12. Schedule Management (Knowledge Area 3) Flashcards
iteration burndown chart
shows the work that remains to be completed in the iteration backlog
WBS
Work Breakdown Structure
precedence diagramming method
used to construct the project schedule network diagram showing the dependencies between activities
fast tracking
a schedule compression technique in which activities are generally done in parallel
This technique generally increases the risk on the project but may not increase costs.
“start to start” relationship
when a successor activity cannot start until the predecessor activity has started. This means that they both generally started the same time, but they may not finish at the same time.
mandatory dependencies
one activity must be done in order for another activity to start
activity attributes
can be used to identify the place where the work is to be performed
critical path method
rolling wave planning
planning technique in which future work is decomposed as the work gets closer
crashing
adding more resources to the project to finish it faster; will increase costs
contingency reserve
unknown and is usually added to the project management plan
management reserve
an unknown-unknown and not added to the project management plan
basis of estimates
indicates the range of possible estimates
discretionary dependencies
the sequence of activities does not necessarily have to be done in that particular order, but is usually at the discretion of the person doing the work
analogous estimating
based on historical information, generally from previous projects that were very similar; leads to a quick estimate, but may not be very accurate