Chapter 12 Relay Pumping Ops Flashcards
A relay pumping operation consists of:
A pumper positioned at the water supply pumping and pressurizing water through a supply to another pumper that repressurises and so on until it reaches the attack pumper
Pg 425
In oder to be effective relay operations require:
Preplanning, training, and coordinating of all participants
Pg 425
Water supply pumper in relay pumping:
Should have the largest pumping capacity. This pumper takes water from the hydrant or static source and pumps it to the next relay pumper.
Pg 426
Relay pumper:
Receives water from another pumper, raises the pressure and supplies it to the next apparatus
Pg 427
Fire attack pumper:
Pumping apparatus located at the fire scene that receives water from the relay and is responsible for supplying the attack lines and appliances required for suppression
Pg 427
Basically the need for relay pumping is determined by the:
Amount of water required at an incident and the distance between the incident scene and the water source
Pg 427
If flow through a relay needs to be increased it can be done in 3 ways:
Increase the diameter of the supply hose or add more supply lines
Increase the pump discharge pressure
Add more pumpers to the relay to overcome friction loss or elevation loss
Pg 428
Increasing flow during a relay operation may e accomplished by:
Placing additional pumpers in the system
Pg 428
The overall capacity of a relay system is determined bye the:
Smallest pump and the smallest diameter of hose used in the relay
Pg 432
When laying long distances the hose lay between each pumper should be:
As equalized as possible
Pg 432
It is advisable or a driver to maintain an intake pressure of ____ to _____ psi as a relay pumper
20/30
Pg 433
Once the relay operation is flowing water at the desired pressure the driver of the attack pumper should:
Set the pressure governor at an appropriate level
Pg 433
Apparatus equipped with pressure governors should be set in the_______ mode when acting as the attack pumper and in the________ mode while working as a relay pumper
Pressure
Rpm
Pg 433
When the need for relay pumping has ended the operations should be discontinued from the:
Fire scene first
Pg 434
Open relay method consists of:
Deploying portable folding drop tanks at each intake for pumpers in the relay operation
Pg 435