12. Schedule Management (Knowledge Area 3) Flashcards

1
Q

iteration burndown chart

A

shows the work that remains to be completed in the iteration backlog

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

WBS

A

Work Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

precedence diagramming method

A

used to construct the project schedule network diagram showing the dependencies between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

fast tracking

A

a schedule compression technique in which activities are generally done in parallel

This technique generally increases the risk on the project but may not increase costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

“start to start” relationship

A

when a successor activity cannot start until the predecessor activity has started. This means that they both generally started the same time, but they may not finish at the same time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

mandatory dependencies

A

one activity must be done in order for another activity to start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

activity attributes

A

can be used to identify the place where the work is to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

critical path method

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

rolling wave planning

A

planning technique in which future work is decomposed as the work gets closer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

crashing

A

adding more resources to the project to finish it faster; will increase costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

contingency reserve

A

unknown and is usually added to the project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

management reserve

A

an unknown-unknown and not added to the project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

basis of estimates

A

indicates the range of possible estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

discretionary dependencies

A

the sequence of activities does not necessarily have to be done in that particular order, but is usually at the discretion of the person doing the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

analogous estimating

A

based on historical information, generally from previous projects that were very similar; leads to a quick estimate, but may not be very accurate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

expert judgment (for scheduling)

A

using subject matter experts and trend analysis to see whether the project is staying on or off schedule

17
Q

lead

A

An overlap of work on a project

18
Q

lag

A

A delay between activities.

19
Q

external dependency

A

when the work is outside of the project team’s control, such as getting a permit

20
Q

schedule management plan

A

describes how schedule will be planned, developed, managed, executed, and controlled throughout the project,

as well as the level of accuracy, reporting formats, and schedule model

21
Q

decomposition

A

breaks down the deliverables and work packages into activities;

best done when the team members are involved, since they are considered subject matter experts and will generally lead to more accurate results;

should be done throughout the project as more work is done and understood

22
Q

The WBS is part of the ___.

A

scope baseline

23
Q

What type of activities have a duration of zero.

A

Milestones have zero duration because they represent a significant point or event on the project

24
Q

In developing the schedule management plan which tool will the project manager use?

A

data analysis tool

25
Q

What is a series of formulas that will tell you the status update on the project

A

earned value analysis

26
Q

While working on an agile project, what can the project manager do in order to track the work that remains to be completed on the project?

A

iteration burndown chart

27
Q

What identifies the working days and shifts that the project will follow?

A

project calendar

28
Q

Which method is used to construct a schedule in which activities are represented by nodes and are graphically linked?

A

precedence diagramming method

29
Q

While conducting the process of define activities, a few of the team members have decided to use the lesson learned repository from previous projects.

Which of the following input describes this lesson learned repository?

A

organizational process assets

30
Q

While getting ready to manage the project schedule, the project manager would like to document how accurate the schedule must be and what model the team will use to create the schedule.

What document would have this information?

A

schedule management plan

= will describe how the schedule will be planned, developed, managed, executed, and controlled throughout the project, as well as the level of accuracy, reporting formats, and schedule model

31
Q

The project team has embarked on a very complex software development project and is currently having a difficult time decomposing work packages that will be done later; they have decided to decompose these work packages as they get closer to the work. What technique best represents the scenario?

A

Rolling wave planning

= planning technique in which future work is decomposed as the work gets closer

32
Q

The project team has completed all duration estimates for the activities on the project and has indicated that their estimates should be with in a -10 to +10% range.

Where should the project team store this range?

A

Basis of estimates

33
Q

While estimating the duration of activities on the project, the project team has decided to base most of their estimates on historical data from a project they completed a few months ago that is very similar to the current project. This would allow them to complete the estimate fairly quickly.

What technique best illustrates this scenario?

A

analogous estimating

34
Q

While working on a complex software development project, the project team has added an additional month to the project schedule due to the uncertainty of the work getting done.

What type of reserve does this represent?

A

contingency reserve = associated with a known-unknown and is usually added to the project management plan

35
Q

The project manager is constructing the project schedule and would like to know the minimum duration needed to complete the project.

What method can he used to determine the minimum duration?

A

critical path method

= used to estimate the minimum project duration and determine the amount of schedule flexibility