Time Mgmt Input/Output Definitions Flashcards
Activity Attributes
In parallel to the WBS dictionary, the activity attributes gives information about the activities in the activity list, such as the resources they would require, who is responsible for doing them, etc.
Activity Duration Estimates
These are quantitative assessments of the likely number of work periods that will be required to complete an activity. Duration estimates do not include any lags. The estimates will typically be presented with some sort of range e.g. the project will take 2 weeks, +2 Days.
Activity List
A list of schedule activities that shows the description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.
Activity Resource Requirements
This is an output of the process 6.3 Estimate Activity Resources. This contains the preliminary requirements for the people needed on the project. This is elaborated as part of this process.
Change Requests
If during the course of executing the project, issues develop that require a change to the scope, budget, or schedule, or quality, then change requests are developed. Note that the change requests are made in the Executing Progress Group, but are evaluated and either accepted or rejected as part of the Monitoring & Controlling Progress Group. If they are accepted, these changes get fed into the Executing Progress Group once again.
EEF
This is the “company culture”, or factors that are external to the project but which influence the project’s success. These can include the company databases and, in particular, the project management software used by the company. Think of them as “soft copy” (software and the company culture or “unwritten rules” that govern how work is done).
Milestone List
This identifies all milestones, whether they are required by contract, or optional based on the organization’s desire to take opportunities to gauge the progress of the project.
OPA
Written procedures, policies, and guidelines that are used by the company to guide all operations, including projects. Lessons learned would be an important part of OPA. Think of the operational process assets as the “hard copy” (written procedures)
Project Document Updates
Any time there has been a change that will impact the project it must be documented and the stakeholder’s must be informed.
Project Management Plan
A formal, approved document that defines how the project is executed, monitored, and controlled. It will be composed of one or more subsidiary management plans and other planning documents.
Project Management Plan Updates
If the project management plan is changed or the performance baseline is changed, then updates to these are made.
Project Schedule
The project schedule contains information on required timelines or mandated deliverable dates. This can be in the form of a bar chart, project schedule network diagram, and/or a milestone chart.
Project Schedule Network Diagrams
This shows the activities as nodes in a diagram which connects them according to the logical relationships or dependencies between them.
Project Scope Statement
The project scope statement contains the following:
1.Project scope description
Characteristics of the product, service or result to be produced by the project.
2.Product acceptance criteria
The criteria for acceptance of the completed product, service, or result.
3.Project deliverables
The product, service, or result of the project plus reports of the management of the project.
4.Project exclusions
What is agreed to be out of scope for the project.
5.Project constraints
Constraints on the project scope, predetermined budget, imposed completion and/or schedule milestone dates,
6.Project assumptions
Assumptions associated with the project scope.
Resource Breakdown Structure
Hierarchical structure of identified resources by category (labor, material, equipment, and supplies) and type (skill level, grade level).