Chap 2 – Roles and Responsibilities Flashcards
Owner responsibilities and rights include:
- Provide information to the contractor.
- Pay for fees and charges associated with the work.
- Make payment to the contractor.
- Stop the work for good cause.
- Carry out the work on the contractors behalf should that become necessary.
- Perform construction with own forces if necessary.
- Award separate contracts and coordinate work between those contracts if necessary.
- Clean the project should that become necessary.
- Partially occupy the project if desired.
- Terminate the contract without cause should that become necessary.
- Terminate for cause.
CAPG 2.1
T/F: A clerk of the works may work for either the owner or A/E.
TRUE:
CAPG 2.1
T/F: The clerk of the works typically is authorized to make decisions on the owner’s behalf.
FALSE: He performs more of a monitoring function—he acts as an information conduit and reporter.
CAPG 2.1
It is important for the owner to provide a reasonable ___________ in the project budget to cover changes and unforeseen issues.
…. contingency fund
CAPG 2.1.2
Typical A/E responsibilities for CCA are to:
- Represent the owner.
- Observe the work and be familiar with its progress.
- Certify/recommend the validity or contract compliance of an item or work.
- Interpret the contract documents.
- Resolve disputes.
- Modify the contract documents should that become necessary.
- Review submittals.
- Perform inspections of the work.
CAPG 2.2
Responsibilities of the contractor during construction include:
- Review contract documents and notify the A/E of any errors or omissions.
- Follow procedures for substitution of products.
- Furnish competent supervision.
- Maintain accessible current construction documents for use on the project.
- Schedule and coordinate material deliveries and subcontractor’s work.
- Indemnify and hold harmless the owner and the owner’s agents.
- Furnish payment and performance bonds to the owner.
- Furnish contractor’s liability insurance and workers’ compensation insurance.
- Implement and enforce project safety rules and regulations. Comply with local, state, and federal safety requirements.
- Schedule and facilitate testing as specified in the contract.
- Implement and monitor quality control (QC) and quality assurance (QA).
- Promptly pay subcontractors and suppliers for work performed and materials provided.
- Furnish submittals and samples as required by the contract documents for review by the A/E.
- Schedule and obtain required inspections by AHJs.
- Furnish record drawings, O&M manuals, etc, to the owner.
CAPG 2.3
T/F: Work performed by subcontractors and suppliers is bound by the same terms of the contract that bind the contractor.
TRUE: This is a requirement of AIA and EJCDC general conditions
CAPG 2.4
If subcontracts and material purchase agreements do not include provisions referencing the conditions of the owner-contractor agreement, the ___________ may be responsible for variations in contractual responsibilities.
….contractor
CAPG 2.4
T/F: If the contractor is bound to pay prevailing wages for the project, subcontractors will be similarly bound.
TRUE:
CAPG 2.4.1
T/F: The terms and conditions of the contract between the contractor and the owner also bind suppliers.
TRUE:
CAPG 2.4.2
T/F: If the contractor engages the help of a consultant, the language in the consultant contract should contain _________ language to ensure adherence to the terms of the agreement between the owner and the contractor.
….. flow-down language.
CAPG 2.5
The basic lines of communication as identified in the AIA and EJCDC general conditions include the following:
- Between owner and contractor: Through the A/E
- To consultants: Through the A/E
- To subcontractors and suppliers: Through the contractor
- To separate contractors: Through the owner, or construction manager
CAPG 2.10
Although the owner and the contractor have a direct contract, the contract documents stipulate that communication between them flows through the _______________ .
…. A/E.
CAPG 2.10
The communication roles may be different on ____________ and ______________ project delivery methods.
…. design-build
….. IPD (Integrated Project Delivery)
CAPG 2.10