TWELVE - Procurement Flashcards

1
Q

What are contracts?

A

Can be written or verbal, typically created with an external entity, and involve an exchange of goods or services for some type of compensation. The contract forms the legal relationship, is mutually binding, and provides a framework for how a failure on one side will be addressed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is an agreement?

A

Broader term that encompasses documents or communications that outline internal or external relationships and their intentions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the relationship between agreement and contracts?

A

A contract is an agreement, but an agreement is not necessarily a contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are examples of agreements?

A

The charter and PM Plans, memos of intent, letters of agreement, emails, and verbal agreements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is a procurement strategy?

A

A plan for how each contract will be managed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What questions does the Plan Procurement Management process answer?

A

How will make-or-buy analysis be performed?
What goods/services do we need to buy?
How will we purchase them?
Who are potential sellers to consider?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does plan procurement management process (P) involve?

A

Performing make-or-buy analysis
Creating a procurement management plan;
Creating a procurement strategy for each procurement;
Creating a procurement statement of work for each procurement;
Selecting the appropriate contract type for each procurement;
Creating bid documents;
Determining source selection criteria;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is procurement management plan?

A

Plan for the overall procurement process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the Inputs to Plan Procurement Management?

A

Project Charter;
Business Documents - Benefits Management Plan, Business Case;
PM Plan - scope, quality, resource;
Project Documents - Milestone list, requirements traceability matrix, schedule, procurements already in place, project team assignments, requirements documentation, resource requirements, risk register, stakeholder register;
EEFs;
OPAs - Types of Contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the benefits management plan?

A

Lists the benefits of the project and details when they are to be delivered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the business case?

A

Outlines the reason the project was undertaken.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Project Team Assignments in Plan Procurement Management?

A

Includes info on who can help the PM with procurement planning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Requirements Documentation in Plan Procurement Management?

A

PM will find scope-related requirements that will help define required end services, products, or results provided by a seller. Also includes requirements for compliance, safety, communications, PM practices, reporting, quality, and risk management that are likely to be used in procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are EEFs relating to procurement?

A

Market conditions, services available to be purchased, and the culture and structures surrounding organizations approach to procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What factors will determine which type of procurement contract should be used?

A

What is being purchased;
Completeness of the statement of work;
Level of effort and expertise the buyer can devout to managing the seller;
Whether the buyer wants to offer the seller incentives;
The marketplace or economy;
Industry standards for type of contract to be used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the three broad categories of contracts?

A

Fixed price, Time and Material, Cost-reimbursable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Fixed Price

A

Used when well defined specifications or requirements. Need a clearly defined statement of work and competing bids will give you a fair price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

who has the least cost risk in fixed price?

A

The buyer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the types of fixed price contracts?

A
Firm fixed price;
Fixed price incentive fee;
Fixed price award fee;
Fixed price with economic price adjustments
Purchase orders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Fixed Price Incentive Fee

A

Financial incentives can be adjusted based on seller meeting specified performance criteria (getting work done faster, cheaper, or better). Final price is calculated using a formula based on the relationship of final negotiated costs to the total target cost (bonus each month project is finished early)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Fixed Price Award Fee

A

Buyer pays fixed price plus an award amount (bonus) based on performance. (bonus each month project is finished early with a maximum award of …..)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Fixed price with economic price adjustments

A

If contract will cover multiyear period, may be uncertainties about future economic conditions. (A price increase will be allowed in year 2 based on US consumer price index report for year 1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Purchase Order

A

Simplest type of fixed price contract. Normally signed by one party (unilateral) used for simply commodity procurements. Become contracts when the buyer accepts the terms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Time and Material

A

Buyer pays on a per-hour or per-item basis. Frequently used for service efforts in which level of effort cannot be defined when contract is awarded. Elements of fixed price (ie fixed price per hour) and cost reimbursable contract (in material costs and that total cost is unkown). Normally simpler terms and conditions.
Best used for work valued at small dollar amounts and lasts short duration of time.
Not to exceed clause is common.
Medium amount of risk to buyer
($100/hr plus expenses and materials at cost)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Cost Reimbursable

A

Used when exact scope of work is uncertain and therefore costs cannot be estimated accurately enough to use fixed price. The buyer to pay the seller allowable incurred costs to extent prescribed in the contract.
Normally include additional fee or award amount to allow seller to profit.
The buyer has the most cost risk because total costs are unknown
Seller provides an estimate that is not binding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What are the types of cost reimbursable contracts?

