11 Flashcards

1
Q

It includes the processes of conducting risk management planning, identification, analysis, response planning, response implementation, and monitoring risk on a project.

A

Project Risk Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The process of defining how to conduct risk management activities for a project.

A

Plan Risk Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The process of identifying individual project risks as well as sources of overall project risk and documenting their characteristics.

A

Identify Risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.

A

Perform Qualitative Risk Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives.

A

Perform Quantitative Risk Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks.

A

Plan Risk Responses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The process of implementing agreed-upon risk response plans.

A

Implement Risk Responses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project.

A

Monitor Risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

It’s an uncertain single event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.

A

Individual project risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

It’s the effect of uncertainty on the project as a whole, arising from all sources of uncertainty including individual risks, representing the exposure of stakeholders to the implications of variations in project outcome, both positive and negative.

A

Overall project risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

They’re recorded in the risk management plan. They should be expressed as measurable risk thresholds around each project objective. These thresholds will determine the acceptable level of overall project risk exposure, and they are also used to inform the definitions of probability and impacts to be used when assessing and prioritizing individual project risks.

A

Stakeholder risk appetite

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Opportunities and threats are represented in a common probability and impact matrix using positive definitions of impact for opportunities and negative impact definitions for threats. Descriptive terms (such as very high, high, medium, low, and very low) or numeric values can be used for probability and impact. Where numeric values are used, these can be multiplied to give a probability-impact score for each risk

A

Probability and impact matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

It’s a predetermined list of risk categories that might give rise to individual project risks and that could also act as sources of overall project risk. It can be used as a framework to aid the project team in idea generation when using risk identification techniques. For example: TECOP, PESTLE or VUCA.

A

Prompt Lists

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

TECOP

A

Technical, Environmental, Commercial, Operational, Political

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

It presents information on sources of overall project risk, together with summary information on identified individual project risks.

A

Risk Report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Captures details of identified individual project risks. The results of Perform Qualitative Risk Analysis, Plan Risk Responses, Implement Risk Responses, and Monitor Risks are recorded in it.

A

Risk Register

17
Q

The key benefit of this process is that it focuses efforts on high-priority risks.

A

Perform Qualitative Risk Analysis

18
Q

For each risk who will take responsibility for planning an appropriate risk response and ensuring that it is implemented

A

Risk Owner

19
Q

Evaluates the degree to which the data about individual project risks is accurate and reliable as a basis for qualitative risk analysis.

A

Risk data quality assessment

20
Q

Considers the likelihood that a specific risk will occur. Considers the potential effect on one or more project objectives such as schedule, cost, quality, or performance. Impacts will be negative for threats and positive for opportunities

A

Risk probability and impact assessment

21
Q

It’s a grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.

A

Probability and impact matrix

22
Q

Where risks have been categorized using more than two parameters. For example, a bubble chart displays three dimensions of data.

A

Hierarchical charts

23
Q

The key benefit of this process is that it quantifies overall project risk exposure, and it can also provide additional quantitative risk information to support risk response planning. This process is not required for every project, but where it is used, it is performed throughout the project.

A

Perform Quantitative Risk Analysis

24
Q

Uncertain duration, cost, or resource requirement for a planned can be represented in the model as a probability distribution. Other sources of uncertainty may also be represented using branches to describe alternative paths through the project.

A

Representations of Uncertainty

25
Q

Quantitative risk analysis uses a model that simulates the combined effects of individual project risks and other sources of uncertainty to evaluate their potential impact on achieving project objectives. They’re typically performed using a Monte Carlo analysis.

A

Simulation

26
Q

They’re used to support selection of the best of several alternative courses of action. Alternative paths through the project are shown in branches.

A

Decision tree analysis

27
Q

They’re graphical aids to decision making under uncertainty. It represents a project or situation within the project as a set of entities, outcomes, and influences, together with the relationships and effects between them.

A

Influence diagrams

28
Q

The key benefit of this process is that it identifies appropriate ways to address overall project risk and individual project risks. This process also allocates resources and inserts activities into project documents and the project management plan as needed.

A

Plan Risk Responses

29
Q

It’s appropriate when the project team or the project sponsor agrees that a threat is outside the scope of the project or that the proposed response would exceed the project manager’s authority. These risks are managed at the program level, portfolio level, and not on the project level.

A

Escalate

30
Q

It’s when the project team acts to eliminate the threat or protect the project from its impact. It may involve changing some aspect of the project management plan or changing the objective that is in jeopardy in order to eliminate the threat entirely, reducing its probability of occurrence to zero.

A

Avoid

31
Q

Involves shifting ownership of a threat to a third party to manage the risk and to bear the impact if the threat occurs. It often involves payment of a risk premium to the party taking on the threat.

A

Transfer

32
Q

An action is taken to reduce the probability of occurrence and/or impact of a threat.

A

Mitigate

33
Q

It acknowledges the existence of a threat, but no proactive action is taken.

A

Accept

34
Q

This strategy may be selected for high-priority opportunities where the organization wants to ensure that the opportunity is realized.

A

Exploit

35
Q

The key benefit of this process is that it ensures that agreed-upon risk responses are executed as planned in order to address overall project risk exposure, minimize individual project threats, and maximize individual project opportunities.

A

Implement Risk Responses

36
Q

The key benefit of this process is that it enables project decisions to be based on current information about overall project risk exposure and individual project risks.

A

Monitor Risks