Admin & Project Management - Henry's Class (Day 2) Flashcards
The following roles are associated with what kind of employee in the planning department: communication of the agency’s goal to subordinate, motivation of subordinates, coordination of subordinates, and reporting of the agency’s work and accomplishments.
Planning director
___________ is a unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project.
Deliverable
_________ is a marker that consumes no time or resources.
Milestone
______________ models activities and events of a project as a network, based on the longest overall duration of dependent activities which determine the shortest time possible to complete the project.
Critical path
The primary purpose of a project charter is to get __________________?
management approval to proceed
___________is a probabilistic model and estimates based on the probability of occurrence.
PERT
__________________ focuses on the sequence of required scheduled activities that determine the duration of the project, it is a deterministic model of probability of occurrence
Critical Path Method
Any delay in critical tasks will delay __________________?
The rest of the project
What would you do if you are behind schedule or over budget?
Fast Track or Crash
__________ is running two or more tasks in parallel.
Fast Track
______________ is adding resources without changing the Work Breakdown dependencies.
Crashing
__________________ uses a mathematical or graphical technique to find the optimal way to use limited resources
Linear programming
Typically the _______________ is used to determine the longest duration and cost required for completing the project.
Critical path method (CPM)
Critical Path Method is a project management
technique designed to:
A. Help employees improve writing skill
B. Assist in decision making
C. Reduce errors in traffic modeling
D. Identify evacuation routes
B
The term “Fast Tracking” can be described as which of the following?
A) Deciding as a group what tasks to cut to get a project completed on time
B) Skipping over tasks on a planning project
C) What occurs when time needs to be made up on a planning project
D) All of the above
C