Chap 3 – Preconstruction Flashcards
Preconstruction activities begin when the contractor has received:
- an executed agreement
- a notice to proceed.
- or a Letter of Intent
CAPG Chap 3 Intro
The process of a project manager taking on the project documents from the estimating team is called __________ .
…. Pass-off or Estimating Pass-off
CAPG 3.1.1
During the estimating pass-off, what happens?
….The estimator usually goes through the entire estimate, explaining the items to the team that will construct the project.
CAPG 3.1.1
When the pass-off has been accomplished, what does the project manager do?
….The project manager takes the estimate and creates the original construction budget.
CAPG 3.1.1
Buyout is a part of which phase?
…the preconstruction phase.
(After award of contract, but before actual construction).
CAPG 3.1.1
What happens during buyout?
….the contractor issues:
- subcontracts,
- supply contracts,
- purchase orders for the work to be done,
- any final negotiating with vendors.
CAPG 3.1.2
To reduce the potential for bid shopping, some procurement documents require:
….The bidders to list subcontractors in their bids, or
….Provide a list after bid opening
CAPG 3.1.2
It is important for the subcontract to contain the flow-down language. This language ensures…..
….that the duties, rights, and responsibilities are properly delegated and the terms are consistent with the contract between the owner and the contractor.
CAPG 3.1.3
Many subcontractors insist that the ____________ or clause be excluded from their subcontract.
….“pay when paid”
CAPG 3.1.3
Subcontracts typically include requirements for:
- Payment and performance bonds
- Liability insurance
- Workers’ comp insurance
- Certified payroll reports
- Payment applications
- Submittals, samples, and mock-ups
- Warranties
- Record documents
CAPG 3.1.3
Purchase orders should reflect the terms of _____________ .
….the supplier’s quote.
CAPG 3.1.4
The supplier’s quote was the_______________; the purchase order is the ______________ in the contract process
…. offer
…. acceptance
CAPG 3.1.4
Purchase orders may include:
- Requirements for submittals, such as shop drawings, samples, and mockups
- Certifications and certificates of materials origin
- Testing requirements
CAPG 3.1.4
T/F: The date of commencement may be established by a notice to proceed.
TRUE:
CAPG 3.2
The EJCDC recognizes the notice to proceed as a ____________ .
…. contract document.
CAPG 3.2
An example of a project delivery method that may not establish a construction start time or duration is:
….. design-build (D-B)
CAPG 3.2
The documents typically used in the administration of a construction contract include:
- Owner-A/E agreement
- Owner-contractor agreement(s)
- Conditions of the contract
- Specifications
- Drawings
- Bid form or proposal, when attached as an exhibit to the agreement (EJCDC)
- Pre-contract revisions, including addenda
- Notice to proceed
- Contract modifications, including change orders
CAPG 3.3.1
The contracts themselves are not usually shared among the project participants, but the rights, roles, and responsibilities of the participants are covered in the ______________ .
….conditions of the contract.
CAPG 3.3.1
T/F: In signing an agreement, the party accepts an obligation to obtain the necessary contract documents.
TRUE:
CAPG 3.3.1
Whose responsibility is it to ensure that subcontractors and suppliers have all of the appropriate documents?
…..the contractor’s
CAPG 3.3.1
T/F: Posting addenda to the construction documents is an obligation of CCA / CPM
TRUE: Posting addenda to the construction documents is an important function of CCA and contractor project management. CAPG 3.3.1
T/F: When standards are specified or referenced, they become an integral part of the construction documents and therefore the contract.
TRUE:
CAPG 3.1.3
Two owner-A/E agreements in common use are:
- AIA B101, Standard Form of Agreement Between Owner and Architect
- EJCDC E-500, Standard Form of Agreement Between Owner and Engineer for Professional Services
CAPG 3.3.1.1
The typical owner-A/E agreement has several CCA provisions including: (list 5)
- The A/E’s Basic Services
- Project Representation
- Additional Services
- Contingent Additional Services
- Owner’s Responsibilities
CAPG 3.3.1.1
Duties and responsibilities the A/E has for CCA include:
- Advise and consult with the owner
- Interpret contract documents
- Observe the work
- Review and certify pay-apps
- Review and approve submittals
- Prepare modifications
- Prepare final punch list
- Inspect to determine date of substantial completion and final completion
CAPG 3.3.1.1
The type of owner-contractor agreement used depends on: (3 things)
- the project delivery method,
- the number of contracts, and
- the basis of payment.
CAPG 3.3.1.2
Common owner-contractor agreements in use include:
- AIA A101, – Stipulated Sum
- AIA A102, – Cost of the Work Plus a Fee with a GMP
- EJCDC C-520, – Stipulated Price
- EJCDC C-525, – Cost - Plus
CAPG 3.3.1.2
The owner-contractor agreement typically includes articles relating to: (list 4)
- Contract Documents
- Contract Time
- Contract Price
- Payment Procedures
CAPG 3.3.1.2
Of all the documents used in construction, the ____________ most clearly establish the responsibilities for CCA and contractor project management.
…. conditions of the contract
CAPG 3.3.1.3
The conditions of the contract identify the ________, _________, and ________ between the parties to the contract.
…rights, responsibilities, and relationships
CAPG 3.3.1.3
Two widely used general conditions of the contract are:
- AIA A201, General Conditions of the Contract for Construction
- EJCDC C-700, Standard General Conditions of the Construction Contract
CAPG 3.3.1.3
Topics covered by the conditions of the contract include:
- Responsibilities of Owner / AE / Contractor
- Construction by owner
- Changes in the work
- Contract time
- Payments for work performed
- Protection of persons and property
- Insurance and bonds
- Correction, or acceptance of defective work
- Suspension of work and termination of the contract
- Claims and disputes
CAPG 3.3.1.3
The general requirements in Division 01 of the specifications specify: (3 things)
- administrative requirements,
- procedural requirements, and
- temporary facilities and controls.
- There’s more they left out….???
CAPG 3.3.1.4