7 Flashcards
It includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget.
Project Cost Management
The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.
Plan Cost Management
The process of developing an approximation of the monetary resources needed to complete project work.
Estimate Costs
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Determine Budget
The process of monitoring the status of the project to update the project costs and manage changes to the cost baseline.
Control Costs
The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project
Plan Cost Management
It is a component of the project management plan and describes how the project costs will
be planned, structured, and controlled.
Cost Management Plan
The key benefit of this process is that it determines the monetary resources required for the project.
Estimate Costs
cE = (cO + cM + cP) / 3
Three-Point Estimate (Triangular distribution)
cE = (cO + 4cM + cP) / 6
Three-Point Estimate (Beta/PERT distribution)
Include quantitative assessments of the probable costs required to complete project work, as well as contingency amounts to account for identified risks, and management reserve to cover unplanned work
Cost Estimates
The amount and type of additional details supporting the cost estimate
Basis of Estimates
Cost estimates are aggregated by work packages in accordance with the WBS
Cost Aggregation
The work package cost estimates, along with any contingency reserves estimated for the work packages, are aggregated into:
control accounts
The summation of the control accounts make up the:
cost baseline
Management reserves are added to the cost baseline to produce the:
project budget
The key benefit of this process is that the cost baseline is maintained throughout the project. This process is performed throughout the project.
Control Costs
It compares the performance measurement baseline to the actual schedule and cost performance. It integrates the scope baseline with the cost baseline and schedule baseline to form the performance measurement baseline
Earned value analysis
The value of the work planned to be completed to a point in time, usually the data date, or project completion.
Planned value