LG must respond to what in 120 days?
How long for LG to respond to business damages claim?
———-
Bus O has 180 days to claim, LG has 120 days to accept, reject, or counter.
What is triggered on LG by 120 days?
Timeline for LG to make offer of judgment.
———–
Start 120 days after Answer. End 20 days b/4 trial.
No later than
120 days after Def answers
OR
20 days before trial.
What is triggered on Def by 120 days?
only for an amount that is under $100,000,
Start 120 days after Answer. End 20 days b/4 trial.
No later than
120 days after Def answers
OR
20 days before trial.
What must be done 120 days post bond issue?
POST-ISSUE "F"our = "F"ees, 120 days. ----------- File 2004, naming any fees paid. ----------- 2003, gen info, is less stringent - asap aft issue.
Timeline to review development permits
166.033 Development permits and orders.—
DAYS ACTION
30 Rvw & advise if deficient
30 Appl corrects deficiency
120 Issue determination w/ findings
or
180 If reqs PH. Issue determination w/ finding
s
State the 4 timelines mixing 180, 120 & 90 day deadlines.
Bert Harris: O = 180 days to claim, LG = 90 days to resp. ---------- ED Business Dmgs: BO = 180 days to claim, LG = 120 days to resp. ----------- ED Offer of Jmt: 120 days aft Answer to 20 days before Trial. ----------- Dev. App: A) 30 + 30 = 60 B) (60 x 2) = 120 C) 120 + 60 = 180
s
What 4 things have a deadline of 120 days?
Hint:
1 = Finance
2 = E.D.
1 = Land Use (re: permits)
ED Business Dmgs:
O = 180 days to claim, LG = 120 days to resp.
———-
ED Offer of Jmt:
120 days aft Answer to 20 days before Trial.
———–
Dev. App. deadline to issue decision w/ findings.
A) 30 + 30 = 60
B) (60 x 2) = 120
C) 120 + 60 = 180
———–
30 days: Rvw & advise if deficient
30 days: Appl corrects deficiency
120 days: Issue decision w/ findings
or
180 days: Issued decision w/ findings IF REQS PH.
s
What 3 unrelated things have a deadline of 180 days?
Hint:
1 = ED
2 + 3 = Land Use
ED Business Dmgs: *Bus cd run 300 days!* BO = 180, LG = 120 ----------- Bert Harris: O = 180, LG = 90. ---------- Dev. App. , issue decision w/ findings w/ PH. ---- A) 30 + 30 = 60 B) (60 x 2) = 120 C) 120 + 60 = 180 ----------- 30 days: Rvw & advise if deficient 30 days: Appl corrects deficiency 120 days: Issue decision w/ findings or 180 days: Issued decision w/ findings IF REQS PH.
s
How remember which 3 unrelated items have a deadline of 180 days?
‘B’ert is very ‘B’usiness oriented but Bert has Better lobbyists.
Bus cd run 300 days!
———–
Bert…………………..: O = 180, LG = 90
Bus Dmgs [ED]: BO = 180, LG = 120.
Permits: Issue decision w/ findings w/ PH.
s
How remember which 4 items have a deadline of 120 days?
FINANCE - file post 2004 [conduit + antic]
———–
PERMIT - w/o hrg.
———–
ED Business Dmgs:
presuit: BO = 180, LG = 120
———-
ED Offer of Jmt:
post suit: 120 days aft Answer to 20 days before Trial.
s
State 5 items w/ 120 deadline.
s
1) File 2004 aft bond.
2) Permit: 30-30-120-180.
3) E.D. Bus Dmg: 180 - 120.
4) Offer Jmt in ED 120 aft Ans, 20 b/4 trial.
5) ADA pub. serv. give 60, up to 120 by agreement.
#s ----------- What does 120 have to do w/ ADA?
#s ----------- Public services. ----------- Put LG on notice, has 60 days to correct. May extend to 120 by agreement.