18. CA Flashcards

1
Q

What is the difference between forecast defined cost and actual defined cost?

A

Clause 63.1 states actual Defined Cost of the work already done, and forecast Defined Cost of the work not yet done.

There is a dividing date, which is now used in NEC4, which is the date the Project Manager gives an instruction to change the Scope.

Extra notes & example… the majority of CEs will be based upon forecast Defined Cost. This protects the Client when they believe the Contractor may have gone a lot slower than they needed to do. If the client/PM believes a reasonable forecast was six days and the Contractor took ten days, the client/PM could still assess it based on six days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is NEC Option C? How is the Contractor paid on an Option C?

A

Target cost contract

Paid defined cost plus fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Talk about the NEC Option A payment provisions.

A

Items in the Activity Schedule are only paid once complete. This is the same for Change.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the pain/gain mechanism?

A

There is a target, built up from the activity schedule. CEs move the target.

At the end of the project, total cost is then compared to the target.

The difference is a Saving/Overspend. This is shared between the Employer and the Contractor. The % split is stated in the Contract Data Part 1. HS2 is not 50/50, it’s based on a matrix.

This is Gain/Pain. It is an incentivised arrangement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name some contractual provisions.

A

payment terms
party obligations
secondary clauses (e.g. bonds)
insurances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the responsibilities of the contract administrator?

A

Chairing meetings, giving instructions and good record keeping. The contract administrator must act in a manner that is independent, impartial, and fair.

This relates to (ROC Rule 1), acting with integrity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Name examples of the secondary clauses.

A

X1 Price adjustment for inflation
X4 PCG
X5 Sectional Completion
X6 Bonus for Early Completion
X7 Delay Damages
X13 Performance Bond
X16 Retention
X20 KPIs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the Y1, Y2 & Y3 secondary clauses?

A

Y(UK)1 – Project Bank Account
Y(UK)2 – The HGCRA 1996
Y(UK)3 – The Contracts (Rights of Third Parties) Act 1999

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who adds the Z clauses?

A

These are additional clauses, added by the client (or Contractor if Employer). Advised to keep to a minimum as not not affect other clauses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who fills in the Subcontract Data Part 1? What does it contain?

A

Client / Employer

General Information, e.g. period for reply
Scope (SO IMPORTANT IT IS CLEAR)
Specifications
Site Information e.g. site boundaries
Adjudicator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who fills in the Subcontract Data Part 2? What does it contain?

A

Subcontractor

General information e.g. fee percentage, price, list of sub subs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why is it important scope is clear?

A

To avoid ambiguities in scope / task.

If any ambiguities, the Employer will have to compensate the Subcontractor for any ambiguities in scope.

Also to avoid dispute.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How long have you got to raise a CE? And PM to respond?

A

Timeframes are what’s in the contract, but on HS2…

Clause 60.1 is the CE.

  • Clause 61.3 Contractor to notify a CE within 8 weeks (MWCC) or 6 weeks (S/C) of becoming aware of the event. If not, he is not entitled to a change in the prices, the completion date or a key date (time). The scenario where this doesn’t apply is if the PM should have notified the event under 14.3 (giving an instruction).
  • Clause 61.4 PM responds within 4 weeks (1 week standard form) and asks for a quote.

If no response from PM, Contractor notifies non-response. If another 4 weeks pass (2 weeks standard form), the CE is deemed accepted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How long have you got to issue a quotation after the PM instructs for it?

A

Timeframes are what’s in the contract, but on HS2…

62.3 - Contractor submits quotation within 4 weeks of being instructed to do so (3 weeks standard form).

PM replies within 4 weeks
(2 weeks standard form). Also 4 weeks for any revised quotations.

62.6 - If no response from PM, Contractor notifies non-response. If another 4 weeks pass (2 weeks standard form) the QTE is deemed accepted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why is it important to raise EWNs? (Referral)

A

If you don’t, you are not giving the client the opportunity to help with its mitigation.

Both parties have a responsibility to work collaboratively to raise EWNs and mitigate risk (RRMs).

Clause 61.5 - Client notifies failure to submit EWN when he instructs him to submit a quotation.

Clause 63.5 - If a timely EWN would have provided an opportunity to identify a more efficient method of resolving the issues, then the Client will only assess and pay the Contractor for that method, as if he had given the EWN. The significance is that it could be assessed at a lower value, so less recoverability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who can raise EWNs?

A

Subcontractor, Contractor, PM.

17
Q

What are the HGCRA payment timescales?

A

Payee submits an AFP on the assessment date.
Payer notifies payment on the payment notice date (about 2 weeks later)
If the payer changes their mind, they must issue a pay less notice no later 1 week (5 days) before the final date for payment.

The HGCRA 1996 states that the payee is entitled to periodic payments. It also provides that a construction contract must contain an adequate mechanism for:
- ‘due date’
- ‘final date’

18
Q

What happens if the subcontractor disagrees with the value of the payment?

A

Correct in the next payment.

Could say about how they didn’t like it once, so going forward to mitigate that conflict, I sent it to them in advance of the payment notice date, so if they had any query there would be time for myself to take another look.

Raise a complaint via CHP

19
Q

How do you go about developing the payment certificate?

A

Excel.

Party names addresses
Package
Certificate Number
Date
Order Value
My name & date assessed
Employer’s liability
Public liability
PI
Gross certification
Previously Certified
This Payment
Signatures

20
Q

How are change procedures defined within the contract?

A

Clause 60 section.

21
Q

What clause is unforeseen physical conditions?

A

60.1 (13) on HS2 contact (not standard)

encounters physical conditions which… are not referred to in the GBR… and… are not conditions an experienced and prudent subcontractor would have judged to have such a small chance of occurring, that it would be unreasonable for them to allow for.

22
Q

6 weeks or 8 weeks to notify a CE under NEC?

A

The MWCC (NEC3 ECC Option C) = 8 weeks

Majority of subcontract packages = 6 weeks (SCSJV changed the timeframes to give us time to raise CEs up the line to HS2 (extra 2 weeks))

23
Q

What is an extension of time?

A

Adjustment to Completion Date due to delay caused by CE.

24
Q

Role of PM & Supervisor in NEC?

A

Both appointed by client.

PM = duties on behalf of the Employer e.g. giving instructions.
Supervisor = protects the interests of site.

25
Q

Why have you got terms like Activity Schedule, Defined Cost in capital letters.

A

Clause 11. It is a defined term.

26
Q

Is it compensation event or Compensation Event?

Is it early warning notification or Early Warning Notification?

A

Small caps

27
Q

Example of when you have managed change?

A

Additional UKPN duct survey to ascertain if it can be used for another live package…

Cl 14.3 issue instruction
61 Notify CE & Request QTE
Receive QTE, respond to QTE
Agreed & Implement

This also includes a programme so both price and programme need to be assessed, agreed and implemented.

28
Q

Anything in italics is what?

A

Found in Contract Data Pt 1.

29
Q

What is float?

What is terminal float?

A

How long an activity can be delayed without affecting the Completion.

Difference between planned Completion and the Completion Date (only were PC is before CD).