Chap 10 - Claims and Disputes Flashcards

1
Q

The successful project is one that is:

A
  • completed on time,
  • within budget, and
  • with all claims resolved.

CAPG 10.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A request for compensation for dealing with a situation that differs materially from what was anticipated by the parties at the time of entering into the contract is called a ___________ .

A

….a claim.

CAPG 10.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Claims are initial requests for __________

A

….adjustment in contract sum or time.

CAPG 10.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

T/F: Change order requests and proposal requests are claims.

A

TRUE

CAPG 10.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Disputes are claims that cannot be resolved by the parties to the construction contract without ___________

A

….the intervention of an independent third party.

CAPG 10.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Generally, three sources of claims may occur on a project. They are:

A
  • claims by the contractor against the owner,
  • claims by the owner against the contractor or the A/E
  • claim by someone other than a party to the construction contract. (third party claims)

CAPG 10.2.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If, during the course of the project, the contractor encounters conditions contrary to those stipulated or inferred in the contract documents, a claim may be initiated. Changed conditions include:

A
  • Active interference by the owner or A/E
  • Conditions beyond the control of either the contractor or the owner
  • Unknown or concealed conditions that affect the extent of the work
  • Modifications made to the contract documents
  • Errors and omissions in the contract documents

CAPG 10.2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

To file a claim, the contractor is required to provide clear documentation that a changed condition _____________

A
  • was not foreseeable at the time of pricing, and
  • resulted in demonstrable damages.

CAPG 10.2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Claims resulting from changed conditions may also be submitted by the contractor on behalf of:

A

….the contractor’s subcontractors and suppliers.

CAPG 10.2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Two types of claims relating to breach of contract are:

A
  • claims for untimely payment or nonpayment
  • claims for improper or ineffective construction contract administration

CAPG 10.2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Claims initiated by the owner may include:

A

• Correction of nonconforming or defective work
• Repair of damages to existing property
• Liquidated or compensatory damages for late performance
• Ineffective management and/or control of the work by the
contractor resulting in added costs for:
• Inordinate re-reviews of shop drawings
• Reviews of substitution requests
• Interferences with the owner’s operations
• Additional site visits, inspections, and related
administrative time

CAPG 10.2.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The most common examples of third-party claims are ___________

A

…. injury or death to persons, and property damage .

CAPG 10.2.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Under the provisions of AIA A201 and EJCDC C-700, the contractor agrees to indemnify ___________ against ______________.

A

….indemnify the owner and A/E against all third-party claims resulting from the contractor’s performance of work on the project.

CAPG 10.2.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Under the legal concept of privity of contract, only the contractor and the owner may make a claim against the other. Therefore, ______________

A

….subcontractors, suppliers, and other participants rely on the contractor to pursue claims on their behalf.

CAPG 10.2.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If either party takes exception to the decision of the initial decision maker, the claim may be ______ (4 items)

A

….negotiated, mediated, arbitrated, or litigated

CAPG 10.2.6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

T/F: AIA Document A201 and EJCDC C-700 stipulate a time limit for submitting claims, and require the A/E to make an initial response within a specified period of time.

A

TRUE:

CAPG 10.2.6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

In analyzing claims, the A/E may:

A
  • request additional information,
  • submit a schedule for resolution to which the parties may agree, or
  • propose other actions that would initiate new time frames.

CAPG 10.2.6

18
Q

A claim should be initially addressed by reviewing the contract documents to determine _____

A

….entitlement.

CAPG 10.2.7

19
Q

The contractor’s entitlement to a claim involves two separate determinations. What are they?

A
  • determination whether the contract documents adequately identify the claim as being within the contractor’s contractual obligations.
  • determination of the timing of the claim.

CAPG 10.3.1

20
Q

Regarding a Contractor’s claim….
If the work in question is found not to be reasonably inferred, then ____________.
If the work in question is found to be reasonably inferred, then ___________.

A

….If not reasonably inferred, the contractor is entitled to a contract modification.
….If reasonably inferred, the entitlement to the claim is denied.

CAPG 10.3.1

21
Q

Failure to properly notify the A/E and the owner of a claim can result in _____________

A

….forfeiture of entitlement to the claim.

CAPG 10.3.1

22
Q

Regarding an Owner’s claim….

If the work in question may be reasonably inferred, then _____________.

If the work in question cannot be reasonably inferred, then _______________.

A

…. If reasonably inferred, the owner’s claim is upheld.

….If not reasonably inferred, the owner’s claim is denied.

CAPG 10.3.2

23
Q

Claims avoidance has become a common term applied to the management of claims and disputes, but perhaps a better term would be:

A

….dispute avoidance.

CAPG 10.4.1

24
Q

Three keys to dispute avoidance are:

A
  • communication,
  • documentation, and
  • claim resolution action plans.

CAPG 10.4.1

25
Q

Initial notification of a claim event should be oral and followed by __________

A

….a written notice as specified by the general conditions.

CAPG 10.4.1

26
Q

Action plans encourage claim resolution at the ___________

A

….lowest possible and appropriate level.

CAPG 10.4.1

27
Q

Claim resolution action plans establish a system for:

A
  • Prioritizing claims and promptly submitting documentation
  • Identifying parties with responsibility and authority for settling claims
  • Advancing the claim to a higher authority when the initial parties are in dispute

CAPG 10.4.1

28
Q

T/F: Disputes often occur when the A/E’s decision on a claim is not accepted by one or both parties and the claim cannot be resolved through negotiation.

A

TRUE:

CAPG 10.5 Intro

29
Q

Failure to negotiate effectively is due to one or more of the participants failing to _________

A

….understand and accept the rights, responsibilities, and requirements established by the contract documents.

CAPG 10.5 Intro

30
Q

T/F: The parties are not obligated under the conditions of the contract to use the specified method of dispute resolution indicated in the contract documents.

A

FALSE

CAPG 10.5.1

31
Q

AIA A201 states that either party can demand the other party file for mediation. If the other party does not file for mediation, then ____________

A

….both parties waive mediation and any other dispute resolution method

CAPG 10.5.1

32
Q

Arbitration and mediation are examples of __________

A

….alternative dispute resolution (ADR) methods.

CAPG 10.5.1

33
Q

AIA Document A201 stipulates binding arbitration. In those states where this is enforceable, then _________

A

….either party will be allowed to litigate the dispute.

CAPG 10.5.1

34
Q

If the A/E has failed to render a decision in the required time period, ____________

A

….a demand for dispute resolution may be made by either party.

CAPG 10.5.2

35
Q

Litigation can, in many instances, be the least desirable method of dispute resolution because _______

A

….the parties to the contract lose control of the outcome.

CAPG 10.5.3

36
Q

When a binding method of ADR is indicated, most judicial jurisdictions do not allow ______

A

….the parties to litigate a dispute.

CAPG 10.5.4

37
Q

Binding dispute resolution methods include:

A
  • Binding arbitration
  • Judicial Reference

CAPG 10.5.4

38
Q

Nonbinding dispute resolution methods include:

A
  • Mediation
  • Nonbinding Arbitration
  • Mini-trial
  • Disputes Review Board

CAPG 10.5.4

39
Q

When a claim has been decided by the initial decision maker, either party dissatisfied with the decision may __________

A

….make a demand for arbitration after an attempt at mediation.

CAPG 10.5.4

40
Q

One advantage of arbitration over litigation is that the arbitrator’s panel __________

A

….is composed of individuals with experience in the construction industry and its idiosyncrasies, and therefore is better able to understand and evaluate the claim

CAPG 10.5.4