A

Cost, cost plus fixed fee, cost plus incentive fee, cost plus award fee, cost plus percentage of cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Cost contract

A

Seller receives no fee (profit). Typically used by nonprofit organizations. Seller is reimbursed but does not make profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Cost Plus Fixed Fee

A

Provides payment to the seller of actual costs plus a negotiated fee that is fixed before the work begins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Cost plus incentive Fee

A

Seller to be paid actual costs plus a fee that will be adjusted based on whether specific performance objectives are met.
An original estimate of the total cost is made (target cost)
A fee for the work is determined (target fee)
The seller gets a percentage of the savings if actual costs are less than target cost
If actual costs are more than target costs, the seller shares the cost overrun with the buyer. Ratio is often 80% to buyer and 20% to seller.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Cost plus Award Fee

A

Buyer pays all costs and a base fee plus an award amount based on performance. The incentive is a potential award, and there is no possibility of penalty. The award amount is determined in advance and apportioned depending on performance.
A type of incentive contract.
Will have a maximum award value
Cost plus a base fee plus award for meeting performance criteria. Maximum award value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Cost plus Fee or Cost plus percentage of costs

A

Buyer pays for all costs plus a percentage of costs as a fee.
Bad for buyers everywhere and not allowed in federal acquisitions.
There is no incentive to control costs and seller will choose higher costs because they will make more profit.
Buyer needs to carefully monitor and control all invoices
Cost plus 10% of costs as fee

32
Q

What are the tools and techniques of Plan Procurement Management?

A

Make-or-Buy Analysis

Source Selection Analysis

33
Q

What is source selection analysis?

A

Determining the criteria that will be used to select a seller. Project constraints are analyzed.

34
Q

What are the outputs to Plan Procurement Management?

A

Info on qualified sellers - OPA update,
Project Document Updates - LL, milestone list, requirements documentation, requirements traceability matrix

PM Plan;
Make-Or-Buy Decisions;
Procurement Strategy;
Procurement Statement of Work;
Source Selection Criteria;
Independent Cost Estimates;
Bid Documents - RFP, Invitation for Bid, RFQ, RFI
Change Requests
35
Q

What are the 3 basic components of the procurement strategy?

A

How goods/services will be delivered to the buyer;
What type of contract will be used;
How the procurement will be carried out throughout each phase

36
Q

What are types of bid documents?

A

RFP, Invitation for Bid, RFQ, RFI

37
Q

What is Invitation for Bid?

A

Requests a total price to do the work.

A form of RFP where the work described is detailed enough for bidders to determine total price.

38
Q

What is an RFQ?

A

Requests a price quote per item, hour, meter, or other unit of measure

39
Q

What is RFI?

A

Purpose is to gather info, ie determine which companies are qualified, what work is possible for later inclusions into RFP/IFB documents.

40
Q

What is a Standard Contract?

A

The contract terms and conditions in a standard format that is used over and over again on similar procurements

41
Q

What are Special Provisions (Special Conditions)?

A

PM must be able to determine when additions, changes, or deletions from standard provisions are required. Can be a result of risk analysis, requirements of project, type of project, admin, legal, or business requirements

42
Q

What is Acceptance in Terms and Conditions?

A

How the PM will know if work is acceptable

43
Q

What is Agent in Terms and Conditions?

A

Authorized representative of each party

44
Q

What is Assignment in Terms and Conditions?

A

Circumstances under which one party can assign its rights or obligations under the contract to another

45
Q

What are Bonds in Terms and Conditions?

A

Payment of performance bonds that must be purchased

46
Q

What is Indemnification (Liability) in Terms and Conditions?

A

Who is liable for personal injury, damage, or accidents

47
Q

What is Intellectual Property in Terms and Conditions?

A

Who owns the intellectual property developed in a project

48
Q

What is Liquidated Damages in Terms and Conditions?

A

Estimated damages for specific defaults

49
Q

What is Material Breach in Terms and Conditions?

A

Kind of breach so large that it may not be possible to complete the work under this contract

50
Q

What is Risk of Loss in Terms and Conditions?

A

Risk between parties to a contract in the event goods or services are lost or destroyed during the performance of a contract

51
Q

What does Time is of the Essence mean in Terms and Conditions?

A

Means delivery dates are strictly binding. Any delay will be a material breach

52
Q

What are Waivers in Terms and Conditions?

