Chapter 7 Flashcards

1
Q

Network diagrams

A

shows project activities or tasks and their logical relationships
also shows events (instants in time; start of an activity)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2 construction methods of network diagrams

A
  1. AON mode (activity on mode)

2. AOA mode (activity on arrow)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AON mode

A
  • each activity (work package or task) in project is represented by a node
  • project represented as arrows and nodes (arranged in sequence as specified by immediate predecessors)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

2 types of dependency relationships

A
  1. mandatory
    - sequence of 2 actions can’t be reversed
    - dependency can’t be eliminated
  2. discretionary
    - sequence is a matter of choice
    - dependency can be eliminated (and activities overlapped to speed up process = fast tracking)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

creating a project network

A

created using list of activities from Work Breakdown Structure and their predecessors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens when a delay occurs in one of the activities on the critical path?

A

the whole project is delayed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Early times: early start and early finish

A

earliest that activities can be started (ES) and finished (EF)

  • ES depends on the EF of its predecessor
  • do not consider potential constraints
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Late times: late start and late finish

A

latest allowable times an activity can start (LS) and finish (LF) without delaying project completion
- LF depends on the LS for its successor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Total slack

A

amount of allowable deviation between the latest an activity must take place and the earliest it can take place
–> how much an activity can be delayed without delaying the whole project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Critical path

A
  • has no or the least slack
  • the time a project takes is dependent of the critical path
  • it is the longest path
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

activities on the critical path

A

critical activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

free slack

A

the time an activity can be delayed without delaying the start of any successor activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Alternative precedence relationships: Start-to-start (SS)

A

Start second task ___ days after first task starts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Alternative precedence relationships: Start-to-finish (SF)

A

Finish second task ___ days after first task starts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

PDM (Precedence Diagramming Method)

A

shows the kinds of relationships in a project

  1. Start activity when predecessors are only partially completed
  2. Start activity n days after start of predecessor
  3. Start activity n days after predecessors are completed
  4. Finish activity n days after finished predecessor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Alternative precedence relationships: Finish-to-start (FS)

A

_______ day lag between predecessor and successor

Start second task ___ days after first task finishes

17
Q

Alternative precedence relationships: Finish-to-finish (FF)

A

finish second task ___ days after first task finishes

–> mostly used with zero lag where activities must end on the same day

18
Q

Time Constrained Project

A
  • A project that must be completed by an
    imposed date
  • Time is fixed, resources are flexible
    –> sometimes resources are required to ensure project meets schedule
19
Q

Resource Constrained Project

A
  • A project in which the level of resources available cannot be exceeded
  • Resources are fixed, time is flexible
  • -> inadequate resources will delay the project
  • Resource levelling (or smoothing) involves attempting to even out demands on resources by using slack (delaying non critical activities) to manage resource utilisation.
20
Q

Resource allocation

A

assigning resources to activity

21
Q

Workload (and formula)

A

amount of work imposed on resource

working days/year) x (productive working hours/day

22
Q

Resource Loading

A

amount of particular resource needed to conduct all allocated activities

23
Q

Loading for particular resources depends of

A
  1. amount of resource needed by project activities

2. start and finish dates of those activities

24
Q

Resource levelling

A

alter schedules of project activities such that the resultant workload for a required resource is somewhat uniform throughout the project
–> do this by adding slack

25
Q

Downside to splitting activities into pieces and schedule them at different times

A

can lead to wasted time and longer activity duration

26
Q

Laddering

A

continue to the next component before entire design is complete

27
Q

Managing multi-project resource schedules

A
  • create project offices or departments to oversee the scheduling of resources across projects
  • Use a project priority queuing system: first come, first served for resources
  • centralise project management: treat all projects as a part of a “mega project”
  • apply Critical Chain Methods to all project scheduling
  • outsource projects/project sections to reduce the number of projects handled internally
28
Q

Problems with multi-project resource schedules

A
  1. Overall project slippage
    - delay on one project creates delays for other projects
  2. inefficient resource application
    - the peaks and valleys of resource demands create scheduling problems and delays for projects
  3. resource bottlenecks
    - shortages of critical resources required for multiple projects cause delays and schedule extensions
29
Q

Criticism of network methods

A
  • they incorporate assumptions and yield results that are sometimes unrealistic
  • activities and duration require periodic modification
  • failing of networks are actually inadequacies in project definition
30
Q

Variability of Activity Duration

A
  • Activity duration is not a single, deterministic value

- there is a range of possible durations for most activities

31
Q

Sensitivity of a network

A

the likelihood that the original critical path(s) will change once the project is initiated

32
Q

the sensitivity of a network is the function of

A
  1. the number of critical paths
  2. amount of slack across near critical paths
  3. the uncertainty of the time duration of activities, on and along the critical path
33
Q

advantage of networks

A

they clearly display the interdependencies of project activities and show the scheduling impact that activities have on each other