6.0 Project Schedule Mgmt Terms Flashcards
Activity List
the primary output of breaking down the WBS work packages
Alternative Analysis
The identification of more than one solution. Consider roles, materials, tools, and approachs to the project work
Analogous estimating (Top-down)
also in Project Cost Mgmt Terms
a somewhat unreliable estimating approach that relies on historical information to predict what current activity durations should be. Analogous estimating is more reliable however than team member recollections. Analogous estimating is also know as top down estimating and is a form of expert judgement
Bottom Up estimating
The most accurate time and cost estimating approach a project manager can us. this estimating approach starts “at the bottom” of the project and considers every activity, and the exact amount of resources needed to complete each activity.
Control Account
A WBS entry that considers the time, cost, scope measurements for that deliverable within the WBS. The estimated performance is compared against the actual performance to measure overall performance for the deliverables within that control account. The specifics of a control account are documented in a control account plan.
control threshold
a predetermined range of accceptable variances, such as +/- 10 percent off schedule. Should the variance exceed the threshold, then the project control processes and corrected actions will enacted.
Crashing
A schedule compression approach that adds more resources to activities on the critical path to complete the project earlier.. When crashing a project, costs are added because the associated labor and sometimes resources (such as faster equipment) cause costs to increase.
critical path
the path in the project network diagram that cannot be delayed,, otherwise the project completion date will be late. there can be more than one critical path. Activities in the critical have no float (no delay)
discretionary dependencies
These dependciences are the preferred order of activities.. Project managers should use these relationships at their discretion and should document the logic behind the decision. Discretionary dependencies allow activities to happen in a preferred order because of the best practices, condition unique to the project work, or external events. Also known as preferential or soft logic
early finish
the earliest a project activity can finish. Used in the forward pass procedure to discover the critical path and the project float.
Early Start
the earliest a project activity can begin. Used in forward pass procedure to discover the critical path and the project float.
External Dependencies
As the name implies, these are the dependencies outside of the project’s control. Examples include the delivery of equipment from a vendor, the deliverable of another project, or the descision of a committee, lawsuit, or expected new law.
Fast tracking
A schedule compression method that changes the relationship of activities. With fast tracking, activities that would normally be done in sequence are allowed to be done in parallel or with some overlap. Fast tracking can be accomplished by changing the relation of activities from finish to start (FS) to SS or even Finish to finish (FF) or by adding lead time to downstream activities. However, fast tracking does add risk to the project.
Finish to finish
an activity relationship type that requires the current activity to be finished before its successor can finish
finish to start
an activity relationship type that requires the current activity to be finished before its successor can start.
Fragnet
A representation of a project network diagram that is often used for outsourced portions of a project, repetitive work within a project, or a subproject. Also called subnet.
Free float
this is the total time a single activity can be delayed without affecting the early start of its immediately following successor activities.
Hard logic
Logic that describes activities that must hapen in a particular order. For example, the dirt must be excavated before the foundaton can be built. the foundation must be in place before the framing can begin. Also known as a mandatory dependency