Ch. 18 Create Estimates for AV Activities Flashcards

1
Q

Why would you put in contingency or management reserve costs in a proposal?

A

To cover any unforseen risks or costs to the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the first task that must be performed to estimate costs for a project?

A

Work Breakdown Structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a BOM?

A

A bill of materials that includes a list of equipment, supplies, and materials required for the project includin the quantity and cost of each item.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly