Ch. 20 Perform Job Costing Activities Flashcards
1
Q
Why is it important to gather actual job costs during the course of a job?
A
To further improve future estimates and gather a good understanding if the project is on track to match the current estimate.
2
Q
What are some other project documents that are relevent to assessing the amount of work and costs incurred in a project?
A
Labor timesheets, and Invoices from Subcontractors.
3
Q
What is it called when you define a series of partial payments based on completing specific portions of work?
A
Interim Payments
4
Q
Why are interim payments beneficial?
A
It ensures that the AV company continues to receive revenue throughout the project.