Chap 10 - Claims and Disputes Flashcards
The successful project is one that is:
- completed on time,
- within budget, and
- with all claims resolved.
CAPG 10.1
A request for compensation for dealing with a situation that differs materially from what was anticipated by the parties at the time of entering into the contract is called a ___________ .
….a claim.
CAPG 10.1
Claims are initial requests for __________
….adjustment in contract sum or time.
CAPG 10.1
T/F: Change order requests and proposal requests are claims.
TRUE
CAPG 10.1
Disputes are claims that cannot be resolved by the parties to the construction contract without ___________
….the intervention of an independent third party.
CAPG 10.1
Generally, three sources of claims may occur on a project. They are:
- claims by the contractor against the owner,
- claims by the owner against the contractor or the A/E
- claim by someone other than a party to the construction contract. (third party claims)
CAPG 10.2.1
If, during the course of the project, the contractor encounters conditions contrary to those stipulated or inferred in the contract documents, a claim may be initiated. Changed conditions include:
- Active interference by the owner or A/E
- Conditions beyond the control of either the contractor or the owner
- Unknown or concealed conditions that affect the extent of the work
- Modifications made to the contract documents
- Errors and omissions in the contract documents
CAPG 10.2.2
To file a claim, the contractor is required to provide clear documentation that a changed condition _____________
- was not foreseeable at the time of pricing, and
- resulted in demonstrable damages.
CAPG 10.2.2
Claims resulting from changed conditions may also be submitted by the contractor on behalf of:
….the contractor’s subcontractors and suppliers.
CAPG 10.2.2
Two types of claims relating to breach of contract are:
- claims for untimely payment or nonpayment
- claims for improper or ineffective construction contract administration
CAPG 10.2.2
Claims initiated by the owner may include:
• Correction of nonconforming or defective work
• Repair of damages to existing property
• Liquidated or compensatory damages for late performance
• Ineffective management and/or control of the work by the
contractor resulting in added costs for:
• Inordinate re-reviews of shop drawings
• Reviews of substitution requests
• Interferences with the owner’s operations
• Additional site visits, inspections, and related
administrative time
CAPG 10.2.3
The most common examples of third-party claims are ___________
…. injury or death to persons, and property damage .
CAPG 10.2.4
Under the provisions of AIA A201 and EJCDC C-700, the contractor agrees to indemnify ___________ against ______________.
….indemnify the owner and A/E against all third-party claims resulting from the contractor’s performance of work on the project.
CAPG 10.2.4
Under the legal concept of privity of contract, only the contractor and the owner may make a claim against the other. Therefore, ______________
….subcontractors, suppliers, and other participants rely on the contractor to pursue claims on their behalf.
CAPG 10.2.5
If either party takes exception to the decision of the initial decision maker, the claim may be ______ (4 items)
….negotiated, mediated, arbitrated, or litigated
CAPG 10.2.6
T/F: AIA Document A201 and EJCDC C-700 stipulate a time limit for submitting claims, and require the A/E to make an initial response within a specified period of time.
TRUE:
CAPG 10.2.6