12. CM Flashcards

1
Q

What are liabilities? What do they do?

A

Amount that is owed to the supply chain. (If the Contractor went bust, what payment is due to the Subcontractor).

They show the financial position of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain the cash flow process on your project. How have you prepared cashflow? (Referral)

A

I put together my liabilities. L, P, M, Prelims etc.

HS2 pay SCSJV our liabilities that are reported, minus applicable deductions, Plus Fee, into our project bank account. These deductions can be:
- queries, in month reasoning.
- when they believe something may be a Disallowed Cost, records.

Payment is then split equally between the parent companies on the JV.

I ensure liabilities are done before payments because liabilities are the cash in, which then enables the cash out to the supply chain (important to pay to comply with HGRCA).

CASH IN VS CASH OUT…

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Talk me through a time you advised on cashflow?

A

F&R

Liabilities = Short-term cash flow (in month / EV)
EAC = Long-term cash flow (future / EAC)

  • L3 Example - I monitored the progress of the works on site against the agreed programme. Performance on site was slower due to harder ground than anticipated, which affected our EV (forecast/budget spend vs actual spend), and therefore EAC. This advised increased future cashflow is required.
  • L3 Example - brick egg sewer.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What can applicable deductions be?

A
  • queries, in month reasoning.
  • when they believe something may be a Disallowed Cost, records.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Give examples of costs of a project.

A

Labour
Plant
Materials
Staff wages
Preliminaries

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are preliminaries?

A

Preliminary costs related to a construction project can be diverse.

You can have people, plant, materials, but it is usually site establishment costs (e.g. site accommodations and welfare facilities) and site running costs (e.g. water, heating, electricity).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What did you learn from the GN on Cash Flow Forecasting, 1st edition?

A

GN on Cash Flow Forecasting, 1st edition states that there are 2 main types of cash flow forecasting: company & project.

  1. Materials on and off site.
    o On site - QS should not allow payment to be made for materials that are brought onto site well in advance just to boost the Contractor/Subbies cash flow.
    o Off site – QS to be mindful this can impact cash flow forecast, as some materials made off-site / pre-fabricated, e.g. bathroom pods, may be paid earlier than usual.
  2. It also talks about the HGCRA 1996, aka The Construction Act and how it attempted to improve payment practices in the UK by improving cash flow & cash flow forecasting. E.g. requiring periodic payments & early communication of the amount that will be paid.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What techniques have you used to financially manage subcontractors?

A

Weekly progress meetings.
Quarterly review meetings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What do you know about materials on and off site?

A

o On site - QS should not allow payment to be made for materials that are brought onto site well in advance just to boost the Contractor/Subbies cash flow.
o Off site – QS to be mindful this can impact cash flow forecast, as some materials made off-site / pre-fabricated, e.g. bathroom pods, may be paid earlier than usual.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What causes for monthly liability variances would you advise can be expected on your project?

A

Change / Variations.
Delays (site access).
Obstructions.
Weather conditions.
Resequencing of works.
Progressing on site quicker / slower.
Inaccurate forecasting in the first place.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How have you collected data for reports?

A

For F&R, I collect data from the site team. E.g. progress on site to date, and likely lookahead programme & forecast.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is cost reporting? How do you go about producing a cost report / forecasting / reporting?

(Dai & Emil - will be asked)
Same Q as PF Q3

A

Cost Reporting is to inform the client of the likely outturn cost of the project. Also seniors / directors / parent company.

On a monthly basis, I carry out:
Liabilities - what we are liable to pay our supply chain. Liabilities are a build up of elements like L, P, M, Prelims. These go into the project cost report. This becomes Cost To Date. In the CVR/F&R meeting, I then advise my Seniors, Directors and the client of variances in forecast vs actual spend in the last period. Is performance on site slower (perhaps obstructions in the ground or harder ground), in which case this would affect our Earned Value (EV). EV is a metric that shows the value of the work completed, against the forecasted (budgeted) value of work. EAC would therefore increase.

Forecasts - speaking to the internal delivery team to establish a likely programme lookahead. They will consider methodology. I attribute costs made up of L, P, M, Prelims & Risk against activities on the programme. This shows a forecast spend per month, and a cost to complete, and then an overall EAC (the outturn cost of the project). Again, any variances, I have to advise the client in the F&R meeting with them.

My example L3 - for this is the Brick Egg Sewer HS2 originally said was not a CE. I advised it was because it wasn’t in the GBR or other Site Information. On our contract, the GBR has been added to Clause 60.1.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Cost value reconciliation (CVR)?

A

Cost value reconciliation (CVR) monitors and measures actual expenditure against budgeted project expenditure. CVR gives you a running account of the project’s profitability by comparing cost and value at given points in the project lifecycle. Relates to Earned Value (EV) analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How have you advised profitability?

A

CVRs. EV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How have you advised the client change movement?

A

HS2 Change Register, updated monthly, advising reasons for movement. For example, I advised the client of an increase to change due to the discovery of a brick egg sewer upon excavation which was not shown on the pre-existing site information or Geotechnical Baseline Report (GBR), advising this resulted in a CE. At first the client did not accept as a CE, but when I explained it was not in the Site Info or GBR, and that we had an amended 60.1 GBR clause, they finally accepted.

Quotation agreement fluctuations are also explained, for example, reduction in quotation value due to a reduction in the plant assessment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How have you applied a Value Engineering process?

A

On one of their quotations for a compensation event, I saw primary type 1 concrete. I knew this was an expensive rate (£60 per m3). I requested they use recycled type 1 concrete to backfill instead (half the rate), as long as it met specifications. It did. They used it.

Another example was the vac ex options mentioned in my case study.

Another is the foam concrete explored, but never actually eventualised because the local Council were not happy with the spec.

17
Q

What factors must be considered when carrying out VE?

A

Ensuring that quality is not affected by a reduction in time or cost.

18
Q

Explain iTWO and how you use this to advise the client.

A

I manage iTWO entry.

For one particular section of work, I carried out a bottom-up review of the budget. This included costs for staff, welfare, and traffic management (TM). On this software, I was able to link costs to activities in the Clause 32 programme with HS2. I presented findings to senior management and the client, advising why specific costs had been spread across specific activities, and the impact this had on the project.

19
Q

What is Earned value (EV)?

A

Earned value (EV) is a metric that shows the value of the work that has been completed against the forecasted (budgeted) value of work.

20
Q

Personal question for MD - Explain the BI3 & ANNEX E scenario in case I need to explain why I haven’t raised a CE.

A

Annex E - additional referenced document to the main contract

Budget Item - anything described in this e.g. (Unknown Utilities, TM for Utilities) that eventualises, is automatically deemed a CE, pre-agreed with the client.

21
Q

What is disallowed cost?

A

Cost the PM decides is not justified by accounts or records / should not have paid the supply chain in accordance with the contract / didn’t follow procurement process / didn’t give an EWN / also mentions correcting Defects after Completion / Resources, Plant & Materials not used to Provide the Works…

and therefore is not recoverable.

This is a defined term for Options C,D,E,F… (you have to have Defined Cost to have Disallowed Cost).

22
Q

What is the difference between cost flow and cash flow?

A

I’m not sure. It’s in the commercial management GN so I would refer to that.