13. Cost Management (Knowledge Area 4) Flashcards
three-point estimating
uses the PERT formula and may or may not be accurate
analogous estimating
a quick estimate that is based on previous projects
management reserves
cost baseline, plus the management reserves.
CPI
cost performance index = measurement of the cost efficiency of the budgeted resources
1 = project on budget
<1= project over budget
contingency reserves
part of the cost baseline
basis of the estimates
will document the confidence level of an estimate
cost aggregation
take the work packages and aggregate their individual cost to find the entire project budget
bottom-up estimating
when work packages are broken down and then rolled back up to form an overall cost estimate
can lead to a very precise estimate, although it requires the most amount of work.
management reserves
added to the cost baseline in case the project exceeds its budget
usually added by the company’s management and is not under the manager’s control
cost baseline
cost estimates
include the cost for labor, materials, equipment, services, and facilities
DO NOT include the operational costs of the product, since those costs cover operations and not a project
PV
Planned Value
EV
Earned Value
BAC
Budget at Completion
AC
Actual Cost
CPI
Cost Performance Index
CV
Cost Variance
SV
Shedule Variance
ETC
Estimate to Completion
EAC
Estimate at Completion
Estimate To Completion
(ETC) Forecasting the amount that will be needed to complete the current project based on the current performance
SPI
Schedule Performance Index