6 Schedule Flashcards
Schedule Process groups:
Plan schedule man Define activities Sequence activities Estimate activity durations Develop schedule Control schedule
Project Schedule Management: Key concepts
Detailed plan of how and when project delivers products, services, results
Tool for communication, managing stakeholders expectations and base for performance reporting
Choose schedule method
Project data -> Tool -> project schedule
Smaller projects (all done at the same time)
Keep it as flexible as possible
Types of schedule
activity list
Bar chart (Gantt)
Network diagram
Plan Schedule Process
Planning
Define policies procedures and documentation for
- planning, developing, managing, executing, controlling schedule
How to manage schedule start to finish
Plan Schedule management inputs
Project charter
PM Plan > Scope Management Plan, developmental approach
EEF/OPA
Plan Schedule Management Outputs
Schedule management plan
Define activities inputs
PM plan >Schedule man plan, scope baseline
EEF/OPA
Define activities outputs
Activity list activity attributes Milestone list Change requests PM plan > Schedule baseline, cost baseline
Scheduling methods
Iterative schedule with back log
>rolling wave (agile)
>Requirements = user stories
>Product features = time box
On-demand
>Laban approach
> pull work from back log
Scheduling in agile considerations
Short cycles, do, check ->feedback, adapt (move to next iteration )
Scheduling is iterative, on demand
Big companies: use predictive, adaptive, hybrid as part of a long-term roadmap
Sequence Activities Process
Planning
Identify and document relationships btwn Activities
Defines logical sequence of work
Sequence Activities inputs
PM plan > Schedule man plan, Scope baseline
Project documents > activity attributes, activity list, assumption log, milestone list
Sequence Activities T/T
PDM - precedence diagramming method
Dependency determination and integration
Leads & lags
PMIS
Define actives T/T
EJ
decomposition
Rolling wave planning
Meetings
Estimate Activity Durations Process
Planning
How many work periods are required
Estimate Activity Durations considerations
Law of diminishing returns
Number of resources - no linear relation between duration and # of ppl
Advances In Technology - can affect duration and resources
Motivation of staff - procrastination, Parkinson’s law (use all time available)
Estimate Activity Durations inputs
PM Plan > Schedule man plan, scope baseline
Project doc> activity attributes, activity list, assumption log, LL, milestone list, proj team assignments, resource BS, resource calendars, resource requirements , risk register
EEF/OPA
Estimate Activity Duration T/T
EJ Analogous Est Parametric Three-point Bottom up Data analysis >alternatives analysis, reserve analysis Decision making Meetings
Estimate Activity Duration Outputs
Duration estimates Basis of estimates Project documents updates - activity log - assumption log - LL
Analogous estimating
Use info from previous project
Parametric estimating
An algorithm is used to calculate cost or duration based on historical data and the project.
Three-point estimation
Use formula
P = pessimistic
M= most likely
O= optimistic
Triangular: (p+m+o)/e
Beta: (p+ 4m + o)/y
Bottom up estimating
Combining the lower level costs of the WBS
Sequence Activities outputs
Project schedule network diagrams
Project documents > activity attributes, activity list, assumption log, milestone list