cycle costs
All costs of a system throughout its full cradle-to-grave life cycle
- all costs incurred during the project life cycle phases of Definition and Execution
- PLUS all costs associated with the Operations phase (Maintenance and Renewal) and the eventual Disposal of the system
Purpose of life cycle cost analysis
- To anticipate the realities of operating, maintaining, and (ultimately) disposing of the end-item system
- To establish target costs for operating, maintaining, and disposing of the end- item system
- To design the system so it will meet those target costs
Estimating process: Estimate versus Target or Goal
Estimate
a realistic assessment based upon known facts about the work, required resources, constraints, and the environment, derived from estimating methods
Target or goal
a desired outcome, commitment, or promise.