7.0 Project Cost Mgmt Terms Flashcards
An estimating approach that starts from zero, accunts for each component of the WBS, and arrives at a sum for the project. It is completed with the project team and can be one of the most time-consuming and most reliable methods to predict project costs
Bottom up estimating
this estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for this estimate can be from -10% to +25
budget estimate
A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.
Commercial database
A contingency allowance to account for overruns in costs. contingency allowance are used at the project manager’s discretion and with management’s approval t counteract cost overruns for scheduled activities and risk events.
Contingency reserve
Costs are parallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts. Each control account then is aggregated to the sum of the project costs.
Cost aggregation
A time-lapse exposure of when the project monies ae to be spent in relation to cumulative values of the work completed in the project.
cost baseline
the cost aggregation achieved by **assigning specific dollar amounts for each of the scheduled activities **or more likely for each of the work packages in the WBS. cost budgeting applies the cost estimates over time.
Cost budgeting
a system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost.
cost change control system
the cost management plan dictates how cost variances will be managed
cost management plan
The monies spent to recover from not adhering to the expected level of quality. Examples may include rework, defect repair, loss of life or limb because safety precautions were not taken, loss of sales, and loss of customers. this is also know as cost of nonconformance to quality.
Cost of poor quality
the monies spent to attain the expected level of quality within a project. Examples include training, teting, and safey precautions.
cost of quality
This estimate type is of the most accurate. Its used late in the planning processes and is associated with bottom-up estimating. You need the WBS in order to create the definitive estimate. The range of variance for the estimate can be from -5% to +10%.
definitive estimate
Costs attributed directly to the project work and cannot be shared among project (for example, airfare, hotels, long-distance phone charges, and so on)
direct costs
An earned value management formula that predicts how much funding the project will require to be completed. Three variations of this formula are based on conditions the project may be experiencing.
Estimate to complete (ETC)
Costs that remain constant throughut the life of the project (the cost of a piece of rented equipment for the project, the cost of a consultant brought on to the project, and so on)
fixed costs