Chap 11 - Measurement and Payment Flashcards
The documents that establish the rights, responsibilities, and duties of the parties regarding measurement and payment are:
- (AIA) A201, General Conditions of the Contract for Construction
- (EJCDC) C-700, Standard General Conditions of the Construction Contract
- AIA B101, Standard Form of Agreement Between Owner and Architect
- EJCDC E-500, Standard Form of Agreement Between Owner and Engineer for Professional Services
CAPG Cap 11 Intro
Most contracts require that a ______________be submitted to the A/E for approval prior to the first application for payment.
…. schedule of values
CAPG 11.1
As a prerequisite for payment, the contractor may be required to submit _____________ . (4 things)
- updated construction progress schedule,
- test reports,
- material certifications, and
- other accompanying information
CAPG 11.1
Name three common payment intervals:
- Periodic Progress Payments
- Provisional Payments
- Single Payment
CAPG 11.2
What are Provisional Payments?
…. Provisional payments are predetermined partial amounts of the total contract sum tied to the attainment of identifiable milestones.
CAPG 11.2
Provisional Payments are often used with what type of project?
…. design-build projects.
CAPG 11.2
The contract sum may be established by a combination of base bid items, as well as: (3 items)
- unit prices
- allowances, and
- alternates
CAPG 11.3
The basis of payment is identified in the contract documents. Name three bases of payment:
- Stipulated Sum
- Unit Price
- Cost-Plus Fee
CAPG 11.3
The contract requires that values of the various portions of the work be established before the first application for payment. This is accomplished how?
…by the contractor preparing and submitting a schedule of values which breaks down the contract amount into definable line items with corresponding dollar amounts. CAPG 11.3
The cost-plus fee basis of payment is also referred to as:
….the time and material basis of compensation
CAPG 11.3
As the term cost-plus implies, the contractor is reimbursed the contractor’s actual cost of labor, equipment, and material, plus a predetermined fixed fee, or percentage of costs, for:
…. overhead and profit.
CAPG 10.3
Regarding Pay-apps, the A/E’s certification is based only on his knowledge, information, and belief that: (2 things)
- the work has progressed to the point indicated
- the quality of work conforms to the requirements of the contract documents
CAPG 10.4
Regarding Pay-apps, the A/E’s certification does not mean that the A/E:
- Made exhaustive on-site inspections
- Reviewed construction means, methods, sequences, or procedures
- Reviewed requisitions of subcontractors or suppliers
- Determined the disposition of previously certified payments
CAPG 10.4
Contract documents addressing payment usually include the following:
- Agreement
- General Conditions
- Supplementary Conditions
- Division 01—General Requirements, Section 01 20 00—Price and Payment Procedures
CAPG 10.4
On complex projects, the schedule of values could be organized using ____________
…. UniFormat™ or MasterFormat® classification system.
CAPG 10.6
When is the schedule of values usually secured? (two items)
… after award of the contract and before processing of the first progress payment.
CAPG 10.6
Two commonly used application forms for payment are:
- AIA G702, Application and Certificate for Payment
- EJCDC C-620, Contractor’s Application for Payment
CAPG 11.7.1
Regarding Pay-Apps, the A/E certifies only the amount having a sound contractual basis for payment, and when there is a disagreement, (does what)?
….provides both parties with a written explanation of the reasons for withholding certification of all or part of the payment.
CAPG 11.7.3
If the owner is informed of a judgment against the contractor or the existence of a lien, what happens? (2 things)
- appropriate amounts are withheld, as provided for under the general conditions
- the amounts dispersed as required by law and recommended by the owner’s legal counsel
CAPG 11.8