Chap 12 - Project Closeout Flashcards
The closeout process begins with ____________, and ends with _______________ .
….starting and adjusting systems …. the contractor’s accepting final payment from the owner
CAPG 12.1
The General Conditions of the Contract for Construction outline procedures to be followed in closing out the project. Name them.
- The contractor inspects the project and prepares an initial punch list
- The contractor submits notice of substantial completion.
- The architect inspects for substantial completion and prepares a final punch list.
- The architect prepares the certificate of substantial completion.
- The contractor completes the items on the punch list.
- The contractor submits notice of final completion and final pay-app.
- The architect inspects the project for final completion.
- The architect processes the final pay-app and closeout submittals.
- The owner makes final payment.
CAPG 12.1
Closeout requirements for record documents, O&M data, product warranties and bonds, spare parts, preventive maintenance instructions, and warranty inspections are found where?
….in Division 01
CAPG 12.1
The starting of systems; testing, adjusting, and balancing of systems; and systems demonstration & training are found where?
….in Divisions 02 - 49
CAPG 12.1
List the basic steps to project closeout:
- Start-up, testing, adjusting, and balancing of systems and equipment
- Demonstration of systems and equipment and training
- Completion of the commissioning activities
- Substantial completion
- Final completion
CAPG 12.3
The scheduling and coordination of start-up (starting of systems) is specified where?
….in Division 01.
CAPG 12.3.1
If contractors are allowed to use newly the installed systems and equipment during the construction stage, where will this be outlined?
….in the contract documents
CAPG 12.3.1
Project record documents assembled by the contractor include:
- construction submittals,
- record drawings,
- record specifications,
- addenda,
- contract modifications,
- photographs,
- start-up logs,
- test reports,
- certifications.
CAPG 12.3.2
The number of copies required for project record documents, and the format (electronic, hard copy, or both) are specified where?
…. in Division 01.
CAPG 12.3.2
Project record drawings include contract modifications, which, in turn, include:
- addenda,
- change directives,
- minor changes in the work, and
- change orders.
They also include locations of concealed elements of the work.
CAPG 12.3.2
How should record submittals may be organized?
…. record submittals may be indexed and organized according to MasterFormat
CAPG 12.3.2
How should you organize record shop drawings?
…. clearly labeled with MasterFormat® section number, and ….the manufacturer’s or fabricator’s name, address, telephone number, fax number, web site address, and e-mail address.
CAPG 12.3.2
When an owner retains the A/E to incorporate the contractor’s record information into a final set of project record documents, what is it called?
…. a “conformed” set.
CAPG 12.3.2
Record project manuals may include:
- Modifications made by addenda, change orders, and minor changes in the work
- Identification of materials and systems incorporated in actual construction
CAPG 12.3.2.1
Project record drawings are frequently used by the owner, facility manager, and maintenance personnel to obtain information about __________ .
….concealed items.
CAPG 12.3.2.2
Project record drawings can include:
- Modifications made to the drawings by addenda, change orders, and minor changes in the work;
- Revisions to materials, detailing, and dimensions incorporated into the project;
- Revised locations of structural elements, mechanical equipment, controls cabling and equipment, piping, valves, filters, cleanouts, access panels, electrical raceway, cabling, and junction boxes;
- Locations of underground utilities with horizontal and vertical dimensions.
CAPG 12.3.2.2
Project record submittals provide information on products, finishes, and equipment that is __________ .
…. actually utilized in construction of the facility.
CAPG 12.3.2.3
The requirements for O & M Manuals are specified where?
….in Division 01.
CAPG 12.3.3
Specific requirements for O&M data for products, systems, and equipment are specified where?
….in PART 1—GENERAL of individual sections of Divisions 02 through 49.
CAPG 12.3.3