Case Study Flashcards

1
Q

What was the 2m3/day based on for Option 2?

A

Site and delivery team. I engaged and trusted their experience and expertise. I also believe it is an assumption, a reasonable assumption for the purpose of this estimate.

Carried out independent research if not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is an unchartered service?

A

It’s a service that was unknown. It was not on the drawings. If you find an unchartered service, work should be stopped.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

You mention buildability. What is this?

What qualifications do you have to advice on buildability?

A

Whether a project can be built and reflect the concept and design. Can it meet design, time, budget.

No qualifications. I speak to the Delivery Team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why did the Subcontractor not allow or foresee the S61 notice?

A

S61 allowed for longer, however their were complaints from the residents about previous work noise, so the local authority revised the S61 down to 2 hours only.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Surely with Option 3 you would just use the 40 day duration originally planned?

A

I get what you mean, and I did consider this, however, 2 factors:

  • I assumed 6 hours per day whereas the Subcontractor had originally done 8.
  • Also, there was a new interface issue on site, which wasn’t there before.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If something went wrong who would be liable?

A

MD - Answer (Matt / Efi)

I believe this answer is whoever owns ownership of the risk / design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why do you have an EWN on the programme? Are they required?

A

No they are not required. It’s choice.

They can be shown to show logic, however they should not drive any other activity.

The planners like to show them on HS2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Key Date?

A

A date by which work is to meet the condition stated in the Contract Data. They are inserted by the client at the tender stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a Defect?

What is a Defect Certificate?

What is a defects date?

What is the defect correction period?

A

Defect is:
- part of the works not in accordance with the WI
or
- not in accordance with law or the design.

Defect Certificate:
- list of defects the Supervisor has notified before the defects date that have not been corrected.

defect date:
- how long the Contractor (Subbie) will be liable to rectify defects in the works. It is 104 weeks on our contract.

defect correction period:
- is the period in which the Contractor must rectify a defect which has been notified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why did you choose Option C?

A
  1. Encourages good management / open communication & COLLABORATION between the parties.
  2. Because of SHARED ownership of risk, there is a willingness to cooperate to resolve issues amicably and work together.
  3. Can lead to better / quicker / more EFFICIENT ways of working, and therefore improvements in price and programme. The incentivisation to chase efficiency ties back to our responsibility (ROC Rule 5) to the client and public taxpayer.
  4. It should be noted, with the Option C, the payment mechanism works so that costs are more reflective of actual cost incurred than say, a lump sum price. They can be higher or lower. Either way, they are more reflective of REALITY which I believe is fair for the Subcontractor and also Client which shows them VfM, particularly as we single-source to this particular Subcontractor.
  5. Back-to-back with MWCC so can pass down main option clauses more easily.

Conclusion, although you may have greater ‘Risk and Cost Uncertainty’ under the Option C, you may actually end up with a lower price overall. At least one that is more reflective of reality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why did you choose an Option C over an Option A?

A

Just to start on risk allocation, usually where the scope is well defined, you would use an A or B. However, for this package there were a few things to note:

RISK
- risk was well fairly well defined. Because the scope had changed so much due to updated Ground Movement Assessments, there was still as risk that this may change again, though unlikely. The Subcontractor themselves expressed concerns around pricing this also.
- also, even though we say scope is well defined, it was deemed there was an interface and programme risk with other packages.

CE/QTE
- Less incentive for collaboration to help mitigate risks. The Subcontractor will issue a CE if it is one, and wait for it to be approved to put in a QTE with higher risk allowances.
- CE / QTE Exploitation (Explain, in next Q).
- We did an internal audit on CE QTEs on an already live Option A and Option C package for this Subbie. For similarly natured scope, quotes were 30% higher, on average on the Option A, which shows how they inflated those QTEs due to risk.

Conclusion, although Option A may have more Cost Certainty, the cost may be higher than a C.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

You mention that with the Option A, the subcontractor might exploit the recoverability of CEs. What do you mean by this? Can you not do this with an Option C?

A

The factors to this are Risk & Cost.

Option A allocates more risk to the Subcontractor. They price a lump sum price so take the risk on that price. The only way they can recover additional money is through CEs.

Yes, you can do this on an Option C also, however, with the Option A they will price the QTE for the CE with more risk than they would with an Option C, which naturally means a higher price. Once the CE is agreed and implemented, they can’t recover more.

That’s what I mean by CE exploitation… it’s the quoted value of the CE.

Also, it’s worth nothing that with Option A they would be paid the value of the implemented CE, HOWEVER, with Option C they wouldn’t. It would increase their target, but they would still only be paid Defined Cost.

We did an internal audit on CE QTEs on an already live Option A and Option C package for this Subbie. For similarly natured scope, quotes were 30% higher, on average on the Option A, which shows how they inflated those QTEs due to risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why is the Option A low financial risk to the client?

A

Subcontractor takes the risk and prices assumptions in its lump sum price. If something happens, that’s not a CE, they won’t recover it. This is different to, say, an Option C or E, where they get paid their Defined Cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What did you mean by ‘Under the A, the Subcontractor showed no intention to find price efficiencies & there is a lack of incentivisation to outperform’?

A

This was a reference to the values of their change. Their quotes were excessive due to higher risk inclusions (Explain). They may have internally found price efficiencies but at no benefit to us under the Option A when we are paying the agreed lump sum.

