Effectively administered meetings have a PAL— a ________, an _________, and a _______.
…. a purpose, an agenda, and a time limit.
CAPG Chap 4 Intro
Where can you find information on the types of meetings to be held during the construction stage.
…… The specification sections in Division 01
CAPG 4.1
Where can you find information on the administrative and procedural requirements for the required meetings?
…… The Division 01 specifications
CAPG 4.1
If Divisions 02 through 49 held information about meetings, what would the likely topic be?
….meetings required prior to installation of certain products and coordination meetings.
CAPG 4.1
T/F: Minutes taken at progress meetings become contract documents only after all parties have had an opportunity to review them and make comments/corrections.
FALSE: Written minutes are not contract documents.
CAPG 4.1.5
List some of the meetings listed in the CAPG:
- Preconstruction Meeting (aka Procedural Meeting)
- Site Mobilization Meeting
- Utility Coordination Meeting
- AHJs Meetings
- Progress Meetings
- Contractor/Subcontractor Meetings
- Preinstallation Meetings
- Closeout Meeting
CAPG 4.2
CSI calls the ___________ meeting a “Procedural Meeting”.
…. Preconstruction Meeting
CAPG 4.1
The Site Mobilization Meeting is often combined with the ______________ .
…. Preconstruction Meeting
CAPG 4.2.1.2
The _______________ meeting typically focuses on the contractor, the subcontractors, and their use of the site, whereas the ____________ meeting typically focuses on contractor project management and CCA procedures.
…. site mobilization
…. preconstruction
CAPG 4.2.1.2
Typical topics for the AHJs Meetings include:
- Required permits and fees
- Advance notice required for inspections
- Routing of test reports
- Supplemental information that must be on-site at the time of inspection
- Fees for re-inspection if work is not ready for inspection
- Public safety and impact of the project on the public
CAPG 4.2.1.2
Typical topics for the progress meetings include:
- Minutes of previous meeting
- Progress and schedule
- Material and equipment
- Deficiencies
- RFIs: Status of clarification
- Progress payments/applications
- Changes and modifications
- Record documents: Maintenance of documents
- Sustainable project items
- Action items
CAPG 4.2.2
Contractor / subcontractor meetings address topics such as:
- progress and of the work,
- scheduling,
- coordination between the trades
- applications for payment,
- project site safety,
- RFIs, and
- contract modifications.
CAPG 4.2.3
To clarify installation procedures, phasing, and coordination of the participants involved in the installation of a specific product, what type of meeting is held?
….. Preinstallation meetings
CAPG 4.2.4
The preinstallation meeting is a form of quality _________ specified in __(where)________ of a specification section.
…. quality assurance (QA)
…. PART 1—GENERAL
CAPG 4.2.4
The closeout meeting is used to:
- review requirements for the completion of the contract, and
- to obtain submittal of the necessary final documents.
CAPG 4.2.5