Chapter 7 Flashcards
Network diagrams
shows project activities or tasks and their logical relationships
also shows events (instants in time; start of an activity)
2 construction methods of network diagrams
- AON mode (activity on mode)
2. AOA mode (activity on arrow)
AON mode
- each activity (work package or task) in project is represented by a node
- project represented as arrows and nodes (arranged in sequence as specified by immediate predecessors)
2 types of dependency relationships
- mandatory
- sequence of 2 actions can’t be reversed
- dependency can’t be eliminated - discretionary
- sequence is a matter of choice
- dependency can be eliminated (and activities overlapped to speed up process = fast tracking)
creating a project network
created using list of activities from Work Breakdown Structure and their predecessors
What happens when a delay occurs in one of the activities on the critical path?
the whole project is delayed
Early times: early start and early finish
earliest that activities can be started (ES) and finished (EF)
- ES depends on the EF of its predecessor
- do not consider potential constraints
Late times: late start and late finish
latest allowable times an activity can start (LS) and finish (LF) without delaying project completion
- LF depends on the LS for its successor
Total slack
amount of allowable deviation between the latest an activity must take place and the earliest it can take place
–> how much an activity can be delayed without delaying the whole project
Critical path
- has no or the least slack
- the time a project takes is dependent of the critical path
- it is the longest path
activities on the critical path
critical activities
free slack
the time an activity can be delayed without delaying the start of any successor activity
Alternative precedence relationships: Start-to-start (SS)
Start second task ___ days after first task starts
Alternative precedence relationships: Start-to-finish (SF)
Finish second task ___ days after first task starts
PDM (Precedence Diagramming Method)
shows the kinds of relationships in a project
- Start activity when predecessors are only partially completed
- Start activity n days after start of predecessor
- Start activity n days after predecessors are completed
- Finish activity n days after finished predecessor