SEVEN - Cost Management Flashcards

1
Q

What is Value Analysis?

A

AKA Value Engineering. Its focus is on finding a less costly way to do the work. Answer’s the question: How can we decrease cost while maintaining same scope/performance?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Cost Risk?

A

Involves cost, risk, and procurement management. Means cost-related risk.
Example: Who has the cost-risk in a fixed price contract? The seller.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does Plan Cost Management (P) involve?

A

Identifying how to plan (including estimating and budgeting), manage, and monitor and control project costs (including resource costs). Answers “How will i go about planning cost for the project” and “How will I manage the project cost to the cost baseline, control costs, and manage cost variances.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are some inputs to Plan Cost Management?

A

Project charter, OPAs/lessons learned,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the outputs to Plan Cost Management (P)?

A

Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What may the Cost Management Plan include?

A

Specifications for how estimates should be stated (currency);
Levels of accuracy and precision;
Approved estimating techniques;
Reporting formats to be used;
Rules for measuring cost performance;
Whether indirect (overhead) costs will be included;
Guidelines for establishing a cost baseline;
Control thresholds;
Cost change control procedures;
Information on control accounts;
Funding decisions;
Methods for documenting costs;
Roles and responsibilities for various cost activities;
Guidelines for dealing with potential fluctuations in resource costs and exchange rates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does Estimating Costs (P) involve?

A

Involves creating cost estimates for all project activities and resources required to complete them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what costs does Estimating Costs includes?

A
Includes cost directly related with the project, such as labour, equipment, materials, training, as well as:
Costs of quality efforts
Costs of risk efforts
Costs of the PM's time
Costs of the PM activities
Overhead/indirect costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the two types of costs required to know for the exam?

A

Direct and indirect costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are direct costs?

A

Costs directly attributed to the work on the project. Examples such as team’s wages, travel, material, resources, etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are indirect costs?

A

They are overhead items or costs incurred for the benefit of more than one project. Such as taxes, janitorial services, rent, etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the inputs to Estimate Costs (P)?

A

PM Plan - Cost, quality, scope
Project Documents - LL register, Schedule, Resource Requirements, Risk Register
OPAs
EEFs - exchange rates, inflation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the Tools and Techniques of Estimate Costs?

A

Data Analysis - Alternatives, Reserve, & Cost of Quality Analysis
PMIS - Estimating spreadsheets and software
Decision Making, Estimate Ranges, and the Estimating techniques same as schedule estimating (three-point, analogous, etc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Cost of Quality?

A

Cost of work added to the project to accommodate quality efforts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Estimate ranges?

A

Organizations have standard ranges for estimating. These ranges tell how much time and effort need to go into estimating to make sure the actual cost is within the range of the estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Rough Order of Magnitude (ROM) estimate?

A

This type of estimate is usually made during project initiating and a typical range is -25 to +75%. This range can vary depending on how much is known about the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is Budget Estimate?

A

Has a range of -10 to +25%. It is best practice to narrow the range of the estimate from ROM before you begin iterating the plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is Definitive Estimate?

A

As project planning progresses, the estimate will be even more refined to +/- 10% or -5 to +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the Output to Estimate Costs (P)?

A

This process results in cost estimates, and an explanation of how those estimates were derived (which is known as the basis of estimates). Also results in changes or updates to project documents - risk register, assumption log, LL register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is involved in the Determine Budget (P) process?

A

The PM calculates the total cost of the project, resulting in the calculation of the budget and the cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the cost baseline?

A

The portion of the budget that the PM will have control over.

22
Q

What are the Inputs to Determine Budget (P)?

A

Business case and benefits management plan,
PM Plan - resource, cost, scope
project documents - schedule, risk register
OPAs
Cost Estimates and Basis of Estimates
Agreements regarding purchase of services or products

23
Q

What are the Tools and Techniques of Determine Budget?

A

Expert judgement, cost aggregation, reserve analysis, historical info review, funding limit reconciliation, and financing

24
Q

What does the cost baseline include?

