Chapter 9 Flashcards

1
Q

Cost estimates

A

The process of forecasting/estimating the time and cost of completing project deliverables
- the task of balancing the expectations of stakeholders and the need for control while the project is implemented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

types of estimates

A
  1. top-down (macro) estimates:
    - analogy
    - group consensus
    - mathematical relationships
  2. bottom-up (micro) estimates:
    - estimates of elements of the work breakdown structure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

method for cost estimation

A

duration = (a + 4m + b)/6

a: optimistic
m: most likely
b: pessimistic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cost escalation

A

The amount by which the actual costs grow to exceed the initial estimates

the ratio that costs are more than the estimate
“normal” to occur on projects = +- 20%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Sources of Cost Escalation and Overruns

A
  • Uncertainty and Lack of Accurate Information
  • Changes in Requirements or Design
  • Economic and social factors
  • inefficiency, Poor Communication, and Poor Lack of Control
  • ego Involvement of the Estimator
  • project contract
  • bias and ambition
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Uncertainty and Lack of Accurate Information

A
  • information needed for cost estimation not available when estimations are make
  • only available when designs finalised and work activities are well defined
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Changes in Requirements or Design

A
  • when discretionary, nonessential changes get made to the system requirements
  • provisions made for changes in contract
  • managed with change control and configuration management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Economic and social factors

A
  • costs can escalate, independent of the quality of planning (due to forces beyond project control: strikes, material shortage etc)
  • inflation should be taken into consideration –> causes cash flow difficulties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Inefficiency, Poor Communication, and Poor Lack of Control

A
  • Especially in bigger projects with lots of team members

- management has a substantial influence on this

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Ego Involvement of the Estimator

A
  • Overly optimistic = underestimate the time and cost
  • lack of experience
  • important for all workers to give input into cost estimates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

project contract

A
  1. fixed price
    - forces contractors to control costs
  2. cost plus
    - has not obligation to control costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

accuracy vs precision

A

Accuracy: the closeness of the estimated value to the actual value
Precision: the number of decimal places in the estimate
–> accuracy is more important than precision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

System Life Cycle costs

A

All costs of a system throughout its full cradle-to-grave life cycle

  • all costs incurred during the project life cycle phases of Definition and Execution
  • PLUS all costs associated with the Operations phase (Maintenance and Renewal) and the eventual Disposal of the system
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Purpose of life cycle cost analysis

A
  • To anticipate the realities of operating, maintaining, and (ultimately) disposing of the end-item system
  • To establish target costs for operating, maintaining, and disposing of the end- item system
  • To design the system so it will meet those target costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Estimating process: Estimate versus Target or Goal

A

Estimate
a realistic assessment based upon known facts about the work, required resources, constraints, and the environment, derived from estimating methods

Target or goal
a desired outcome, commitment, or promise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

the estimating process

A

is directed at producing good estimates, not restating targets or goals

17
Q

estimating methods

A
  1. expert opinion
  2. analogy and compensation for differences
  3. parametric: formula or cost function
  4. cost engineering
18
Q

Cost engineering

A

Detailed cost breakdown of labor, materials, etc. at the work package or task level

19
Q

Rule of thumb for estimating process

A

the smaller the work package/portion of the end-item estimated, the better the estimate

20
Q

Contingency amount

A

added to estimates to offset uncertainty

  • more uncertainty, the higher the amount
  • include allowance for design changes, increases in scope, size or function of end item and delays
21
Q

estimating process: top-down estimates

A

estimating costs by looking at the project as a whole

  • typically based on expert opinion or analogy
22
Q

estimating process: bottom-up estimated

A

estimating costs based on looking at elements of the project

- every activity is estimated separately and aggregated

23
Q

2 types of cost elements

A
  1. fixed costs
    - Rent
    - Labour
    - Overheads
  2. variable costs
    - increase with loading
24
Q

Direct costs

A
  • Costs in the contents of an activity are clearly chargeable to a specific work package
  • Directly related to the work and changes with the volume of the work
  • Costs are spent as the project proceeds
  • Examples: Labour, Materials, Equipment, Management
25
Q

Direct (Project) Overhead Costs

A
  • Costs of the organisation resources that are used in the project
  • Related to project deliverables
  • Can be determined by basing it on a specific percentage of direct costs
  • Allocated to summary activities
  • Changes with the time duration of the project and not the volume
26
Q

General and Administrative Overhead Costs

A
  • Organisation costs indirectly linked to a specific package
  • Organisation costs of all products and projects (e.g., advertising, book keeping and senior managers above project level)
  • Differs from organisation to organisation
  • Head office makes strategic decisions
27
Q

Profits and Total Billing (External projects)

A
  • maximise this rate in order to pay the shareholders
  • profits must be added to the project costs as per the company policy
  • PM does not have to manage (but profit is influenced by the success and quality of PM)
28
Q

Bias and ambition

A

optimism may lead to over estimating benefits and underestimating costs