Performance - not as collaborative as a C due to shared risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why did you not consider the other NEC options B or D?

A

These were not the Options that the commercial team were preferencing. A, C & E were the preferences so this task was to provide analysis on those 3.

However, a re-measurable option like B & D were not used because the quantities required were unlikely to change. The scope was mainly monitoring work, as opposed to major excavation work, so the re-measurement benefit of a B or D would not have been utilised. Had we had large amounts of excavations lets say, we know what the scope is, we just don’t exactly know what the quants are, then B would be useful, but this wasn’t the case.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why not B in particular?

A

Quantities required were unlikely to change.

Mainly because no pain/gain target mechanism which the C brings you.

17
Q

Why not the D then?

A

Again quantities unlikely to change.

With Option D, the Client takes the risk of errors in the BoQ, so changes in BoQ Qty would result in a CE. If we forgot to put something in BoQ, that’s our risk. We wouldn’t want to take this risk. We wanted them to provide us what they believed was needed. Extra: (Qty risks are shared on C).

I’m also aware that D can be more tricky to administer because not only do you have the Defined Cost checking and audits for that, but you also have to keep track of and calculate whether the 0.5% mechanism for change in quantities. Essentially, where the Qty done is different to the Qty stated in the BOQ, this can become a CE. For an item, if the Rate in the BoQ x the final total Qty of work done is more than 0.5% of the total prices at the Contract Date (entered into), and the differences cause a change in Defined Cost, this is a CE.

From speaking to experienced and competent colleagues, it isn’t really used.

18
Q

Why did you not choose D over C when subcontractor was using a BoQ?

A

The simple answer to that is that Option C was stated in the conditions of contract within the tender, and Option C had been previously agreed.

However, Option C over Option D reasons are (as stated in previous Q).

19
Q

Why not Option E?

A

Higher client risk, unnecessary due to the scope being fairly well defined to inform a price.

20
Q

How is disallowed cost applied to pain/gain?

A

We are not paid the cost at all. It comes off our bottom line which is a situation we really need to avoid.

21
Q

Is your pain/gain in the subcontract the same as in the MWCC?

A

No.

There are share ranges in both, but they differ slightly.

22
Q

What is NEC Option F? Why did you not consider it?

A

Management Contract (cost reimbursable).

Contractor does not carry out any construction work. They engage Subcontractors.

These were not the Options that the commercial team were preferencing. A, C & E were the preferences so this task was to provide analysis on those 3.

However, because it is cost-reimbursable which is unnecessary risk for SCSJV & HS2.

23
Q

Do you know what NEC Option G is?

A

Term Contract.

It’s a professional service contract (PSC) for the appointment of consultants.

Based on a priced schedule.

24
Q

What is Defined Cost?

A

This is a defined term under Cl 11.2. The SoCC or SSoCC are options to calculate Defined Cost.

A&B - It is the cost of the components stated in the SSoCC (A-B).

C/D/E - is the amounts due to the Subcontractor for works which are subcontracted & the cost of the components stated in the SoCC (Options C-E) for other work (Essentially the costs the Subcontractor incurs). SSoCC can be used on C-E if agreed by both parties.

25
Q

What is Disallowed Cost?

A

Cost the PM decides is not justified by accounts or records / should not have paid the supply chain in accordance with the contract / didn’t follow procurement process / didn’t give an EWN / also mentions correcting Defects after Completion / Resources, Plant & Materials not used to Provide the Works…

and therefore is not recoverable.

This is a defined term for Options C,D,E,F… (you have to have Defined Cost to have Disallowed Cost).

26
Q

What is a Schedule of Cost Components?

A

The SoCC sets out what the Subcontractor will be paid for and how that is calculated.

The cost components in the schedules include people, equipment, plant and materials, charges, manufacture and fabrication, design and insurance.

If a cost item is not listed in the schedules, then it is not a Defined Cost and is instead deemed included in the Fee, as per Cl 52.1.

27
Q

For the option C, did you use the SoCC or the SSoCC?

List some of the items in the SoCC, but not in shorter SoCC. How are these covered under the SSoCC?

A

Full SoCC.

SSoCC - A & B
SoCC - C, D & E (unless otherwise agreed to use shorter for CE assessments cl 63)

Full SoCC - Sick pay. Travel subsidence.
SSoCC covers minimum law requirements, then the full contains extras.

28
Q

Difference between ‘subcontracted fee percentage’ and ‘direct fee percentage’?

A

Subcontracted = cover overheads and profit

Direct = cover direct costs

However, NEC drafters found that bidders usually use the same fee for both, so changed this to a single fee percentage for NEC4.

29
Q

Did you consider a short form? Also what about other suites of contract?

A

We tend to not use them unless complexity, risk and price is low.

£1.2m quite a large package so the short form was dismissed by the procurement team at an early stage.

ECC/ECS/ECSC/ECSS - Suited for D&B.
PSC - Providing a service.
TSC - Maintenance or operating.

30
Q

Under an Option C, if VE leads to a change in the WI, this will reduce the target. What is the incentive under the C then?

A

VE doesn’t mean the WI changes, just better / more efficient ways of carrying out the WI.

On the flip side, VE & innovation could cost more, which can increase the target, but in the long-run add value to the project.

31
Q

How do you incorporate VE opportunities into a NEC3 contract?

A

Not NEC term. Done through CEs (can be a change to the WI).