Chap 9 - Executing the Work Flashcards

1
Q

T/F: The contractor is required to confirm completeness and accuracy of the contract documents, and to ascertain that the contract documents are in accordance with applicable codes and regulations.

A

FALSE:

CAPG 9.2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If the contractor discovers errors, omissions, or inconsistencies in the contract documents, or discovers nonconformity with applicable codes and regulations, then……

A

…the contractor is obligated to notify the A/E in the form of an RFI.

CAPG 9.2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are coordination drawings and who prepares them?

A

Coordination drawings are prepared by the contractor primarily to coordinate related work, which is shown on several different contract drawings or shown schematically by the drawings.

CAPG 9.3.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is phasing:

A

Phasing is:
…the division of major portions of a project…
…separated by sequence and time intervals…
… to allow continued or early use.

CAPG 9.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When phasing is required on a project, where will the requirements be set forth?

A

….in Division 01 of the project manual.

CAPG 9.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

T/F: Construction means and methods are within the purview of the A/E.

A

FALSE: Construction means and methods are the sole responsibility of the contractor.

CAPG 9.6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Several of the critical components of successful means and methods are as follows:

A

Successful means and methods include:

  • regular progress meetings
  • communicate with the members of the construction team
  • have contingency plans for unexpected events
  • follow the construction progress schedule and keep it updated

CAPG 9.6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If the product is not stored correctly, the product may be damaged and the _________

A

….warranty may be voided before it is installed in the project.

CAPG 9.7 Intro

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

T/F: Each installer should inspect previously completed work prior to starting the installer’s own work.

A

TRUE: This procedure is a QA action that will help prevent compounding defects.

CAPG 9.8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Installation procedures are specified in:

A

….PART 3—EXECUTION of individual specification sections.

CAPG 9.10.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If installation standards are specified by reference, then the installer _________________

A

….must understand the requirements of the referenced standards and should have a copy of each referenced standard.

CAPG 9.10.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

T/F: The quality of workmanship required for each project is established by the contract documents.

A

TRUE:

CAPG 9.10.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

T/F: Construction specifications identify the quantitative requirements for products, materials, and workmanship

A

FALSE: Construction specifications identify the qualitative requirements for products, materials, and workmanship

CAPG 9.10.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The contractor should perform _______ throughout the project, to ensure __________.

A

…. regular inspections
…. conformance to the contract documents.

CAPG 9.10.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

T/F: The contractor is not responsible to ensure elements of work not constructed with the contractor’s own forces are in compliance with the contract documents.

A

FALSE: The fact that the contractor did not perform an element of work with the contractor’s own forces does not excuse the contractor from compliance with the contract documents.

CAPG 9.10.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The procedures and responsibilities for cleaning and construction waste management are listed where?

A

….in Division 01— General Requirements

CAPG 9.11 Intro

17
Q

The contract may allow the owner to _________ if periodic project cleaning is not done, or _________ .

A

….withhold monies from the contractor, or
….the owner may have the cleaning done and request a contract modification for the costs incurred.

CAPG 9.11.1

18
Q

On sustainable projects, the cleaning methods are often required to comply with ___________ for general-purpose cleaning and toilet room cleaning.

A

….the environmental standard Green Seal 37

CAPG 9.11.1

19
Q

Sustainable projects will require the contractor to develop and implement a ___________

A

….construction waste management plan, which complies with an established industry-recognized reference standard.

CAPG 9.11.2

20
Q

The contractor has an obligation to protect the work until:

A

….the owner takes possession, as any damage done in the interim is usually the contractor’s responsibility.

CAPG 9.12.2

21
Q

Requirements for protection of the public are typically specified in:

A

….Division 01—General Requirements, Section 01 50 00, Temporary Facilities and Controls.

CAPG 9.12.3

22
Q

T/F: The A/E specifies who is responsible for testing.

A

False: The contract documents specify who is responsible for testing.

CAPG 9.13 Intro

23
Q

The party responsible for payment of the testing agency may vary, but _____________

A

….the contractor is always responsible for scheduling the testing.

CAPG 9.13 Intro

24
Q

Who gets copies of the test reports?

A

For documenting required testing: the contractor and the A/E.

The contract documents may also require the testing agency to submit copies of test reports to the owner, the A/E, the applicable subcontractor, and AHJs.

CAPG 9.13 Intro

25
Q

Who pays for retesting when initial inspections and tests indicate that work does not comply with the contract documents?

A

….the contractor

CAPG 9.13.1

26
Q

Who pays the costs of fees for the A/E for re-review of new inspection/test information?

A

The contractor is normally required to pay for retesting when initial inspections and tests indicate that work does not comply with the contract documents. This includes additional A/E fees.

CAPG 9.13.1

27
Q

The contractor is responsible for scheduling the test/inspection, and for providing adequate notice to _____

A

….all parties involved in testing and inspection., such as the owner and A/E if their personnel need to be present during testing.

CAPG 9.13.2

28
Q

Who is responsible for assembling and maintaining accurate record documents?

A

….the contractor

CAPG 9.15.6

29
Q

Record documents typically include:

A

Record documents typically include:

  • Record drawings
  • Record project manual
  • Record submittals
  • Start-up logs

CAPG 9.15.6

30
Q

Record drawings should include contract modifications such:

A
  • addenda,
  • change directives,
  • minor changes in the work, and
  • change orders.

CAPG 9.15.6

31
Q

The location and identification of any existing buried or concealed items that were encountered during the project should be shown where?

A

…on the record drawings.

CAPG 9.15.6

32
Q

Record submittals should be indexed and ordered how?

A

…. according to MasterFormat®.

CAPG 9.15.6

33
Q

Record shop drawings should be clearly labeled with:

A
  • MasterFormat® section number
  • the manufacturer’s or fabricator’s name, address, telephone number, fax number, web site address, and e-mail address.

CAPG 9.15.6