A

Includes contingency reserves and represents the funds the PM is authorized to manage and control

25
Q

What is the cost budget?

A

It is the cost baseline plus the management reserve

26
Q

How do you create a budget? What is this process called?

A

Activity cost estimates are rolled up into work package estimates which is then rolled up into control account costs, and finally to project costs. this process is called cost aggregation. Contingency reserves are then added to create cost baseline. Finally, management reserves are added

27
Q

What does the PM need to do once the cost budget is created?

A

Compare the numbers to expert judgement, historical information, etc and investigate and justify any significant differences between project estimates and the reference data. PM also has to review cost constraints in the charter and perform another reconciliation. If the project estimate exceeds the cost constraints, the PM will need to propose options to decrease costs and meet with management

28
Q

Cash flow

A

The cost baseline is time-phased and cash flow must be considered for when project funding will be available, and when it needs to be spent

29
Q

What are outputs to Determine Budget?

A

Cost baseline including all funding requirements

Updates to project documents - cost estimates, risk register, project schedule

30
Q

What are the inputs to Control Cost (M&C)?

A

Work performance data - provides the info about project progress that needs to be analyzed to determine if changes need to be requested

PM Plan, LL register, project funding requirements, OPAs

31
Q

What are Tools and Techniques to Control Cost?

A

Data analysis: Earned Value Analysis, Reserve, Variance, and Trend Analysis

32
Q

What is EVM (Earned Value Management)

A

Used in performance reviews to measure project performance against scope, schedule, and cost baselines. EVM indicates if there are potential variances from the performance measurement baseline.

33
Q

What is the performance measurement baseline?

A

Cost, Scope, and Schedule Baselines

34
Q

What is PV?

A

Planned Value - As of today, what is the estimated value of the work planned to be done?

35
Q

What is EV?

A

Earned Value - As of today, what is the estimated value of the work actually done?

36
Q

What is AC?

A

Actual Cost - As of today, what is the actual cost incurred for the work accomplished?

37
Q

What is BAC?

A

Budget at Completion - Cost baseline. How much did we budget for the total project effort?

38
Q

What is EAC?

A

Estimate at Completion - What do we currently expect the total project to cost? A forecast

39
Q

What is ETC?

A

Estimate to Complete - From this point on, how much more do we expect it to cost to finish the project? A forecast

40
Q

What is VAC?

A

Variance at Completion - As of today, how much over or under budget do we expect to be at the end of the project?

41
Q

What is the interpretation of CV?

A

Negative is over budget, positive is under budget

42
Q

What is the interpretation of SV?

A

Negative is behind schedule, positive is ahead of schedule

43
Q

What is the interpretation of CPI?

A

We are getting $___ worth of work out of every $1 spent. Funds are or are not being used efficiently. Greater than is good (cost underrun) less than one is bad (cost overrun)

44
Q

What is the interpretation of SPI?

A

We are progressing at __ percent of the rate originally planned. Greater than one is good (more work being completed than planned). Less than one is bad (;es work was done than planned)

45
Q

What is the interpretation of EAC?

A

Calculates actual cost to date plus remaining budget. AC plus the remaining value of work to perform

46
Q

What is the interpretation of ETC?

A

Calculates the total project cost as of today minus what has been spent to date

47
Q

What is the interpretation of VAC?

A

How much over or under budget will we be at the end of the project

48
Q

What is the interpretation of Time Variance (TV)?

A

Calculates schedule variance using earned schedule (ES) and actual time (AT)

49
Q

What does variance analysis include?

A

Involves identifying the causes of variances and determining what to do about them

50
Q

What is Trend Analysis

A

Involves at least two types of tools - charts and forecasting. Involves forecasting the final cost of the project using EVM metrics to determine likelihood of meeting agreed-upon end date/costs

51
Q

What are the outputs to Control Cost?

A

Work performance info, Cost Forecasts, Change Requests, PM Plan and project document updates.

The control cost process provides measurements that indicate how the work is progressing.