16. Communication Management (Knowledge Area 7) Flashcards
interactive communication
= multidirectional exchange between the sender and receiver
push communication
Project communications management is about ____.
preventing misunderstandings and miscommunications.
The project manager has decided that he will send the project status reports to the stakeholders using emails and memos. The stakeholders will not have to request any of the information; the project manager will just send it to them.
What communication method does this illustrate?
push communication
= when information is sent directly to the recipient
pull communication
= sender acquires the information at his or her own time using things such as a web portal
During project communications the receiver is having difficulty understanding the message. Which of the following can cause a message not to be understood by the receiver?
noise
The project manager has reviewed the stakeholder register and has concluded that there are 17 stakeholders on the project. After speaking with a few of them, he added four more stakeholders. How many communication channels are there currently on the project?
communications formula is N(N-1)/2.
Replacing N with 21 stakeholders currently will give you 21(21-1)/2 = 210.
The project manager is working on a multinational project and has met with the company’s senior management during a private meeting to discuss the project’s performance. They have indicated that they are very happy with the progress and would like the meetings to be shorter next time.
What process best describes this scenario?
manage communications
Process: Manage Communications
Process that ensures the timely and appropriate collection, creation, management, and disposition of project information
What is it called when a project manager builds a consensus and overcomes obstacles when managing a group?
facilitation = building consensus and overcoming obstacles
The project manager would like the team to actively listen during project meetings. How would the project manager know if active listening is taking place?
acknowledging, clarifying and confirming information
When conducting the process of manage communication what does the project manager circulate to the stakeholders throughout the process?
Work Performance Reports (aka Status Reports or Progress Reports) as specified in the communication management plan.
The project manager is giving a presentation to a large group of senior stakeholders. The project manager knows that his communication skills make a big difference during the presentation.
What type of communication skills are gestures, tone of voice, and facial expressions?
non-verbal
The project manager has collected the work performance data and has created the work performance report. The project manager distributes this status report according to the communication management plan.
What tool best describes this?
project reporting
Tool: Project Reporting
Tool that is used used to manage communication to collect and distribute project information.