Chap 8 - Interpretations and Modifications Flashcards
There are two types of modifications: ______
- those that require a change to the contract sum or time, and
- those that do not.
CAPG Chap 8 Intro
Changes that do not affect cost or time are minor changes in the work and may take the form of, ______
…substitutions, supplemental instructions (ASI), or field orders.
CAPG Chap 8 Intro
Information should be stated ______
… clearly, but only once.
CAPG 8.1 Intro
If similar information appears in both the drawings and specifications but is in conflict, ______
…document interpretation or modification will be needed.
CAPG 8.1 Intro
Disagreement by the contractor and owner on an A/E interpretation of the contract may result in:
- change directive
- minor change in the work (ASI or Field Order)
- change order
- notice of claim
- claim
CAPG 8.1 Intro
The contract documents are __________ , and what is required ______ is as ______________.
The contract documents are complementary, and what is required by one is as binding as if required by all.
CAPG 8.1.1
Contract documents are defined as the _________ that become ________ when the _______.
…. legally enforceable requirements that become part of the contract when the agreement is executed.
CAPG 8.1.1
Contract documents usually include the _____________ (6 things)
- contracting forms,
- conditions of the contract,
- specifications,
- drawings,
- addenda, and
- modifications.
CAPG 8.1.1
The AIA A201 states that the contractor is required to do only what is:
- reasonably consistent with the contract documents and
- reasonably inferable as being required to produce the intended results.
CAPG 8.1.1
The conditions of the contract require the contractor to report_____________ to the ________.
…errors, inconsistencies, or omissions to the A/E.
CAPG 8.1.1
When the A/E makes an interpretation consistent with the intent of the contract documents, he then issues an:
- Interpretation,
- minor change, or
- proposal request
CAPG 8.1.1
RFIs asking for interpretation of an item in the contract documents, may be initiated by who?
- the owner or
- the contractor.
CAPG 8.1.2
The AIA A201 states that the architect’s decisions regarding aesthetic effect are _____, unless they are _____.
….are final, unless they are inconsistent with the intent expressed in the contract documents.
CAPG 8.1.2
In order to maintain proper lines of communication, RFIs should be accepted only from:
- the owner or
- the contractor.
CAPG 8.1.2
RFIs may occasionally be an attempt to make a ___________ after expiration of the time limit.
…. Substitution of
- product,
- material, or
- system
CAPG 8.1.2
AIA A201 and EJCDC C-700 stipulate that the A/E’s decisions will be consistent with the intent of what may be _________________
….reasonably inferable from the contract documents.
CAPG 8.1.3
The A/E should render interpretations based on the contract documents without ___________
….partiality to either the owner or the contractor.
CAPG 8.1.3
Claims may be caused by the ______ or _____ disagreement with the A/E’s interpretation.
….owner’s or contractor’s
CAPG 8.1.3.2
Unresolved claims become __________.
…. disputes.
CAPG 8.1.3.3
Contract modifications are required whenever a change will ____________ .
modify the contract documents, regardless of a change in time or cost.
CAPG 8.2 Intro
________ are used to modify the contract documents when time or cost are affected.
________ are issued when neither time nor cost are affected.
….Change orders are used to modify the contract documents when cost, time, or both are affected.
….Minor changes in the work (ASI / Field Order)
CAPG 8.2 Intro
Prior to preparation of a change order, the contractor is usually asked to respond to a __________
….proposal request or submit a request for proposal which outlines the cost of the change and schedule impact.
CAPG 8.2 Intro