6 Schedule Flashcards

1
Q

Schedule Process groups:

A
Plan schedule man
Define activities
Sequence activities
Estimate activity durations
Develop schedule
Control schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project Schedule Management: Key concepts

A

Detailed plan of how and when project delivers products, services, results

Tool for communication, managing stakeholders expectations and base for performance reporting

Choose schedule method

Project data -> Tool -> project schedule

Smaller projects (all done at the same time)

Keep it as flexible as possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Types of schedule

A

activity list
Bar chart (Gantt)
Network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Plan Schedule Process

A

Planning
Define policies procedures and documentation for
- planning, developing, managing, executing, controlling schedule

How to manage schedule start to finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Plan Schedule management inputs

A

Project charter
PM Plan > Scope Management Plan, developmental approach
EEF/OPA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Plan Schedule Management Outputs

A

Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define activities inputs

A

PM plan >Schedule man plan, scope baseline

EEF/OPA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define activities outputs

A
Activity list 
activity attributes
Milestone list
Change requests
PM plan > Schedule baseline, cost baseline
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Scheduling methods

A

Iterative schedule with back log
>rolling wave (agile)
>Requirements = user stories
>Product features = time box

On-demand
>Laban approach
> pull work from back log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Scheduling in agile considerations

A

Short cycles, do, check ->feedback, adapt (move to next iteration )

Scheduling is iterative, on demand

Big companies: use predictive, adaptive, hybrid as part of a long-term roadmap

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Sequence Activities Process

A

Planning

Identify and document relationships btwn Activities
Defines logical sequence of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Sequence Activities inputs

A

PM plan > Schedule man plan, Scope baseline

Project documents > activity attributes, activity list, assumption log, milestone list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Sequence Activities T/T

A

PDM - precedence diagramming method
Dependency determination and integration
Leads & lags
PMIS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Define actives T/T

A

EJ
decomposition
Rolling wave planning
Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Estimate Activity Durations Process

A

Planning

How many work periods are required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Estimate Activity Durations considerations

A

Law of diminishing returns
Number of resources - no linear relation between duration and # of ppl
Advances In Technology - can affect duration and resources
Motivation of staff - procrastination, Parkinson’s law (use all time available)

19
Q

Estimate Activity Durations inputs

A

PM Plan > Schedule man plan, scope baseline
Project doc> activity attributes, activity list, assumption log, LL, milestone list, proj team assignments, resource BS, resource calendars, resource requirements , risk register
EEF/OPA

20
Q

Estimate Activity Duration T/T

A
EJ
Analogous Est
Parametric
Three-point
Bottom up
Data analysis >alternatives analysis, reserve analysis
Decision making
Meetings
21
Q

Estimate Activity Duration Outputs

A
Duration estimates
Basis of estimates 
Project documents updates
- activity log
- assumption log
- LL
22
Q

Analogous estimating

A

Use info from previous project

23
Q

Parametric estimating

A

An algorithm is used to calculate cost or duration based on historical data and the project.

24
Q

Three-point estimation

A

Use formula
P = pessimistic
M= most likely
O= optimistic

Triangular: (p+m+o)/e

Beta: (p+ 4m + o)/y

25
Q

Bottom up estimating

A

Combining the lower level costs of the WBS

26
Q

Sequence Activities outputs

A

Project schedule network diagrams

Project documents > activity attributes, activity list, assumption log, milestone list

27
Define Activities Process
Planning Identify and document specific actions that will produce the deliverables Goals: breakdown work packages into schedule activities > provide a basis for estimate, scheduling, executing, M&Cwork
28
Develop Schedule Process
Planning Create a schedule - analysis I’d activity sequence, Durations, resource requirements and schedule constraints Goal: planned dates to complete activities Iterative - done all the time, check resources and duration estimates, baseline to track progress
29
Develop Schedule Inputs
PM Plan > Schedule man plan, scope baseline Project doc> activity attributes, activity list, assumption log, Basis of estimates, duration estimates, LL, milestone list, project schedule network diagram, proj team assignments, resource calendars, resource requirements , risk register Agreements EEF/OPA
30
Develop Schedule T/T
``` Schedule network analysis Critical path method Resource optimization Dat analysis - what if scenarios - simulation Leads and lags Schedule compression PMIS Agile release planning ```
31
Develop Schedule Outputs
``` Schedule baseline Project schedule Schedule data Project calendars Change request Proj management plan updates - schedule management plan - cost baseline Project document updates - activity attributes - assumption log - duration estimates - LL - resources requirements - risk register ```
32
Control Schedule Process
Monitor: update the schedule, manage changes to the baseline goal: verify actual vs. planned, maintain the baseline Done many times throughout life of the project
33
Control schedule: integrated change control
``` Assess current status Control factors that create change Review schedule reserves Has the schedule changed? Manage changes ```
34
Control Schedule inputs
``` . Proj management plan - schedule man plan - schedule baseline - Scope baseline - resource calendars - schedule data Work performance data OPA ```
35
Control schedule - agile approach
Work delivered vs estimates of work complete Retrospectives Update priorities Velocity (how fast the team is working on the feature)
36
Control Schedule T/T
``` Data analysis Critical path method PMIS Resource optimization Leads and lags Schedule compression ```
37
Control Schedule Outputs
``` Work performance info Schedule forecasts Change requests PM plan updates >Schedule management plan >schedule baseline >cost baseline >performance measurement baseline Project documents updates >assumption log >basis of estimates >LL register >project schedule >resource calendars >risk register >schedule data ```
38
PDM
Precedence Diagramming Method AKA Activity on Node Schedule activity = rectangular box Node =Activity Arrow= Activity link, dependencies Lag time= period of time that separates or assigns a waiting period between 2 Activities Predecessor —> successor
39
Total Float
=LS-ES | =LF-EF
40
How to calculate float?
On critical path, there is NO float ( that’s what makes it the critical path) LS-ES=float