A

Saying that rights under a contract may not be waived or modified other than by agreement by all parties

53
Q

What is Work for Hire in Terms and Conditions?

A

The work provided under contract will be owned by the buyer

54
Q

What does Conduct Procurements (E) involve?

A

Involves getting bid documents, including procurement statement of work and other documents, to prospective sellers, answering the sellers’ questions, and receiving and evaluating responses.
The PM must also select a seller using the source selection criteria, and then negotiate the contract

55
Q

What are the inputs to Conduct Procurements?

A

Procurement Management Plan;
PM Plan;
LL - previous experience with sellers;
Procurement Documentation - bid documents
OPA, advertising - determine who to send bid documents to;

Seller Proposal (Price Quote or Bid);
Independent Cost Estimates
56
Q

What is the response to RFP, RFQ, and IFB respectivly

A

Proposal, Quote, Bid

57
Q

What are Tools and Techniques of Conduct Procurements?

A

Advertising, Bidder Conferences, Proposal Evaluation, Negotiations

58
Q

What are Bidder Conferences?

A

To ensure all sellers’ questions are answered, buyer may invite the sellers to attend a meeting called a bidder conference (or contractor conference).
Questions asked and the responses are documented and sent to all prospective bidders and also added as addenda.

59
Q

What must the PM watch out for in a Bidder conference?

A

Collusion,
sellers not asking questions in front of the competition,
making sure all questions and answers are put in writing and issued to all as addenda

60
Q

What are the objectives of the negotiations?

A

To obtain a fair and reasonable price;

Develop a good relationship between the buyer and seller

61
Q

What are the main items to negotiate?

A

Scope, Schedule, Cost negotiated in this order

62
Q

What are the outputs of conduct procurements?

A
Procurement Contract is Awarded;
Agreements (Contracts);
Selected Sellers;
Change Requests
PM Plan and Project Document Updates - quality or communications management, resource calendars, requirements traceability matrix, risk register, pre-approved seller list
63
Q

What is the purpose of a contract?

A

To define roles and responsibilities;
To make things legally binding;
To mitigate or allocate risk

64
Q

What do you need to have a Legal Contract?

A

An offer;
Acceptance;
Consideration (transfer of something of value);
Legal capacity (separate legal parties that are legally competent);
Legal purpose (can’t be contract of illegal services/products);

65
Q

Change requests in project executing

A

Seller who isn’t performing

66
Q

What does Control Procurements involve?

A

Involves managing the legal relationship between the buyer and seller, ensuring both parties perform as required by the contract, and closing each contract when it is completed or terminated.
The seller is focused on completing the work while the buyer is focused on measuring the performance of the seller

67
Q

What points should you understand regarding control procurments?

A

What the PM should be doing at any point in time;
What problems and issues to watch out for that may affect the management of the project under each contract type;
That all work and legal requirements in the contract must be accomplished;
That the PM must uphold all parts of the contract

68
Q

What are the inputs to control procurements?

A

Procurement Management Plan;
LL;
Approved change requests are implemented in this process;
Milestone list and schedule, scope, and cost baselines;
Requirements documentation;
Quality reports;
Work performance data from direct and manage project work;
EEFs - contract change control system;

69
Q

What are the tools and techniques of control procurements?

A

Performance reviews - to ensure seller is performing;
Inspections - ie walk-throughs of work site;
Audits - by team of both buyer and seller;
Earned Value Analysis - variances from performance baseline;
Trend Analysis - is performance getting better/worse;
Claims Administration;

70
Q

What can Trend Analysis develop?

A

Forecast estimates and estimate at completion

71
Q

What is Claims Administration?

A

Seller submitting a claim against the buyer. A claim is an assertion that the buyer did something that has hurt the seller, and seller is asking for compensation. Seller initiated change request.

Claims are addressed through contract change control system.

72
Q

What are the outputs of Control Procurements?

A

Change Requests
Procurement Documentation Updates
Closed Procurements

73
Q

What are constructive changes?

A

Occur when the buyer limits the sellers ability to perform the work according to the contract

74
Q

Procurement Documents Update?

A

Thorough records relating to the contract must be kept (ie communications, etc). Records management system should be used due to the legal nature of a contract

75
Q

What does closing procurements involve?

A

Tying up loose ends, verifying that all work and deliverables are accepted, finalizing open claims, paying holdback. Provide formal notice contract is closed. Warranties may still occur after a contract is closed.

76
Q

When are procurements closed?

A

When a contract is complete, or terminated